CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
Moorlands Partnership Board, Tuesday 15 July 2025 at 2.00pm

Summary of Projects.

Decided Committee 1 paper

Moorlands Partnership Board decided this item on Tuesday 15 July 2025. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

That a site visit to The Plough, Endon be undertaken by Officers. 2. That the report be received.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Moorlands Partnership Board

Recommendation

2.1That the update report is noted.

Executive summary

3.1This report deals with progress to date on those projects awaiting commencement, on site, or completed since the last meeting of the Moorlands Partnership Board.

3.2This report is for information only but does offer Members an opportunity to comment on progress. The report will be presented with an accompanying power point presentation which displays images of each project.

4. How this report links to Corporate Priorities

4.1This report concerns publicly funding the restoration and repair of historic properties or places that are either listed or an identified heritage asset. This in turn, is related to the Council’s corporate aims 3:

 Help create a strong economy by supporting further regeneration of towns and villages.

Alternative options

5.1There are no alternative options as this is an update report on progress only. 6. Project updates and progress

2020/2021 OFFERS:

St Edwards Summerhouse – Repair of Grade II listed summer house within site The summer house is currently being repainted and the roof will be reinstated after the redecoration is complete.

2021/2022 OFFERS:

Christ Church, Biddulph Moor – Roof repairs The applicant is still keen to complete the works but there are budget constraints. An application to the Heritage Lottery Fund has been submitted for the remaining funds. They hope to start and complete the project by the end of the year.

2023/2024 OFFERS:

St James Court Clock tower redecoration Work is now complete.

Village Hall Endon Works now complete to the satisfaction of both the Regeneration Officer and applicant. The grant has been paid.

2024/2025 OFFERS:

The Plough Endon – Mural restoration The pub has been subject to a full internal and external refurbishment including the repair and consolidation of the existing mural.

Stockton Brook former pumping station – roof repairs Match funding has now been secured. Works to repair the roof will start soon.

St Chads Church Longsdon – Porch repairs Works now complete.

Former Cattle Shed Endon – Replacement doors Grant accepted but no works on site yet.

St Giles The Abbot Cheadle – Church clock repairs Slight delay to works as possible change of contractor being explored.

76 Derby St/89 Haywood St Leek – Window repairs Works complete to all windows on upper floors. Redecoration scheme to be applied to ground floor shopfront and new signage. As a result, the building will look more coherent. ANTICIPATED APPLICATIONS:

Den Engel Leek - Courtyard resurfacing and refurbishment of outbuildings. Application will be made next year.

White Bridge Endon – Bridge repairs after vandalism. Positive contact with the Canals and Rivers Trust who are keen to explore a grant application for consideration at the November meeting.

7. Implications

7.1Community Safety – No implications at this stage.

7.2Workforce – The Moorlands Partnership Scheme is administered by an officer within the Regeneration Team with assistance when required from the Council’s Conservation Officer.

7.3Equality and Diversity/ Equality Impact Assessment - No implications at this stage.

7.4Financial considerations - There are allocations within the capital programme for the Moorlands Partnership grant scheme. The projects outlined in this report have been met from approved budgets from previous years. The budget for this year 2025-2026 is £50,000.

7.5Legal - Local authorities are empowered to give grants towards improvements in conservation areas under Section 57 of the Planning (Listed Buildings and Conservation Areas) Act 1990.

7.6Climate Change – No Implications at this stage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Summary of Projects.Report 134 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 24 attended
CJ
Councillor Christina JebbChair, present
LM
Councillor Linda MalyonVice-Chair, present
BB
Barry BirchCommittee Member, absent
BE
Bob EggintonCommittee Member, present
BE
Councillor Ben EmeryCommittee Member, present
EF
Councillor Elsie FallowsCommittee Member, present
KF
Councillor Keith FlunderCommittee Member, present
KH
Councillor Ken HarperCommittee Member, absent
AH
Andrew H HartCommittee Member, absent
MJ
Councillor Mark JohnsonCommittee Member, apologies, sent representative
DP
Councillor Darren PriceCommittee Member, present
AT
Alan ThomasCommittee Member, absent

All 24 on the meeting page

On this subject at High Peak

Search all
  1. Summary of Projects.This decision
  2. Summary of ProjectsDecided
  3. Summary of Projects.Decided
  4. Summary of ProjectsDecided
  5. Summary of ProjectsNoted
  6. Summary of ProjectsNoted

More from High Peak Moorlands Partnership Board

All decisions
MeetingDecisionOutcome
16 Mar 2026 To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. Approved Open
16 Mar 2026 Summary of ProjectsThat the report be received. Decided Open
16 Mar 2026 Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... Noted Open
16 Mar 2026 Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. Decided Open
17 Nov 2025 To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies