Resolved
Officers had included all of the sub items on the agenda into one report.
Gunnersbury Park Joint Advisory Panel decided this item on Friday 30 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Officers had included all of the sub items on the agenda into one report.
GUNNERSBURY PARK REGENERATION PROJECT
GUNNERSBURY PARK London
Gunnersbury Park Joint Advisory Panel Progress Report 30 January 2015
1 1.0 HLF Project Update
1.1Design The Stage E Review meeting with HLF was held on 24 November 2014 and their feedback was very positive. They felt that good progress had been made and they supported the changes to the café and carriage new build.
The Design Team has continued to concentrate on producing detailed specifications and drawings in preparation for the Invitation to tender (ITT) that is now programmed to go out end of January 2015. The contractor appointment now set for May 2015. External works to the Large mansion and works to the parkland are planned to start in the summer and internal repairs and alterations to the large mansion in the autumn.
1.2Museum Service The museum shut to the public on the 24 th December 2014 so that we can begin the process of packing the collection in order to transfer it to an off-site store during the refurbishment works. A lease is being arranged and we will reassess our storage requirements once the collections for display have returned to the museum
Invigour, our Museum development lead consultants, have appointed two temporary curatorial staff to help the design team deliver the curatorial and conservation tasks for this programme. Preparations to employ a permanent curator will commence next month so that this post can be appointed to the CIC but seconded to the local authorities until the CIC is able to manage the position.
We hope to achieve practical completion on the refurbishment of the large mansion on 22 August 2016 and begin the fit out of the museum and recruitment of new posts so that we are ready for a soft opening on 6th March 2017 and an official opening on the 15th May.
The Arts Council England (ACE) has advised that with the closure of the museum for refurbishment the museum will revert to Provisional status until it reopens in 2017. Since ACE advice currently prevents a CIC from being the museum authority the collections will remain in the ownership of the councils and they will retain authority for the collections development policy. ACE will issue an invitation to apply for Full status to the authority in 2018. This has all been explained to the satisfaction of HLF
The Education team has moved to the Small mansion so that we can continue to offer learning sessions to schools during the works. There is a final opportunity for the public for an exclusive access tour of the Victorian Kitchens on Wednesday 25 th February at 2.00pm before the refurbishment. Admission £3 payable in cash on the day contact the museum on 020 8992 2247/1612.
1.3Changes to the café proposals A meeting was held with English Heritage and LB Hounslow planners on the 9th December to discuss changes concerning Large mansion roof drainage, the South Terrace, East Arch roof arrangements and the café and carriage new build. These were agreed in principle and are considered a minor material amendment and will not require Secretary of State approval.
2 There are a number of advantages which the new proposals offer the project which are summarised as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Heritage Lottery Fund (HLF) Project UpdateReport | 281 KB | DownloadRead as text |
Follow Gunnersbury Park Joint Advisory Panel at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2017 | Heritage Progress ReportThe submitted report was noted. | Noted | Open |
| 7 Jul 2017 | Sports Progress ReportResolved : The submitted report was noted. | Noted | Open |
| 28 Apr 2017 | Dates of future meetingsIt was agreed to move the July 21 date forward to 7 July 2017. James Wisdom submitted apologies for the new date and ... | Agreed | Open |
| 18 Nov 2016 | Presentation on Sports HubIt was agreed that revised images would be circulated the following week to members of the Panel, as well as to other... | Agreed | Open |
| 21 Oct 2016 | Update on Park Events Licence ProposalIt was agreed to arrange an additional meeting with appropriate officers attending to discuss the licensing policy. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.