Resolved
That the update report be noted.
Moorlands Partnership Board noted this item on Tuesday 21 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the update report be noted.
2.1That the update report is noted.
3.1This report deals with progress to date on those projects, awaiting commencement, on site or, completed since the last meeting of the Moorlands Partnership Board.
3.2This report is for information only but does offer Members an opportunity to comment on progress. The report will be presented with an accompanying power point presentation which displays images of each project.
4. How this report links to Corporate Priorities
4.1This report concerns publicly funding the restoration and repair of historic properties or places that are either listed or an identified heritage asset. This, in turn, is related to the Council’s corporate aim 3:
Help create a strong economy by supporting further regeneration of towns and villages.
5.1There are no alternative options as this an update report on progress only. 6. Project updates and progress
2016/17 OFFERS:
Biddulph Town Council Projects
The Trough – The Architect is discharging the listed building conditions relating to materials and the scheme will be complete by the end of the year. Gillow Heath Station – Complete and grant paid.
2020/2021 OFFERS:
St Edwards Summerhouses – Repair of grade II listed summer houses within site Work commencing January 2024.
2021/2022 OFFERS:
Heaton House, Rushton Spencer – Reinstatement of stone boundary wall to match original The wall is complete but there is a 6- 8 week lead in time for the coping stones.
St Giles Church, Cheadle - Funerary Monument repairs No further update.
Guild Hall, Alton Castle – Roof repairs Fund raising and grant awards have secured 100% of the funding required for the repair to the roof of the building. A contractor has been appointed to undertake the works after a tender process with a target completion date of 29th September.
19 Hugo Street, Leek – Sash window reinstatement All but one of the windows has been installed. The grant has been part paid. The remaining window wont be installed until internal decoration has been completed.
Ipstones Boundary Post – New boundary post carved and erected Boundary post complete grant not claimed yet.
Christ Church, Biddulph Moor – Roof repairs No update to report.
Upper Tean Heritage trail and map Works complete but grant not paid as yet. Endon Station platform repairs, new gate and sign board, reinstatement of windows and door. Platform repairs complete and fence installed along with new gates. Decoration to be undertaken imminently along with the new windows and door.
Bank House Leek window repairs Works complete but grant not paid as yet.
Consall Station platform repairs North section of the platform complete with works undertaken by volunteers.
Foxlowe Arts Centre Applicant is currently applying for match funding before they can commit to a start date.
Brown Edge Road Playing Fields gate repairs Works to be undertaken shortly.
Cheddleton Station Signal Box relocation Not started as yet due to funding issues.
ANTICIPATED APPLICATIONS:
Former garage/barn Ipstones – Heritage interpretation
St Leonards Church Ipstones - Wall painting restoration
Buttercross Cheddleton - Schedule Monument repairs
Endon Village Hall – Window repairs
33 Compton, Leek – Window reinstatement
7. Implications
7.1Community Safety – No implications at this stage.
7.2Workforce – The Moorlands Partnership Scheme is administered by an officer within the Regeneration Team with assistance when required from the Council’s Conservation Officer.
7.3Equality and Diversity/ Equality Impact Assessment - No implications at this stage.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Summary of ProjectsReport | 138 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.