Resolved
Resolved – That no objection be raised subject to the considerations set out in the officer’s report.
Central & South Planning Committee decided this item on Tuesday 23 November 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That no objection be raised subject to the considerations set out in the officer’s report.
Report of the Head of Planning & Enforcement Services
Address LAND AT WESTERN END OF HEATHROW AIRPORT HEATHROW AIRPORT HOUNSLOW
Development: Erection of a single storey building for hold baggage screening to the south of Terminal 5 (Consultation under Schedule 2, Part 18 of the Town and Country Planning (General Permitted Development) Order 1995) (as amended.)
LBH Ref Nos: 47853/APP/2010/2338
Drawing Nos: Photos of existing site Location Plan as existing 539-001 Rev A Elevations looking North & East as existing 539-002 Rev A Location Plan Proposed HBS Facility as proposed 539-500 Rev A Site Plan as proposed 539-501 Rev A Ground Floor Plan as proposed 539-502 Rev A Roof Plan as proposed 539-503 Rev A Elevation looking North & East as proposed 539-504 Rev A Elevation as proposed 539-505 Rev A Sections as proposed 539-506 Rev A Covering letter from BAA 4-10-10 Design & Access Statement 28-09-10
Date Plans Received: 05/10/2010 Date(s) of Amendment(s): Date Application Valid: 05/10/2010 1. SUMMARY BAA has submitted this proposal for consultation under Part 18 of the Town and Country Planning (General Permitted Development) Order 1995.
It is proposed to erect a single storey building for hold baggage screening for VIP passengers to the south of Terminal 5.
The proposal is considered to be visually acceptable in this location and complies with relevant UDP and London Plan policies.
The Council's Environmental Protection Unit raises no objection, subject to appropriate contamination and ground gas considerations.
Accordingly, it is considered that the proposal does not give rise to any material planning concerns and it is recommended that no objection is raised subject to the considerations set out in this report.
2. RECOMMENDATION That NO OBJECTION be raised subject to the following considerations:
1 OM1 Development in accordance with Approved Plans
Central & South Planning Committee - 23rd November 2010 PART 1 - MEMBERS, PUBLIC & PRESS The development shall not be carried out otherwise than in strict accordance with the plans hereby approved unless consent to any variation is first obtained in writing from the Local Planning Authority.
REASON To ensure that the external appearance of the development is satisfactory and complies with Policy BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
2 NONSC Site survey and remediation scheme Before any part of this development is commenced a site survey to assess the land contamination levels shall be carried out to the satisfaction of the Council and a remediation scheme for removing or rendering innocuous all contaminates from the site shall be submitted to and approved by the Local Planning Authority. The remediation scheme shall include an assessment of the extent of site contamination and provide in detail the remedial measures to be taken to avoid risk to the occupiers and the buildings when the site is developed. All works which form part of this remediation scheme shall be completed before any part of the development is occupied (unless otherwise agreed in writing by the Local Planning Authority). The consideration will not be discharged until verification information has been submitted for the remedial works. Any imported material i.e. soil shall be tested for contamination levels therein to the satisfaction of the Council.
REASON To ensure that the occupants and users of the development are not subject to any risks from contamination in accordance with policy OE11 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Land at western end of Heathrow Airport, Heathrow Airport, Hounslow 47853/APP/2010/2338Report | 13 pages | DownloadRead as text |
Follow Central & South Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 May 2021 | To sign and receive the minutes of the previous meeting dated 7 April 2021That the minutes of the meeting dated 7 April 2021 be approved as an accurate record subject to an amendment to indic... | Approved | Open |
| 4 May 2021 | 2 De Salis Road, Hillingdon - 38071/APP/2020/36391) That the application be refused; and 2) That delegated authority be granted to the Head of Planning to explore the... | Refused | Open |
| 4 May 2021 | 43 Sweetcroft Lane, Hillingdon - 17412/APP/2021/5991) That the application be refused; and 2) That delegated authority be granted to the Head of Planning, in consultati... | Refused | Open |
| 4 May 2021 | Heinz Wolff Building, Brunel University - 532/APP/2021/330That the application be approved. That the application be approved. | Approved | Open |
| 4 May 2021 | Harmondsworth Landfill Site, Harmondsworth Lane - 43155/APP/2020/4267That the application be approved. 1) That delegated authority be granted to the Head of Planning to reword Point 2 on... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.