Resolved
RESOLVED that the revenue and capital forecast variances from budget for 2012/13 based on the first quarter’s full monitoring to Cabinet be noted.
Economic Development Cabinet Committee noted this item on Friday 21 September 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the revenue and capital forecast variances from budget for 2012/13 based on the first quarter’s full monitoring to Cabinet be noted.
Members of the Cabinet Committee are asked to note the first quarter’s full budget monitoring report for 2012/13 reported to Cabinet on 17 September 2012.
FOR INFORMATION
1. Introduction:
1.1This is a regular report to this Committee on the forecast outturn for Regeneration and Economic Development Portfolio.
2.1A detailed quarterly monitoring report is presented to Cabinet, usually in September, December and March and a draft final outturn report in either June or July. These reports outline the full financial position for each portfolio and will be reported to Cabinet Committees after they have been considered by Cabinet. In the intervening months an exception report is made to Cabinet outlining any significant variations from the quarterly report. The relevant sections from the annexes from the first quarter’s monitoring report for 2012/13 for the Business Strategy and Support, and Environment, Highways and Waste Directorates are attached.
3. Regeneration and Economic Development Portfolio 2012/13 Financial Forecast - Revenue
3.1There are no exceptional revenue changes since the writing of the attached quarter 1 report.
4. Regeneration and Economic Development Portfolio 2012/13 Financial Forecast - Capital
4.1There are no exceptional capital changes since the writing of the attached quarter 1 report. 5. Recommendations
5.1Members of the Economic Development Cabinet Committee are asked to note the revenue and capital forecast variances from budget for 2012/13 based on the first quarter’s full monitoring to Cabinet.
Jackie Hansen Business Strategy and Support Finance Business Partner Tel 01622 69(4054) Email [email protected] BUSINESS STRATEGY & SUPPORT DIRECTORATE SUMMARY JUNE 2012-13 FULL MONITORING REPORT (EXTRACT)
1. FINANCE
1.1REVENUE
1.1.1 The cash limits that the Directorate is working to, and upon which the variances in this report are based, include adjustments for both formal virement and technical adjustments, the latter being where there is no change in policy. The Directorate would like to request formal virement through this report to reflect adjustments to cash limits for changes required in respect of the allocation of previously unallocated budgets, where further information regarding allocations and spending plans has become available since the budget setting process and to reflect adjustments required as a result of the finalisation of restructuring. Within the Regeneration and Economic Development portfolio, there have been revisions to the Development Staff and Projects budget to reflect changes in the external funding of a number of projects. This has increased gross by £1.093m and income by £1.055m; the difference of +£0.038m on gross is a correction to the element of this budget that sits within the Enterprise and Environment Directorate and therefore a corresponding reduction is shown within Annex 4 of this report.
Table 1a shows: § the published budget, § the proposed budget following adjustments for both formal virement and technical adjustments, together with roll forward from 2011-12 as approved by Cabinet in July and the inclusion of 100% grants (i.e. grants which fully fund the additional costs) awarded since the budget was set. These are detailed in Appendix 1 to the executive summary, § the total value of the adjustments applied to each A-Z budget line.
Cabinet is asked to approve these revised cash limits
Table 1b shows the latest monitoring position against these revised cash limits.
1.1.2.1 Table 1a below details the change in cash limits by A-Z budget since the published budget:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Regeneration and Economic Development Portfolio Financial Monitoring 2012/13Report | 9 pages | DownloadRead as text |
Follow Economic Development Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jan 2014 | Unlocking the Potential: Going for Growth: The Kent and Medway Growth Plan(a) That the report be noted (b) That Ross Gill (Economic Strategy and Policy Manager) be thanked for his work to pro... | Noted | Open |
| 23 Jan 2014 | Minutes of the meeting held on 3 December 2013RESOLVED that the Minutes of the meeting held on 3 December 2013 were correctly recorded and that they be signed by t... | Decided | Open |
| 23 Jan 2014 | Verbal Update by Cabinet MemberRESOLVED that the information given in the verbal update be noted. | Noted | Open |
| 23 Jan 2014 | PRESENTATIONS:- Kent Savers Credit Union and Linkages to Trading Standards Loan Sharks Project - Gail Devries, Chairman of the Board and Kent Loan Sharks Project(a) That the report be noted; (b) That the presentations and the responses to comments and be noted. | Noted | Open |
| 23 Jan 2014 | New Leader Programme 2014-2020RESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.