CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hounslow
Cabinet, Monday 16 March 2026 at 7.00pm

Delivery Plan Monitoring 2025-26 (Q3)

Noted Executive 5 papers

AI summaryHounslow Cabinet noted Q3 progress across the People, Place, Capital and Digital Portfolios, with £475,000 of £2.06m planned 2025/26 savings delivered at Q3 and £825,000 forecast by year-end.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAcross all four Delivery Plan Portfolios
Money£2.06m FY25/26 savings£475,000 delivered at Q3, £825,000 projected
What happens nextQ4 monitoring reportQuarterly Cabinet update cycle
Who it affectsCouncil services and residentsAcross all four Portfolios

What was decided

Cabinet noted progress on programmes in the People Portfolio as set out in Appendix 1. Report 16.1

Cabinet noted progress on projects in the Place, Capital and Digital Portfolios as set out in Appendices 2, 3 and 4. Report 16.2, P73, 16.4

Why

Cabinet receives quarterly progress reports on all Delivery Plan programmes and projects under a Cabinet decision from 5 July 2022. Report 15.2

The report is a standing monitoring update; there are no direct financial implications from noting it. Report 14.2, 15.3

What happens next

Fortnightly monitoring of in-year benefit delivery will continue in coordination with Finance. Report 9.8

The next quarterly Delivery Plan monitoring report will be presented to Cabinet and the Overview and Scrutiny Committee. Report 15.2

The money

  • £2.06m Total Delivery Plan savings due for delivery in FY25/26 Report 9.6, P24
  • 475,000 FY25/26 savings actuals at end of Q3 Report P24
  • 825,000 FY25/26 savings projected by year-end Report P24
  • £8m Indicative savings from People Portfolio by end of FY27/28 Report 9.2
  • 365,000 Savings delivered in FY24/25 Report 9.4, P9
  • 911,000 FY24/25 savings delayed and carried forward into FY25/26 Report 9.5, P15
  • £1.1m Further FY25/26 savings agreed by Cabinet in February 2025 Report 9.6
  • 8,280,000 Additional indicative savings identified for 2026/27 and 2027/28 Report 9.9, P35
  • 12,438,000 Total indicative benefits identified across Delivery Plan programmes Report 9.10, P49
  • 1,460,000 Total benefits delivered to date across the Delivery Plan Report 9.10, P49
  • 11,287,000 Total projected benefits remaining to be delivered to FY27/28 Report 9.10, P49

Implications

  • Financial: No direct financial implications from noting the report; each programme must be delivered within its approved budget. Report 14.2, 14.3
  • Financial: People Portfolio funding is drawn from the One Hounslow Transformation reserve under existing approvals. Report 9.1
  • Financial: Place and Capital Portfolio projects are funded from the council's Capital Programme (General Fund and HRA). Report 9.11
  • Financial: Digital Portfolio is funded mainly through the Digital Strategy capital programme, with some from HRA Estate Investment and the One Hounslow Transformation Reserve. Report 9.12
  • Equalities: No direct equalities implications; equalities, diversity and inclusion is a core case within the One Hounslow Business Case approach. Report 11.1, 11.2
  • Climate: No direct climate implications; a Climate Impact Case forms part of the One Hounslow Business Case approach. Report 12.1
  • Legal: No direct legal implications; all projects and programmes must comply with the Constitution and relevant legislation. Report 10.1
  • Risk: Other implications such as staffing, accommodation and property will be identified through business cases and managed under the Constitution. Report 13.1

Who and where

  • Residents using council services across the People, Place, Capital and Digital Portfolios Report 16.1, 16.2, P73, 16.4
  • Council staff affected by People Portfolio programmes such as Organisational Design Report 9.4, P7

Timeline

  • FY24/25: £365,000 of Delivery Plan savings delivered Report 9.4, P9
  • FY25/26: £2.06m of Delivery Plan savings due; £475,000 delivered at Q3 with £825,000 forecast by year-end Report 9.6, 9.7, P24
  • 2026/27: £4,952,000 of further indicative savings identified across the Delivery Plan Report 9.9, P35
  • 2027/28: £3,328,000 of further indicative savings identified, taking the total to £8.28m across 2026/27 to 2027/28 Report 9.9, P35

Plain English for the jargon

  • One Hounslow Transformation reserve: The council's funding reserve used to deliver People Portfolio programmes.
  • One Hounslow Business Case: The council's business case approach, which adds an Equalities, Diversity and Inclusion Case and a Climate Impact Case to the standard HM Treasury five case model.
  • Delivery Plan: The set of programmes and projects across the People, Place, Capital and Digital Portfolios through which the council delivers its Corporate Plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Resolved : · Cabinet noted progress to date with the programmes within the People Portfolio as set out in Appendix 1 of the submitted report. · Cabinet noted progress to date with the projects within the Place Portfolio as set out in Appendix 2 of the submitted report. · Cabinet noted progress to date with the projects within the Capital Portfolio as set out in Appendix 3 of the submitted report. Cabinet noted progress to date with the projects within the Digital Portfolio as set out in Appendix 4 of the submitted report.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 15 pages

Report for: INFORMATION

Contains Confidential N or Exempt Information

Cabinet Key Decision N

Report Title Delivery Plan Monitoring Q3 2025/26

Member Reporting Councillor Shantanu Rajawat Leader of the Council and Portfolio Holder for Strategy, Resources and External Affairs

Contact Details Andrew Cox, Director of Climate and Strategic Programmes [email protected] Mark Lumley, Director of Digital, IT and Resilience [email protected]

For Consideration By Cabinet

Date to be Considered 16 March 2026

Deadline for call-in 24 March 2026

Implementation Date 25 March 2026 (if not Called In)

Affected Wards All wards

Approved by Andrew Cox, Director of Climate and Strategic Programmes Mark Lumley, Director of Digital, IT and Resilience

Official 1. Recommendations

Cabinet is asked to:

1. Note progress to date with the programmes within the People Portfolio as set out in Appendix 1

2. Note progress to date with the projects within the Place Portfolio as set out in Appendix 2

3. Note progress to date with the projects within the Capital Portfolio as set out in Appendix 3

4. Note progress to date with the projects within the Digital Portfolio as set out in Appendix 4

2. Report Summary

2.1The Delivery Plan was approved by Cabinet on 5 July 2022 and Council on 20 September 2022.

2.2This report provides an update to Cabinet on progress with the Delivery Plan, with a particular focus on progress to date on projects and programmes within all four portfolios, highlighting their overall status, what has been achieved and the key activity planned over the coming period.

3. Background and links to Corporate Priorities

3.1The Delivery Plan, which was approved by Cabinet on 5 July 2022 and Council on 20 September 2022, describes the activity that the Council will deliver to meet the priorities, objectives and ambitions set out within the Corporate Plan 2022-2026, as well as the process and approach that will be followed to monitor progress and ensure success.

3.2It details the Council’s large, ambitious programmes and projects that impact across the whole (or large part of) the organisation, place or population. It also details the activity that is taking place to ensure that the Council has the required systems, processes and structures established and is prioritising its capital investment to enable the delivery of high-quality public services.

3.3All projects and programmes in the Delivery Plan follow the One Hounslow Approach to Project and Programme Management (PPM), with business case development, benefits tracking and regular monitoring being fundamental to this approach. The approach is recognised as adding rigour and corporate visibility to ensure well informed decision-making in accordance with the strategic priorities set out in the Corporate Plan.

3.4In December 2022, as part of the Delivery Plan Monitoring Q2 2022/23 report, Cabinet agreed that the Delivery Plan be split into two portfolios: People and

Official Place. The People Portfolio is made up of programmes and projects associated with transforming the council’s services and offer to residents. The Place Portfolio is made up of programmes and projects associated with the development activity to the built and natural environment, primarily capital funded, to transform a place in line with the council’s strategic objectives.

3.5In March 2023, as part of the Delivery Plan Monitoring Q3 2022/23 report, Cabinet agreed to the creation of the Capital Portfolio, recognising that whilst the two portfolios represented a large proportion of the council’s project activity, much of which is capital funded, they did not include the totality of the capital spend. The Capital Portfolio is made up of capital funded programmes and projects that are not in scope of either the People or Place Portfolios. Monitoring of the Capital Portfolio in this report is aligned to the programme headings in the 2023/24 – 2026/27 Capital Programme approved by Council in February 2023.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Delivery Plan Monitoring 2025-26 (Q3): Appendix 1 PeopleAppendix 6 pages Download
PDF
Delivery Plan Monitoring 2025-26 (Q3): Appendix 2 PlaceAppendix 16 pages Download
PDF
Delivery Plan Monitoring 2025-26 (Q3): Appendix 3 CapitalAppendix 11 pages Download
PDF
Delivery Plan Monitoring 2025-26 (Q3): Appendix 4 DigitalAppendix 17 pages Download
PDF
Delivery Plan Monitoring 2025-26 (Q3)Report 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Delivery Plan Monitoring 2025-26 (Q3)This decision
  2. Delivery Plan Monitoring - Q4 2025/26Agreed
  3. Charlton House and Albany Estate Regeneration Delivery PlanApproved
  4. Delivery Plan Monitoring - Q4 2024-25Noted
  5. Charlton House and Albany House Estate Regeneration Delivery PlanNoted
  6. Initiation of Enforcement Review Project with the Council's Delivery PlanApproved

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies