Resolved
noted the spending variations for the revenue budget for 2010/1011, the present position in terms of the revenue budget for 2011/12 outturn and position on debts collected and written-off.
Cabinet noted this item on Thursday 21 July 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
noted the spending variations for the revenue budget for 2010/1011, the present position in terms of the revenue budget for 2011/12 outturn and position on debts collected and written-off.
CABINET 21 JULY 2011
2010/11 OUTTURN AND 2011/12 REVENUE BUDGET MONITORING (Report by the Head of Financial Services)
1 INTRODUCTION
1.1The 2010/11 accounts have now been completed and submitted for audit. This report compares the total outturn with the original budget and the forecast assumed in the current MTP (Para. 2). It also compares this in more detail – firstly at controllable level by Senior Manager with explanations of the main variations (Annex A) and then at service level (Annex B).
1.2It also considers the initial variations in the current year’s budget.
1.3Finally it reports on the amounts collected and debts written off in the first quarter of 2011/12.
2 GENERAL FUND OUTTURN 2010/11
2.1The table below shows a comparison of the original budget, the forecast used to produce the MTP and the actual outturn for the year.
Original Forecast Outturn Budget for £000 MTP £000 £000 Approved budget 24,848 24,848 24,848 Delayed spending from 2009/10 274 370 370 Variations -1,699 -1,167 Projects delayed to 2011/12 -274 -370 -559 Net spending 24,848 23,149 23,492
Government support -12,940 -12,940 -12,940 Council tax -7,273 -7,273 -7,273 Collection fund adjustment 35 35 35 Reserves Use of delayed projects reserve -274 -370 -370 Contribution to delayed projects reserve 274 370 559 Special reserve 0 0 -1,554 General reserves -4,670 -2,971 -1,949 Total reserves -4,670 -2,971 -3,314 Total -24,848 -23,149 -23,492
2.2The outturn of £23.5m was £1.4M below the original budget. This included the deferral to the current year of items amounting to £0.6M and the spending of £1.6m on redundancies which is funded from the Special Reserve. As a result £1.9M will be taken from the general fund reserve to meet the budget deficit.
2.3A major part of this saving is due to service managers recognising the financial issues facing the Council and holding posts vacant wherever possible in order to be ready to deliver targeted savings for the current year. £0.6M was due to approved projects not happening as quickly as planned due to circumstances beyond our control but this will simply slip to the current year rather than create a real saving. The main savings result from NNDR revaluation appeals (-£0.2M), reduced operating costs for One Leisure (-£0.3M), concessionary Fares (-£0.2M), staff vacancies (- £0.3M), interest (-£0.1M), recycling gate fees (-£0.2M) and the A14 Enquiry (-£0.2M). There were some additional costs including development management fees (+£0.3M) and government grants (+£0.3M).
2.4For the future, the key element is the variation from the assumed use of reserves on which the MTP was based as this highlights the future impact on the Council. The MTP was based on a £3M use of revenue reserves to meet the budget deficit and so the Council will now have an extra £1M in its reserves.
2.5Cabinet have received monitoring reports at regular intervals throughout the year. The last was in April and forecast a £2.5M use of reserves. The table in Annex C shows the £0.6M of net savings that have emerged since that time.
2.6Variations can, and will, emerge right up until the accounts are finalised each year but there should be few significant items that could not have been more effectively forecast. The scale of variations that emerged this year, particularly in the light of our financial situation, are too high and discussions have taken place at the Senior Management Group (Managing Directors and Heads of Service) to stress the need for managers to give higher priority to the accurate forecasting of the outturn throughout the year.
2.7However, the reduced need to use reserves is clearly of significant benefit to the Council as it allows some extra flexibility in the speed with which the future savings target of £2M per year will have to be achieved. The Financial Strategy report in September will report on the progress with which already identified savings are being achieved and progress in finding the extra savings.
3. REVENUE MONITORING 2011/12
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revenue Monitoring: 2010/11 outturn and 2011/12 revenue budgetReport | 195 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.