Resolved
Resolved - That the progress made on managing the Council’s strategic risks be noted.
Audit and Governance Committee noted this item on Tuesday 20 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That the progress made on managing the Council’s strategic risks be noted.
Contact: Phil Brown Tel: 020 8583 2346 E-mail: [email protected]
Audit Committee – 20 March 2007
RISK MANAGEMENT MONITORING
Report by: Director of Finance
Summary This report updates Members on how the risks identified in the 2006/07 corporate risk register are being managed.
1.0Recommendation 1.1 To note the progress made on managing the Council’s strategic risks.
2.0Background 2.1 The Council’s corporate risk register consists of the risk registers of each of the Council’s departments. These were formally reviewed and updated in Spring 2006 with an updated risk register being agreed by CMT in June 2006. The management of the significant risks highlighted by departments is monitored quarterly by CMT and the Audit Committee.
2.2The most significant corporate risks the 2006/07 Risk Register are: • Failure of IT Hardware and Software • Recruitment and Retention of appropriately skilled staff • Pressure on the local infrastructure and employment market due to airport intensification and expansion and other large scale developments • Disruption to services due to an incident in Hounslow or London or due to Avian flu • The Council fails to deliver effective integrated services to children and families • Failure to modernise services. • Failure of DCLG to include accurate population figures in RSG settlement.
2.3This report sets out the actions taken over the last quarter to manage the most significant risks identified in the 2006/07 corporate risk register.
3.0Management of significant corporate risks 3.1 The actions taken from December 2006 to February 2007, and further actions required to mitigate the effects of these risks where appropriate are summarised below.
3.2Access controls to the Council’s network have been strengthened in recent months. Users are now required to have an alphanumeric password, which they are required to change regularly. 3.3 ICT are continuing to explore with other West London authorities how to share each other’s data centres to secure major corporate systems in the event of an incident.
3.4ICT are appraising the level of support required by key applications including the new HR/Payroll system and Agresso, (the Council’s financial system).
Failure of IT Hardware and Software 3.5 The risk of the failure of IT hardware and software is also being addressed through the Corporate Business Continuity Plan.
Recruitment and Retention of appropriately skilled staff 3.6 All sections in the Chief Executives Directorate and Street Management & Public Protection have draft workforce plans.
3.7The number of temporary staff is monitored each month by the HR Shared Service Centre and reported to HR SMT. This enables the tracking of posts that are filled by agency staff.
Airport intensification and expansion and other adverse developments 3.8 The Council has successfully lobbied the Government to stop the removal of the seasonal movement limit on aircraft flying at night.
3.9The Transport Select Committee released its report on the workings of the Civil Aviation Authority. Hounslow Council had been invited to provide evidence to the committee in both written and verbal presentations. Our evidence has been taken into account within the CAA's recommendations.
3.10Implementation of the air quality action plan continues. We have a received favourable response to our progress report on this matter from both DEFRA and the GLA. The Council has commissioned a report on freight related issues.
3.11A report is submitted once every two months to the Executive detailing the progress made on each of the major development projects. This includes Key Site 1, Lampton Park Conference Centre and Brentford Town Centre development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Monitoring ReportReport | 42 KB | DownloadRead as text |
Follow Audit and Governance Committee at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Apologies for absence, declarations of interest or any other communication from MembersThere were no apologies for absence, declarations of interest or other communications. | Decided | Open |
| 8 Sep 2026 | Minutes of the meeting held on 3 February 2026The minutes of the meeting held on 3 February 2026 were agreed as an accurate record. | Agreed | Open |
| 8 Sep 2026 | Matters arising from the minutesThere were no matters arising from the minutes. | Decided | Open |
| 8 Sep 2026 | Quarterly Monitoring of Corporate Risk Register (Q1, 2026-27)Please see the report by Sarah Filby, Director Strategy, Performance & Commissioning (agenda item 4) The report was p... | Decided | Open |
| 8 Sep 2026 | Treasury Management Annual Report 2025/26Please see the report by Jake Bacchus, Executive Director of Finance and Resources (agenda item 5) The report was pre... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.