British Airways Community Learning Centre, Accommodation Lane, Harmondsworth 43410/APP/2010/2426
ApprovedPlanning1 paper
Central & South Planning Committee approved this item on Tuesday 23 November 2010. Below is the council's own wording, with the papers it was decided on.
Resolved – That the application be approved subject to the conditions and informatives set out in the officer’s report and the revision of Condition 1 as follows: ‘ The building and hard surfaces shall be removed and the access to Accommodation Lane close within 6 months of the Community Learning and Visitor Centre use ceasing and the land shall be restored to Green Belt in accordance with a landscape scheme which has been submitted to and approved in writing by the Local Planning Authority’.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Central & South Planning Committee, 11 pages
Report of the Head of Planning & Enforcement Services
Address BRITISH AIRWAYS COMMUNITY LEARNING CENTRE ACCOMMODATION LANE HARMONDSWORTH
Development: Variation of condition 1 (temporary consent) of planning permission ref: 43410/APP/2007/3886 dated 12/03/2008 (Retention of Community Learning/Visitor Centre and toilet block for a temporary period of three years) to enable the permanent retention of the Community Learning Centre.
LBH Ref Nos: 43410/APP/2010/2426
Drawing Nos: IL12297/02-001 (Site Location) Flood Risk Assessment prepared by Peter Brett Associates dated September 2001 P344 1 (Site Survey) Modelled Flood Extents
Date Plans Received: 18/10/2010 Date(s) of Amendment(s): Date Application Valid: 18/10/2010 1. SUMMARY The British Airways Community Learning Centre (CLC), which is located on the southern side of Accommodation Lane in Harmonsdsworth, has been in place since 1998 and provides a range of educational, environmental and heritage programmes to the local community in addition to accommodation for the parkland rangers, who are responsible for the upkeep of the park.
This application seeks the variation of condition 1 of planning permission ref: 43410/APP/2007/3886 (temporary consent) to allow the permanent retention of the CLC.
It is considered that the CLC provides a facility which is directly related to the conservation and management of the surrounding parkland. In addition it provides an important asset to the local community. It has limited visual impact on the surrounding area and the parking and access arrangements are considered to be acceptable.
The proposal is considered to comply with relevant UDP and London Plan policies and, accordingly, approval is recommended. 2. RECOMMENDATION APPROVAL subject to the following:
1 NONSC Removal of building when no longer required The building and hard surfaces shall be removed and the access to Accommodation Lane closed within 6 months of the use ceasing and the land shall be restored in accordance with a landscape scheme which has been submitted to and approved in writing by the Local Planning Authority.
REASON In the interests of visual amenity and to safeguard the long-term openness of the Green Belt, in accordance with policies OL1, OL4 and BE13 of the Hillingdon Unitary
Central & South Planning Committee - 23rd November 2010 PART 1 - MEMBERS, PUBLIC & PRESS Development Plan Saved Policies (September 2007).
2 NONSC Development in accordance with submitted documents The development hereby approved shall be carried out in strict accordance with the submitted application documents, except where expressly varied by other conditions of the consent.
REASON In the interests of visual amenity in accordnace with policies OL1, OL4 and BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
3 NONSC Restricted use of building to visitor centre/CLC only The building hereby approved shall be used as a parkland Visitor Centre and Community Learning Centre, as described in the letter from Nathaniel Lichfield and Partners, dated 18/10/10 and for no other purposes.
REASON To ensure that uses, not appropriate to the Green Belt setting of the site and which could prejudice the openness and visual amenities of the Green Belt are not permitted in accordance with Policy OL1 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
4 NONSC Energy/sustainability The building hereby approved shall employ devices that automatically turn the heating and lighting off when the rooms are not in use.
REASON In the interests of energy conservation in accordance with Policy 4A.3 of the London Plan (2008).
5 NONSC Refuse details Within three months of the date of this consent details of facilities to be provided for the covered, secure and screened storage of refuse at the premises shall be submitted to and approved in writing by the Local Planning Authority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.