Resolved
RESOLVED that the revenue and capital forecast and variances from the budget for 2013/14 for the Regeneration and Economic Development Portfolio based on the second quarter’s full monitoring to Cabinet be noted.
Economic Development Cabinet Committee noted this item on Tuesday 3 December 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the revenue and capital forecast and variances from the budget for 2013/14 for the Regeneration and Economic Development Portfolio based on the second quarter’s full monitoring to Cabinet be noted.
EXTRACT FROM ENTERPRISE & ENVIRONMENT DIRECTORATE SUMMARY SEPTEMBER 2013-14 MONITORING REPORT
1. REVENUE
1.1Cash Limit Variance Before Mgmt Action Management Action Net Variance after Mgmt Action Directorate Total (£k) - - - -
1.2Table 1 below details the revenue position by A-Z budget:
Cash Limit Variance Management Action/ Budget Book Heading Explanation Gross Income Net Net Impact on MTFP £'000 £'000 £'000 £'000 £'000 Regeneration & Enterprise portfolio Development Staff & Projects 656.6 -656.6 0.0 0
Total E&E controllable 656.6 -656.6 0.0 0
Assumed Mgmt Action - R&E portfolio Total Forecast after mgmt 656.6 -656.6 0.0 0 action EXTRACT FROM BUSINESS STRATEGY & SUPPORT DIRECTORATE SUMMARY BUSINESS STRATEGY AND SUPPORT (EXCL. PUBLIC HEALTH) SUMMARY SEPTEMBER 2013-14 MONITORING REPORT
1. REVENUE
1.1Cash Limit Variance Before Mgmt Action Management Action Net Variance after Mgmt Action Total (£k) +3,882 - - -
1.2Table 1 below details the revenue position by A-Z budget:
Cash Limit Variance Management Action/ Budget Book Heading Explanation Gross Income Net Net Impact on MTFP £'000 £'000 £'000 £'000 £'000 Regeneration & Enterprise portfolio Directorate Management & 172.2 0.0 172.2 +3 Support Development Staff & Projects 5,043.7 -1,333.7 3,710.0 -3 Total R&E portfolio 5,215.9 -1,333.7 3,882.2 0
Assumed Management - R&E portfolio
Total Forecast after mgmt 5,215.9 -1,333.7 3,882.2 0 action 2. CAPITAL
2.1The working budget for 2013-14 is £38,308k. The forecast outturn against the 2013-14 budget is £36,955k giving a variance of - £1,353k.
2.2Table 2 below details the Regeneration and Economic Development Capital Position by Budget Book line.
Three 2013-14 2013-14 Variance year Working Variance Break- Rephasing / Real Explanation of In-Year Project Explanation of Project Budget Book Heading cash Budget down Variance and Funding Actions Variance Status 1 Status limit Stream (£000) (£000) (£000) (£000) Individual Projects Dover Priory Station 0 -3 0 0 Green Approach Road
Broadband 23,500 2,650 0 0 Green Empty Property 7,500 3,710 0 0 Green Initiative Eurokent Road (East 65 84 -69 -69 Rephasing Green Kent) Folkestone Heritage 380 402 -300 -300 Rephasing Re-alignment of budget Green Quarter to agree with updated project plan, this has not affected the completion date. Incubator 0 262 0 0 Green Development LIVE Margate 6,800 6,508 0 0 Green Managed Work Space 160 174 0 0 Green - The Old Rectory Marsh Million 0 100 0 0 Green No Use Empty - 750 750 0 0 Green Rented Affordable Homes Old Town Hall 94 25 0 0 Green Regeneration Fund 5,061 3,555 0 0 Green Projects Three 2013-14 2013-14 Variance year Working Variance Break- Rephasing / Real Explanation of In-Year Project Explanation of Project Budget Book Heading cash Budget down Variance and Funding Actions Variance Status 1 Status limit Stream (£000) (£000) (£000) (£000) Regional Growth 37,200 14,384 0 0 Green Fund, including Expansion East Kent Rural Broadband 1,897 1,568 -984 -984 Re-phasing Spend will be incurred on Green Demonstration Project four or five local schemes this year with the remainder of the funding being kept as a contingency. The rephasing is not expected to impact on the completion date of the overall project. Swale Parklands 0 65 0 0 Green TIGER 20,000 4,000 0 0 Green Tram Road/Tontine 0 74 0 0 Green Street Road Works
Total 103,407 38,308 -1,353 -1,353
1. Status:
Green – on time and within budget Amber – either delayed completion date or over budget Red – both delayed completion and over budget
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item C1: Regeneration and Economic Development Portfolio Financial MonitorReport | 4 pages | DownloadRead as text |
PDF |
Regeneration and Economic Development Portfolio Financial Monitoring 2013/14Report | 2 pages | Download |
Follow Economic Development Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jan 2014 | Unlocking the Potential: Going for Growth: The Kent and Medway Growth Plan(a) That the report be noted (b) That Ross Gill (Economic Strategy and Policy Manager) be thanked for his work to pro... | Noted | Open |
| 23 Jan 2014 | Minutes of the meeting held on 3 December 2013RESOLVED that the Minutes of the meeting held on 3 December 2013 were correctly recorded and that they be signed by t... | Decided | Open |
| 23 Jan 2014 | Verbal Update by Cabinet MemberRESOLVED that the information given in the verbal update be noted. | Noted | Open |
| 23 Jan 2014 | PRESENTATIONS:- Kent Savers Credit Union and Linkages to Trading Standards Loan Sharks Project - Gail Devries, Chairman of the Board and Kent Loan Sharks Project(a) That the report be noted; (b) That the presentations and the responses to comments and be noted. | Noted | Open |
| 23 Jan 2014 | New Leader Programme 2014-2020RESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.