CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
Development Control Committee, Monday 7 November 2022 at 1.30pm

HPK/2021/0707 - Land adjacent to Unit 18, Tongue Lane Industrial Estate, Dew Pond Lane, Fairfield, Buxton

Approved Planning 1 paper

Development Control Committee approved this item on Monday 7 November 2022. Below is the council's own wording, with the papers it was decided on.

Item23/44

Resolved

That the application be approved for the following reasons: a. The economic, regeneration and employment benefits the proposal would bring to the area outweighed the proposed reasons for refusal as set out in the report; b. Parking in accordance with the Local Plan parking standards could now be accommodated within the site; c. Members of the committee had viewed the highway in the area of the site and considered that displaced parking onto the public highway, if any, as a result of the poor layout would not jeopardise highway safety in this particular location where the carriageway width was 6.5m. Lack of Highways Authority objection in this regard was noted; d. Para 111 of the NPF states that ‘Development should only be prevented or refused on highways grounds if there would be an unacceptable impact on highway safety.’ Having considered the report, plans, verbal submissions and having viewed the site in person, on balance Members did not agree that this was the case here; e. The agreement of the applicant to ensure that a bankman is used to supervise the manoeuvring of HGVs accessing the site was noted and welcomed; 2. That authority be delegated to the Head of Development Services and Chair to determine the detailed wording of the reasons for approval including suitable conditions.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Development Control Committee

HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE

Date 7th November 2022

Application No: HPK/2021/0707 Location Land adjacent to Unit 18, Tongue Lane Industrial Estate, Dew Pond Lane, Fairfield, Buxton Proposal Erection of 3no. Business Units Applicant Pork Chop Ltd Agent Sammons Architectural Parish/ward Stone Bench Date registered 17th Dec 2021 If you have a question about this report please contact: James Stannard, Tel. 01298 28400 extension 4298, [email protected]

1. SUMMARY OF RECOMMENDATION

Refuse

1. REASON FOR COMMITTEE DETERMINATION

1.1This application has been brought before the Development Control Committee by Councillor Sloman on grounds of economic growth and disputes over parking provision.

1.2The application was deferred at the previous meeting of the Development Control Committee for further discussions on the highways issues and to enable a Members site visit to be undertaken.

2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS

2.1The application refers to a small parcel of land within the current confines of Unit 18, Tongue Lane Industrial Estate, which currently serves as off-street parking for this unit.

2.2Tongue Lane Industrial Estate is identified as a Primary Employment Zone which lies within the built-up area boundary of Buxton, and home to a variety of industrial and commercial premises.

2.3The unit currently accommodates the ‘World of Power’ Warehouse which consists of a warehouse and ancillary trade shop and office facilities. The warehouse has a total floor area of 485 square meters. When considering the ancillary trade and office space, the total floor area of the unit spans a depth of approximately 34m and a width of 23m (782 square metres in total).

1 2.4 Unit 18 is connected to a separate industrial unit (Unit 18A) which was sub-divided following the granting of planning permission in 2008, and is currently occupied by ‘Plasma Biotal Ltd’, a company that provide a specialist service to industry using thermal spraying technology to apply metal, ceramic and composite coatings to a wide range of components. This spans a total floor area of 492 square metres.

2.5The shared access for both units 18 and 18A is directly from Tongue Lane to the south west into a yard area which provides turning provision for HGV’s accessing the roller shutter doors within the existing warehouse.

2.6An extract of the approved Site Plan under HPK/2008/0616 for the sub- division of Unit 18 is below which shows the provision of a total of 24 no. spaces for both industrial units, which includes 4no. spaces immediately adjacent to Unit 18

2.7An extract of the approved Car Parking Plan under HPK/2010/0309 for the change of use of Unit 18A to a Gymnasium is shown below which shows (in light blue) 17no. spaces allocated to Unit

2 2.8 An extract of the approved Site Plan for the subsequent change of use of the Gymnasium back to an Industrial Unit under HPK/2015/0041 is shown below, which makes clear that 12no. spaces are allocated to Unit 18A with the remaining 12no. spaces allocated to Unit 18.

2.9Crucially, the approved Site Plan under HPK/2015/0041 shows that the area subject of this application includes a turning and manoeuvring area for HGV vehicles which would allow these large vehicles to enter and exit the site in a forward gear.

2.10Latest commentary from the applicant’s agent argues that whilst accepting that this area is lawfully allocated for parking and turning, the reality is that this has always been unachievable. The latest Existing Site Plan (Ref: 2021-2631-01A) shows the turning circle of a HGV which shows conflict with the existing car parking space. However, this is based on a full turn with no reversing within the site to access the existing roller shutter doors.

2.11The total of 24no. car parking spaces thus provides off-street parking provision for a combined 1,724 square metres of industrial unit.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HPK/2021/0707: Land adjacent to Unit 18, Tongue Lane Industrial Estate, Dew Pond Lane, Fairfield, BuxtonReport 892 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 21 attended
RM
Councillor Robert McKeownChair, present
DL
Councillor David LomaxVice-Chair, present
AB
Councillor Alan BarrowCommittee Member, present
LD
Councillor Lance DowsonCommittee Member, apologies
CF
Councillor Charlotte FarrellCommittee Member, present
IH
Councillor Ian HuddlestoneCommittee Member, present
GO
Councillor Graham OakleyCommittee Member, present
JP
Councillor Jim PerkinsCommittee Member, present
PR
Councillor Peter RobertsCommittee Member, present
ET
Councillor Emily ThraneCommittee Member, present
JT
Councillor Jean ToddCommittee Member, present
SY
Councillor Stewart YoungCommittee Member, present

All 21 on the meeting page

On this subject at High Peak

Search all
  1. HPK/2021/0707 - Land adjacent to Unit 18, Tongue Lane Industrial Estate, Dew Pond Lane, Fairfield, BuxtonThis decision
  2. HPK/2026/0146 - Land at St Georges Rd, New Mills DerbyshireRefused
  3. HPK/2023/0328 - Portland Nursing Home, 8 Park Road, BuxtonApproved
  4. HPK/2025/0340 - Hargate Hill Equestrian Centre Hargate Hill, Glossop - Retrospective application for change of use of land for the siting of caravans for residential occupation with associated developmentRefused
  5. HPK/2025/0447 - Land at Crossings Road, Chapel-en-le-FrithApproved
  6. HPK/2024/0496 - Land off Brown Edge Close, BuxtonApproved

More from High Peak Development Control Committee

All decisions
MeetingDecisionOutcome
10 Aug 2026 Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. Approved Open
10 Aug 2026 Update SheetThat the update sheet be noted. Noted Open
10 Aug 2026 Planning ApplicationsThat the report be noted. Noted Open
10 Aug 2026 HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... Approved Open
10 Aug 2026 HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies