CHAS 545: Non-HRA Housing Programme - Phase 2

Approved Executive 1 paper

Cabinet approved this item on Tuesday 10 October 2017. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

That Cabinet approved the: i). Release of the five (5) General Fund sites identified at Table 1, which had been identified as surplus to current use and requirements, for the purpose of redevelopment for housing. ii). Commissioning of Lampton Investment 360 Ltd to include the additional sites as Phase 2 of the Non-HRA Housing Development Programme , and to develop detail proposals for taking forward the sites having regard to the Council’s housing needs and supply requirements. iii). The revision of the property purchase plans to prioritise the purchase by Lampton Investment 360 Ltd of private rented properties delivered by Lampton Development 360 Ltd through the Non-HRA Housing Development Programme . iv). Undertaking of work by Corporate Property to facilitate the acquisition, variation or release of covenants related to the identified sites; and the transfer of land ownership from the Council to Lampton Development 360 LLP at best value, subject to the production of an RICS Red Book Valuation That Cabinet approved the: i). Release of the five (5) General Fund sites identified at Table 1, which had been identified as surplus to current use and requirements, for the purpose of redevelopment for housing. ii). Commissioning of Lampton Investment 360 Ltd to include the additional sites as Phase 2 of the Non-HRA Housing Development Programme , and to develop detail proposals for taking forward the sites having regard to the Council’s housing needs and supply requirements. iii). The revision of the property purchase plans to prioritise the purchase by Lampton Investment 360 Ltd of private rented properties delivered by Lampton Development 360 Ltd through the Non-HRA Housing Development Programme . iv). Undertaking of work by Corporate Property to facilitate the acquisition, variation or release of covenants related to the identified sites; and the transfer of land ownership from the Council to Lampton Development 360 LLP at best value, subject to the production of an RICS Red Book Valuation
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 9 pages

Report for: ACTION / INFORMATION

Contains Confidential No or Exempt Information

Title CHAS 545: Non-HRA Housing Programme - Phase 2 Member Reporting Councillor Steve Curran, Lead Member Corporate Strategy, Planning and Regeneration Contact Details Peter Matthew – Director of Housing [email protected] 0208 583 5321 For Consideration By Cabinet Date to be Considered 10 October 2017 Implementation Date if October 2017 Not Called In Affected Wards Based on site locations Keywords/Index Housing Development Programme

1. Details of Recommendations

Cabinet is asked to approve the: i). Release of the five (5) General Fund sites identified at Table 1, which have been identified as surplus to current use and requirements, for the purpose of redevelopment for housing. ii). Commissioning of Lampton Investment 360 Ltd to include the additional sites as Phase 2 of the Non-HRA Housing Development Programme, and to develop detail proposals for taking forward the sites having regard to the Council’s housing needs and supply requirements. iii). The revision of the property purchase plans to prioritise the purchase by Lampton Investment 360 Ltd of private rented properties delivered by Lampton Development 360 Ltd through the Non-HRA Housing Development Programme. iv). Undertaking of work by Corporate Property to facilitate the acquisition, variation or release of covenants related to the identified sites; and the transfer of land ownership from the Council to Lampton Development 360 LLP at best value, subject to the production of an RICS Red Book Valuation.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will benefit, Dates by which they can link to Values expect to notice a difference Improvement of local facilities and services Various dates based on individual’s site redevelopment. Improvement of available affordable housing Improvement of housing solutions for the wider community Economic, Environmental and Sustainable developments, that add to the local economy, and create employment opportunities

2. Report Summary

The Corporate Property Strategy identifies a number of General Fund sites with potential for redevelopment to better serve Council objectives, in particular, to provide much needed housing to cater for the borough’s severe housing needs.

In April 2016, Cabinet agreed proposals for commissioning Lampton 360 Ltd to prepare a business plan for developing a first tranche of the “Non-HRA Housing Development Programme”, with potential to deliver in excess of 825 new homes by 2021. This included the preparation of detail plans for developing, financing and delivering a first tranche of schemes.

This report seeks approval for the development of a second tranche of general fund sites by Lampton 360 Ltd.

3. Reason for Decision and Options Considered

3.1The Corporate Property Strategy sets out the thinking for establishing the optimal use of General Fund sites that are surplus to the current needs of Services having regard to the Council’s service priorities. It explains that where assets are not being used by the main service areas or for the benefit of the community, then they should be considered for redevelopment that would meet key Council objectives.

3.2In April 2016, Cabinet agreed proposals for commissioning Lampton 360 Ltd to prepare a business plan for developing a first tranche of the “Non-HRA Housing Development Programme”, with potential to deliver in excess of 825 new homes by 2021. This included the preparation of detail plans for developing, financing and delivering a first tranche of schemes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CHAS 545: Non-HRA Housing Programme: Phase 2Report 9 pages DownloadRead as text

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies