RESOLVED : That the Council’s current risk position and the mitigation / fruition plans summarised within Appendix A (strategic risks), Appendix B (operational risks), Appendix C (project risks) and Appendix D (opportunity risks) to the report be noted.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
2.1That the Committee notes the Council’s current risk position and the mitigation / fruition plans summarised within Appendix A (strategic risks), Appendix B (operational risks), Appendix C (project risks) and Appendix D (opportunity risks).
Executive summary
3.1The Council’s Strategic, Operational and Project Risk Registers are reviewed by the Audit and Regulatory Committee on an exception basis. This report is based upon the Council’s position as at March 2023.
3.2The latest analysis of the Strategic Risk Register reveals that the Council has identified and assessed 19 strategic risks, of which 47% are rated as 'high' and therefore above the Council’s risk tolerance threshold. The strategic risk profile has seen the addition of one new medium threat risks (PSTN switch off) since last reported, The nine ‘high’ rated risks are listed in full at Appendix A.
3.3The Operational Risk Registers reveal that the Council has identified and assessed 47 operational risks in total, of which 12 are rated as ‘high’ and therefore above the Council’s risk tolerance thresholds. The details of all the significant changes can be found at paragraph 9. The risks falling within the ‘high’ category are listed in full at Appendix B.
3.4The project risk registers currently cover 8 projects and the risk profile is bulleted below:
4.1Risk Management impacts on all service areas and therefore links to each of the Council’s Corporate Plan aims
Alternative options
5.1There are no options to consider
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998) None
6.2Workforce None
6.3Equality and Diversity/Equality Impact Assessment This report has been prepared in accordance the the Council’s Diversity and Equality Policies
6.4Financial Considerations Effective Risk Management contributes to financial objectives
6.5Legal None
6.6Climate Change None 6.7 Consultation None
6.8Risk Assessment The Council’s Risk Registers are a critical element in the Council’s Risk Management Framework.
ANDREW P STOKES Chief Executive
Web Links and Contact details Background Papers Risk Registers March 2023” Tanya Cooper- Head of Organisational Development and Transformation [email protected] 7. Detail
7.1The Council ensures that it undertakes a deliberate and systematic identification of the key risks that might prevent, degrade, delay or enhance the achievement of its objectives and priorities. The Council's Risk Management Strategy sets out the process for undertaking this on an ongoing basis.
7.2In addition to the identification of risks, managers also have to quantify them in terms of likelihood and potential impact. The risks are then recorded in the Council's Risk Registers. These have three aspects – strategic, operational and project risks.
7.3Under the Risk Management Strategy, the Council’s ‘risk tolerance’ threshold is set along the border between ‘medium’ and ‘high’ rated residual risks. The Strategy stipulates that mitigating actions should be identified for all risks that exceed this threshold.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.