Noted variations in the 2005/06 approved Capital Programme, their estimated capital and revenue impact and approved in the programme of £151,000 for the Car Park Strategy Scheme and associated staffing costs of £59,000 as outlined in paragraphs 2.3 and 2.4 of the report
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
MONITORING OF THE CAPITAL PROGRAMME – 2005/06 (Report by the Head of Financial Services)
1. PURPOSE
1.1This report highlights the variations from the currently approved Capital Programme (as updated for any member or officer decisions already taken in accordance with the Code of Financial Management).
1.2More detailed information on specific schemes can be obtained from the relevant Head of Service.
2. MONITORING INFORMATION
2.1The Budget and Medium Term Plan approved in February and any subsequent adjustments are shown below:-
Gross External Net Budget Contributions Budget Capital £000 £000 £000 Approved (February 2005) 27,658 4,571 23.087 Delayed/Deferred from 2004/05 (21 July 2005) 5,760 1,008 4,752 Cabinet approved variations • Sawtry Leisure Centre (21 July 2005) 214 0 214 • Barriers/Lighting, St Neots Riverside (21 July 2005) 30 0 30 • Savings required to finance part of above approvals (21 -84 0 -84 July 2005) • Sapley Square Development from Capital Receipts (28 620 0 620 April 2005) • Franking Machine at Pathfinder House from Revenue (28 12 0 12 April 2005) • Ramsey and District Community Bus – Grant from 10 0 10 Revenue (21 July 2005) • Revenue items recharged to Capital (21 July 2005) 147 0 147 • Huntingdon Town Centre Development (13 October 2005) -55 0 -55 Changes in funding arrangements (para 2.2) -375 -375 0 Financing correction to Capital Receipts (para 2.3) 151 0 151 Revenue items recharged to Capital (para. 2.4) 59 0 59 Total Capital Budget 34,147 5,204 28,943
Revenue Cabinet approved variations • Franking Machine at Pathfinder House to Capital (28 April -12 0 -12 2005) • Ramsey and District Community Bus – Grant to Capital -10 0 -10 (21 July 2005) • Revenue items recharged to Capital (21 July 2005) -147 0 -147 Huntingdon Town Centre Development (13 October 2005) 55 0 55 Revenue items recharged to Capital (para. 2.4) -59 0 -59 Total -173 0 -173 2.2 The capital programme was based on the Council jointly funding certain schemes with the County Council. The budget assumed the total cost would be this Council’s gross expenditure but we would receive a capital contribution from the County. It has now emerged that some of the schemes will be undertaken by the County and we will make our contribution to them. This adjustment therefore corrects the gross cost with no change to the net cost.
2.3When the budget was prepared a capital receipt was incorrectly netted off of the cost of the Implementation of Car Park Strategy scheme. This has been corrected by increasing the capital programme by £151k. The capital receipts assumptions will be increased correspondingly so that there will be no eventual net increase in the revenue budget.
2.4The budget is based on an assumed level of staff time being charged to capital in order to support the delivery of capital schemes. It is now forecast that this sum will need to increase by a further £59k. This will result in a corresponding saving to the revenue budget.
2.5The current expected variations from the Budget are highlighted below:-
Gross External Net Cost Contributions Cost £000 £000 £000 Capital Budget (as adjusted above) 34,147 5,204 28,943 Forecast Variation Previously reported (21 July) -7,107 -190 -6,917 Additional items this time -3,020 -459 -2,561
Reasons for Additional Variation Project Delays/Deferrals to 2006/07 -2,981 -459 -2,522 Savings -39 0 -39 -3,020 -459 -2,561
2.6Annex A shows, for each scheme, any variation in the planned completion date or the scheme cost. The final page of the Annex defines the content of each column.
2.7Delays/Deferrals to 2006/07 The additional spending now expected to be delayed or deferred to next year is detailed below:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.