23/00038 - Fastrack Electrification - Land matters
AgreedExecutive2 papers
Growth, Environment & Transport Cabinet Committee agreed this item on Tuesday 23 May 2023. Below is the council's own wording, with the papers it was decided on.
RESOLVED to endorse the Cabinet Member for Highways and Transport on the proposed decision to authorise the Director of Infrastructure in consultation with the Corporate Director of Growth Environment and Transportation to agree all necessary contractual arrangements relating to land and property matters to facilitate the Fastrack Electrification schemes at Thameside and Dover.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 4 pages
From: David Brazier, Cabinet Member for Highways & Transport
Simon Jones, Corporate Director of Growth, Environment and Transport
To: Environment & Transport Cabinet Committee - 23 May 2023
Subject: Fastrack electrification – land matters
Decision Number: 23/00038
Classification: Unrestricted
Future Pathway of report: Cabinet Member Decision
Electoral Division: Dartford East, Dartford North East, Dartford Rural, Dartford West, Dover North, Dover Town, Dover West, Gravesham East, Northfleet & Gravesend West and Swanscombe & Greenhithe
Summary: Under decision 22/00086 the Cabinet Member for Highways and Transport agreed the delivery of three Fastrack Electrification Sites, two for Fastrack Thameside and one site for Fastrack Dover.
It has become apparent that several of the property and land related decisions may fall outside of the usual delegations outlined in KCC’s Constitution, specifically its Property Management Protocol.
As a precaution, and to ensure that the project can progress to time, a further decision is required, delegated to the Director of Infrastructure, whose team will conduct negotiations as necessary on behalf of KCC’s public transport team, to ensure that all property related decisions can be made efficiently.
Recommendation(s): The Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Highways and Transport on the proposed decision to authorise the Director of Infrastructure in consultation with the Corporate Director of Growth Environment and Transportation to agree all necessary contractual arrangements relating to land and property matters to facilitate the Fastrack Electrification schemes at Thameside and Dover as shown at Appendix A.
1. Introduction
1.1The decision to progress with the procurement process to implement the electrification of Fastrack Bus Services in Kent, using ZEBRA funding was taken by David Brazier, Cabinet Member for Highways and Transport on 30 September 2022.
1.2This further decision is requested to allow KCC Fastrack team and the KCC property/ infrastructure team to progress and finalise land matters and enter into legal agreements with relevant District Councils, Network Rail, and other parties to allow the Fastrack electric bus charging solution to be installed as per the proposed timeline.
2. Body of the report
2.1Fastrack is Kent County Council’s Bus Rapid Transit (BRT) flagship operation at Thameside, and a new Fastrack Dover BRT service is due to begin during 2024.
2.2The new Fastrack Thameside electric operator service is due to start operating with a new electric bus fleet from November 2024 and is currently in a procurement process for a new Fastrack electric operator with contract award due June 2023.
2.3The electric charging infrastructure to support Fastrack needs to be installed and tested with the new zero emission buses at least one month before the start of the electric operations at both Thameside and Dover. A Fastrack Electric Charging Infrastructure Solution Contractor is currently in procurement with contract award due during October 2023.
2.4The Fastrack Electric Bus charging infrastructure is proposed to be installed during 2024 at:
1. Acacia Hall car park, Dartford 2. Gravesend Bus Hub, Gravesend 3. Dover Priory Station, Dover
2.5Fastrack electrification land matters include but is not limited to:
Land leases Land Agreements for the duration of the Fastrack EV charging solution contract Easements/wayleaves Various license arrangements Other legal land matters documentation as required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.