i). That Cabinet approved proposals for entering into a Contract with Hounslow Highways Services Limited for a capital works programme, not to exceed £10m over the next three years, to upgrade the housing estate roads, footways, footpaths and street lighting. ii). That Cabinet delegated authority to the Director of Housing to finalise the agreement for the undertaking of the capital works under the terms of the existing Hounslow Highways contract and to award a contract for the ongoing maintenance of the new street lighting on estates. i). That Cabinet approved proposals for entering into a Contract with Hounslow Highways Services Limited for a capital works programme, not to exceed £10m over the next three years, to upgrade the housing estate roads, footways, footpaths and street lighting. ii). That Cabinet delegated authority to the Director of Housing to finalise the agreement for the undertaking of the capital works under the terms of the existing Hounslow Highways contract and to award a contract for the ongoing maintenance of the new street lighting on estates.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Title CHAS 588 Housing Estate Roads and Lighting Member Deciding Councillor Katherine Dunne Lead Member for Housing, Equalities and Inclusion [email protected] Contact Details Peter Matthew, Director of Housing 0208 583 5321 [email protected] Date to be Considered 10th October 2017 Implementation Date if October 2017 Not Called In Affected Wards All Keywords/Index Housing Estate Roads and Lighting
1. Details of Recommendations
This report recommends that Cabinet:
i). Approves proposals for entering into a Contract with Hounslow Highways Services Limited for a capital works programme, not to exceed £10m over the next three years, to upgrade the housing estate roads, footways, footpaths and street lighting.
ii). To delegate authority to the Director of Housing to finalise the agreement for the undertaking of the capital works under the terms of the existing Hounslow Highways contract and to award a contract for the ongoing maintenance of the new street lighting on estates.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Improved condition of roadways and footways. Lighting improvements will Improved LED lighting on estate roads and footpaths start early in the 2018 A safer estate environment calendar year with a 3 year Improved visual amenity of the estates programme of road and Energy savings on lighting costs within service footpath improvements to charges. follow. 2. Report Summary
1. These recommendations are being made in recognition of the poor condition of a number of estate roads, footways and footpaths and to update the existing street lighting stock to a modern LED (light-emitting diode) specification. The proposals will provide improved safety to road users, cyclists and pedestrians and improve the visual appearance of the estates. We would be using the call off arrangements within the existing long term Hounslow Highways contract to deliver these improvements.
2. If adopted, the key financial implications for the Council are capital expenditure of approx. £2m on street lighting and approx. £8m on roads and footpaths. The total capital expenditure will not exceed £10m over a 3-year period.
3. This package of works replaces the original proposal to fully integrate housing estate roads, footpaths, lighting and other network assets into the existing highways maintenance contract.
3. Reason for Decision and Options Considered
3.1On 26th April 2016 the Cabinet agreed draft proposals to incorporate the management and maintenance of all Housing Revenue Account estate roads, footways, footpaths and communal grounds (the Housing network) into the existing Hounslow Highways contract to December 2037, subject to satisfactory completion of due diligence on the detailed proposals, its value for money, and consultation with tenants and leaseholders. This would entail the full accrual of the management and maintenance of all aspects of the Housing networks including risk transfer, into the extant Hounslow Highways PFI.
3.2To inform the development of the proposals and agreement between the Council and Hounslow Highways Services Limited (the Service Provider/Contractor) a number of detailed asset surveys were commissioned to provide information about the condition of the Housing network. These surveys were comprehensive and provide data to enable the Council to target investment in its housing network.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.