The Executive - Individual Executive Decisions decided this item on Thursday 28 May 2020. Below is the council's own wording, with the papers it was decided on.
That the summary of progress of the restoration works and likely opening timetable for the Buxton Crescent Hotel, in particular in light of the impacts of COVID-19. ANY DECLARATION OF INTEREST None A NOTE OF ANY DISPENSATION RECEIVED, IF ANY None
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Report to The Executive - Individual Executive Decisions
Recommendation
2.1The Leader is asked to note the update on the progress of the Crescent project and outstanding issue around the leases and legal arrangements for the project.
Executive summary
3.1The Council has been working with partners over a number of years to restore the Crescent, Natural Baths and Pump Room to deliver a spa hotel and visitor attraction for Buxton. The project is very nearly complete and whilst scheduled opening of the hotel had been targeted for May / June this year, the COVID-19 pandemic has resulted in inevitable delays to the programme.
3.2Internal and external works to the Hotel are virtually complete. The contractors Vinci have remained on site to work through snagging items and any outstanding works that can be undertaken safely, and within Government guidelines on distancing. This has restricted the nature of the tasks that can be undertaken. However the Hotel would be in a position to open relatively quickly, following a decision taken to do so. 3.3 The Council’s legal consultants, Gowling WLG (UK) continue to provide advice on the leases. A number of issues are being worked through in order to reach a position whereby the leases can be completed. These issues include agreeing a Landlords Management Plan, finalising a Public Access Policy, approving works to the Pavilion Garden car park, and ensuring satisfactory condition of the Pump Room.
3.4There is no current opening date proposed for the Hotel. The date will be determined by a number of key factors, including when the government’s five tests are met enabling an ease of the lockdown restrictions, the social distancing requirements that will remain at that point, and the Hotel’s assessment of the state of the travel and leisure market.
4. How this report links to Corporate Priorities
4.1Opening of the Buxton Crescent Hotel will have implications for:
Aim Three: To protect and create jobs by supporting economic growth, development and regeneration
Alternative options
5.1Option 1 (recommended) – that Councillors note the detail of the progress update. There are no further options.
Neil Rodgers Executive Director (Place)
Web Links and Contact details Background Papers https://buxtoncrescent.com/ Joanna Bagnall
6.1The project involves the renovation and restoration of the Crescent, Natural Baths, Pump Room and the Old Bakery.
6.2The Crescent was built between 1780 and 1789. It was the centrepiece of the Fifth Duke of Devonshire’s plans to establish a fashionable Georgian spa town in Buxton. The Crescent is a Grade I listed building and is one of the most architecturally significant buildings in the country. 6.3 The Natural Baths were built in 1853. The building sits over Buxton’s thermal natural mineral water spring. The Pump Room, where the public went to “take the waters”, was built in 1894. Both are Grade II listed buildings.
6.4The Old Bakery is a small building (unlisted) behind the Crescent on George Street. Its freehold is owned by High Peak Borough Council, as is the car park in Pavilion Gardens, part of which is to be used for hotel parking.
Scope of the project
6.5The project includes provision of the following key elements:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Executive - Individual Executive Decisions at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1...
Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.