Resolved
RESOLVED that the revenue and capital forecast variances from budget for 2012/13 based on the last exception report be noted.
Economic Development Cabinet Committee noted this item on Wednesday 6 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the revenue and capital forecast variances from budget for 2012/13 based on the last exception report be noted.
Members of the Cabinet Committee are asked to note that the second quarter’s full budget monitoring report for 2012/13 was reported to Cabinet on 3 December 2012. Members of the Cabinet Committee are also asked to note the subsequent update to this position which was reported in the monitoring exception report to Cabinet on 23 January 2013.
FOR INFORMATION
1. Introduction:
1.1This is a regular report to this Committee on the forecast outturn for the Economic Development Portfolio.
2.1A detailed quarterly monitoring report is presented to Cabinet, usually in September, December and March and a draft final outturn report in either June or July. These reports outline the full financial position for each portfolio and will be reported to Cabinet Committees after they have been considered by Cabinet. In the intervening months an exception report is made to Cabinet outlining any significant variations from the quarterly report. The relevant extracts from the last exception report presented to Cabinet on 23 January are included in the revenue and capital sections below.
3. Regeneration and Economic Development Portfolio 2012/13 Financial Forecast - Revenue
3.1The forecast remains at a nil variance with no movements reported in the exception report following the quarter 2 report provided to Cabinet Committees in January. 4. Regeneration and Economic Development Portfolio 2012/13 Financial Forecast - Capital
4.1Table 1 shows the revised approved budget in the exception report following the quarter 2 report provided to Cabinet Committees in January.
Regeneration & Enterprise £m Approved budget last reported to 104.392 Cabinet Approvals made since last Cabinet -0.165 meeting Revised approved budget 104.227
Table 2 shows a summary of the variance.
Forecast Movement Variance from Qtr 2 report £m £m Unfunded variance 0.000 0.000 Funded Variance 0.000 0.000 Variance to be funded from revenue 0.000 0.000 Project underspend -0.282 +0.002 Rephasing (to/from beyond 2012-15) -22.083 -5.773 Total Variance -22.365 -5.771
Within the forecast movement, the main projects subject to re-phasing and overall variances are detailed below:
4.2Movements in unfunded variance There have been no movements in unfunded variance since the quarter 2 report.
4.3Movements in re-phasing (to/from beyond 2012-15) Movements since the quarter 2 report are detailed below:
Regional Growth Fund (REG) -£5.724m: The forecast has now been realigned to show actual payments to be made rather than committed funds.
The other -£0.049 movement on re-phasing is a result of small movements less than £0.100m.
4.4Other movements
Eurokent (REG) -£0.284m: There is a forecast underspend on Eurokent due to a reduction in the forecast of compensation claims which are payable under the Land Compensation Act Part 1. 4.5 Key Issues & Risks Rural Broadband (REG): is re-phasing within the three year period (2012-15), mainly due to further rounds of the grant schemes having been temporarily placed on hold, pending the outcome of the Kent and Medway BDUK procurement and until the DEFRA bidding rounds have concluded (to reduce the risk of displacing the draw-down of national funding). BDUK are also advising local authorities that they should consider holding a contingency for the BDUK - particularly to address any differences between budgeted tender provision and final procured costings. A view will be taken as to whether the rural community funding should be used as a contingency once the outcome of the BDUK procurement, surveys and delivery plan are known or to fund delivery to areas not currently included in the procurement.
There are no other new key issues and risks to report since those previously reported to Cabinet.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Regeneration and Economic Development Portfolio Financial Monitoring 2012/13Report | 3 pages | DownloadRead as text |
Follow Economic Development Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jan 2014 | Unlocking the Potential: Going for Growth: The Kent and Medway Growth Plan(a) That the report be noted (b) That Ross Gill (Economic Strategy and Policy Manager) be thanked for his work to pro... | Noted | Open |
| 23 Jan 2014 | Minutes of the meeting held on 3 December 2013RESOLVED that the Minutes of the meeting held on 3 December 2013 were correctly recorded and that they be signed by t... | Decided | Open |
| 23 Jan 2014 | Verbal Update by Cabinet MemberRESOLVED that the information given in the verbal update be noted. | Noted | Open |
| 23 Jan 2014 | PRESENTATIONS:- Kent Savers Credit Union and Linkages to Trading Standards Loan Sharks Project - Gail Devries, Chairman of the Board and Kent Loan Sharks Project(a) That the report be noted; (b) That the presentations and the responses to comments and be noted. | Noted | Open |
| 23 Jan 2014 | New Leader Programme 2014-2020RESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.