That Cabinet noted developments in the last 21 months to deliver the first phase of 178 homes on the Lampton site by autumn 2018 (with over 900 ready by 2022). 2. That Cabinet noted that all of the first phase of housing would be affordable and the proportion of affordable housing on the completed site had increased from 40% to 50% due to additional support through the GLA. 3. Cabinet noted progress to relocate the civic centre to Bath Road to enable the full scheme of housing to be delivered and the associated work to ensure the move takes forward our commitment to be a council that is ambitious for our residents through improving customer services, modernising working practices and driving an efficient back office 4. Cabinet approved a budget increase of £2.25 million (to £13.520m) for increased commitments on the capital development (set out in para 5).
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Title CEX156 Worksmart and New Civic Programmes and Development Agreement. Member Reporting Cllr Theo Dennison and Cllr Ed Mayne Contact Details Mary Harpley/Frances Houston For Consideration By Date to be Considered 10 Oct 2017 Implementation Date if 24 October 2017 Not Called In Affected Wards All Keywords/Index Lampton Road Housing, Customer Services, Civic Centre, Worksmart.
1. Details of Recommendations
The Cabinet is asked to
1. Note developments in the last 21 months to deliver the first phase of 178 homes on the Lampton site by autumn 2018 (with over 900 ready by 2022). 2. Note that all of the first phase of housing will be affordable and the proportion of affordable housing on the completed site has increased from 40% to 50% due to additional support through the GLA. 3. Note progress to relocate the civic centre to Bath Road to enable the full scheme of housing to be delivered and the associated work to ensure the move takes forward our commitment to be a council that is ambitious for our residents through improving customer services, modernising working practices and driving an efficient back office. 4. Approve a budget increase of £2.25 million (to £13.520m) for increased commitments on the capital development (set out in para 5).
If the recommendations are adopted, how will residents benefit? Provision of new housing that will contribute to the Council’s First phase housing target Autumn 2018 Improved customer experience and online service offer to First phase Jan residents 2017 Modernised service delivery from a fit for purpose and more Spring 2019 efficient back office and development of a culture of continuous service improvement to benefit residents 2. Report Summary
In November 2015 (REG 335), the Cabinet gave approval for the council to enter into a Development Agreement with BY Development Ltd (and associated parties) to develop the Lampton Road site for housing and relocate Council and partner services – along with the Central Hounslow Library – to a new building on Bath Road car park.
Since signing the Development Agreement with BY Ltd in July 2016, building on both the Lampton and Bath Road sites has progressed beyond groundworks and foundations with the concrete frame(s) to buildings on both sites progressing well. The first phase of 178 housing units on Lampton Road is on target for first occupation in autumn 2018. The new civic centre is on target for occupation by spring 2019.
Considerable progress has been made in joining up the work needed to get the council and its partners ready for the move to the new building and in developing coherent management arrangements for this complex programme. Since late 2016 a single Programme Board has been overseeing work on Transforming the Customer Experience, Worksmart and the move to the new building which is jointly chaired by the lead member for Finance and Citizen Engagement and the Chief Executive and includes the lead member for Customer Care and Performance.
In May 2017, Central Hounslow Library was relocated to the Civic Centre at Lampton Road following agreement of a new ten-year sub-lease of a major portion of the Treaty Centre Library demise to Job Centre Plus (JCP) which will result in considerable savings for the council including a rental income of c£ £215,000 p.a and a contribution to service charge and rate outgoings in the region of £290,000. This will also allow for the library to more easily ‘lift and shift’ when it moves to the new Civic Centre in Bath Road.
At the outset of the Development Agreement it was recognised that a number of risks were associated with the initial budget. These included the provision for professional fees, ground works and other costs which had not been revised since July 2015. Further evaluation of these costs has been undertaken and a gap of £2.25m between budgeted provision and commitments has been identified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.