Resolved
· That the update report be noted. · That the application for Christ Church, Biddulph Moor remain open until the next meeting.
Moorlands Partnership Board noted this item on Tuesday 16 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
· That the update report be noted. · That the application for Christ Church, Biddulph Moor remain open until the next meeting.
2.1That the update report is noted.
3.1This report deals with progress to date on those projects awaiting commencement, on site, or completed since the last meeting of the Moorlands Partnership Board.
3.2This report is for information only but does offer Members an opportunity to comment on progress. The report will be presented with an accompanying power point presentation which displays images of each project.
4. How this report links to Corporate Priorities
4.1This report summarises the funding provided for the restoration and repair of historic properties or places that are either listed or an identified heritage asset. This is related to the Council’s corporate aims 3:
Help create a strong economy by supporting further regeneration of towns and villages. 5. Alternative Options
5.1There are no alternative options as this an update report on progress only.
6. Implications
6.1Community safety, including safeguarding and prevention of terrorism No implications at this stage.
6.2Workforce The Moorlands Partnership Scheme is administered by an officer within the Regeneration Team with assistance when required from the Council’s Conservation Officer.
6.3Equality and Diversity/ Equality Impact Assessment No implications at this stage.
6.4Financial Considerations There are allocations within the capital programme for the Moorlands Partnership grant scheme. The projects outlined in this report have been met from approved budgets from previous years. The budget for this year 2023- 2024 is £60,000.
6.5Legal Local authorities are empowered to give grants towards improvements in conservation areas under Section 57 of the Planning (Listed Buildings and Conservation Areas) Act 1990.
6.6Climate Change and Sustainability No Implications at this stage.
6.7Conservation and Enhancement of Biodiversity None
6.8Consultation Grant offers are made in consultation with and approved by the Moorlands Partnership Board. Where required, projects that require planning permission and listed building consent are subject to the normally statutory consultations.
6.9Risk Assessment Not applicable
ANDREW P STOKES Chief Executive
Web Links and Contact details Background Papers Joanne Brooks Regeneration Officer [email protected] 7. Project Updates and Progress
2016/17 OFFERS:
Biddulph Town Council Projects
The Trough – To be completed within the next 8 weeks.
2020/2021 OFFERS:
St Edwards Summerhouse – Repair of Grade II listed summer house within site Work commenced mid-February and site visit undertaken 13th Feb. Zinc roof to be reinstated.
2021/2022 OFFERS:
Heaton House, Rushton Spencer – Reinstatement of stone boundary wall to match original Works complete and grant paid.
St Giles Church, Cheadle - Funerary Monument repairs Grant withdrawn due to the length and complexity over obtaining Diocese approval.
Guild Hall, Alton Castle – Roof repairs Works complete and grant paid.
Christ Church, Biddulph Moor – Roof repairs No update or anything received from applicant since Oct 23. Officers recommend grant is withdrawn as it expired in March 24.
Endon Station platform repairs, new gate and sign board, reinstatement of windows and door Platform repairs complete and new fence installed along with new gates. Decoration now complete and grant paid. Works to reinstate windows and doors delayed. Grant expires July 25.
Consall Station platform repairs Works complete and grant paid.
Foxlowe Arts Centre Applicant is currently applying for match funding through the UKSPF before they can commit to a start date.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Summary of ProjectsReport | 139 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.