Resolved
RESOLVED that the revenue and capital forecast variances from the budget for 2012/13 based on the second quarter’s full monitoring to Cabinet be noted.
Economic Development Cabinet Committee noted this item on Wednesday 9 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the revenue and capital forecast variances from the budget for 2012/13 based on the second quarter’s full monitoring to Cabinet be noted.
Members of the Cabinet Committee are asked to note the second quarter’s full budget monitoring report for 2012/13 reported to Cabinet on 3 December 2012.
FOR INFORMATION
1. Introduction:
1.1This is a regular report to this Committee on the forecast outturn for the Regeneration and Economic Development Portfolio.
2.1A detailed quarterly monitoring report is presented to Cabinet, usually in September, December and March and a draft final outturn report in either June or July. These reports outline the full financial position for each portfolio and will be reported to Cabinet Committees after they have been considered by Cabinet. In the intervening months an exception report is made to Cabinet outlining any significant variations from the quarterly report. The second quarter’s monitoring report for 2012/13 is attached.
3. Regeneration and Economic Development Portfolio 2012/13 Financial Forecast - Revenue
3.1There are no exceptional revenue changes since the writing of the attached quarter 2 report.
4. Regeneration and Economic Development Portfolio 2012/13 Financial Forecast - Capital
4.1There are no capital movements from the attached quarter 2 report.
5. Recommendations 5.1 Members of the Economic Development Cabinet Committee are asked to note the revenue and capital forecast variances from budget for 2012/13 based on the second quarter’s full monitoring to Cabinet.
Jackie Hansen Business Strategy and Support Finance Business Partner Tel 01622 69(4054) Email [email protected] BUSINESS STRATEGY & SUPPORT DIRECTORATE (EXTRACT) SUMMARY SEPTEMBER 2012-13 FULL MONITORING REPORT
1. FINANCE
1.1REVENUE
1.1.1 All changes to cash limits are in accordance with the virement rules contained within the constitution, with the exception of those cash limit adjustments which are considered “technical adjustments” i.e. where there is no change in policy, including: § Allocation of grants and previously unallocated budgets where further information regarding allocations and spending plans has become available since the budget setting process. § Cash limits for the A-Z service analysis have been adjusted since the quarter 1 monitoring report to reflect a number of technical adjustments to budget including the centralisation of training budgets and room hire budgets. § The inclusion of a number of 100% grants (i.e. grants which fully fund the additional costs) awarded since the budget was set. These are detailed in Appendix 1 of the executive summary. 1.1.2 Table 1 below details the revenue position by A-Z budget:
Budget Book Heading Cash Limit Variance Comment G I N G I N £'000s £'000s £'000s £'000s £'000s £'000s Business Strategy & Support Regeneration & Enterprise portfolio Directorate Management & Support 166 0 166 5 0 5 Development Staff & Projects 4,892 -1,389 3,503 43 -48 -5
Total R&E portfolio - BSS 5,058 -1,389 3,669 48 -48 0
1.1.3 Major Reasons for Variance:
None
1.1.4 Actions required to achieve this position:
None
1.1.5 Implications for MTP:
The MTFP assumes a breakeven position for 2012-13.
1.1.6 Details of re-phasing of revenue projects:
None
1.1.7 Details of proposals for residual variance: [eg roll forward proposals; mgmt action outstanding]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Regeneration and Economic Development Portfolio Financial Monitoring 2012/13Report | 6 pages | DownloadRead as text |
Follow Economic Development Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jan 2014 | Unlocking the Potential: Going for Growth: The Kent and Medway Growth Plan(a) That the report be noted (b) That Ross Gill (Economic Strategy and Policy Manager) be thanked for his work to pro... | Noted | Open |
| 23 Jan 2014 | Minutes of the meeting held on 3 December 2013RESOLVED that the Minutes of the meeting held on 3 December 2013 were correctly recorded and that they be signed by t... | Decided | Open |
| 23 Jan 2014 | Verbal Update by Cabinet MemberRESOLVED that the information given in the verbal update be noted. | Noted | Open |
| 23 Jan 2014 | PRESENTATIONS:- Kent Savers Credit Union and Linkages to Trading Standards Loan Sharks Project - Gail Devries, Chairman of the Board and Kent Loan Sharks Project(a) That the report be noted; (b) That the presentations and the responses to comments and be noted. | Noted | Open |
| 23 Jan 2014 | New Leader Programme 2014-2020RESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.