Resolved
That the revised attached as Appendix 1 to the report be approved.
Audit & Regulatory Committee approved this item on Wednesday 10 February 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the revised attached as Appendix 1 to the report be approved.
2.1That members approve the revised Risk Management Strategy as detailed at Appendix 1.
3.1The Alliance Risk Management Strategy is reviewed every two years in order to ensure the Council’s approach reflects changing circumstances.
3.2The 2021 strategy review has been informed by a number of considerations, including:
A voluntary external review of our operational risk management arrangements by strategic risk engineers from our Insurance partner, Zurich Municipal Findings of internal audit and other reviews Financial challenges facing the Council over the course of its Medium Term Financial Plan and how this might affect our tolerance to financial risk Consultation with senior managers and the corporate Risk Management Group Horizon-scanning for emerging risks within the public sector and more widely, as identified by the risk and insurance sectors.
4. How this report links to Corporate Priorities
4.1Risk Management is embedded across all service areas and therefore links to each of the Council’s Corporate Plan aims.
5.1The committee can approve the revised strategy or suggest amendments.
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998) None
6.2Workforce Employee wellbeing is identified as a new risk for inclusion within the strategic risk register
6.3Equality and Diversity/Equality Impact Assessment This report has been prepared in accordance with the Council's Diversity and Equality Policies
6.4Financial Considerations Effective Risk Management contributes to the Council’s financial objectives
6.5Legal None
6.6Sustainability Compliance with environmental regulatory frameworks are included as a risk within the council’s strategic risk register
6.7Internal and External Consultation Heads of Service have been consulted on the current risk tolerance thresholds through the Risk Management Group
6.8Risk Assessment Establishing the Council’s risk tolerance is central to delivering a successful Risk Management Strategy. ANDREW P STOKES Chief Executive
Background Papers Location Contact details Medium Term Financial Plan. Available on request Vanessa Higgins Global Risks Report 2021 – OD & Transformation, World Economic Forum. Ext 4057 Leek Zurich Risk Review – 2020. 7. Background 7.1 The Council’s Joint Risk Management Strategy was first adopted in December 2010. In line with the commitment given in the Strategy to undertake regular reviews, the Strategy is now in its eighth iteration.
8. 2021 Review
8.1The 2021 strategy review has been informed by the areas bulleted below, which are explored in more detail in the following paragraphs.
A voluntary external review of our operational risk management arrangements by strategic risk engineers from our Insurance partners, Zurich Findings of internal audit and other reviews relating to risk management Financial challenges facing the Council over the course of its Medium Term Financial Plan and how this might affect our tolerance to financial risk. Consultation with senior managers and the corporate Risk Management Group. Horizon-scanning for emerging risks within the public sector and more widely, as identified by the risk and insurance sectors.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
for Risk Management Strategy /17Appendix 1 | 225 KB | Download |
PDF |
Risk Management StrategyReport | 111 KB | DownloadRead as text |
Follow Audit & Regulatory Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2026 | To approve the Minutes of the previous meetingThat the minutes of the previous meeting held on 11 February 2026 be approved as a correct record. | Approved | Open |
| 2 Jun 2026 | High Peak Borough Council Audit Plan 2025 - 2026 (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Audit Progress and Sector Update Report (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Internal Audit Periodic Report February 2026 to May 2026That the Committee notes the progress information within the report. | Decided | Open |
| 2 Jun 2026 | Internal Audit CharterThat the Council’s Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.