Highway Term Maintenance Service Commissioning Programme Update

Noted Executive 1 paper

Growth, Environment & Transport Cabinet Committee noted this item on Tuesday 23 May 2023. Below is the council's own wording, with the papers it was decided on.

Item156

Resolved

RESOLVED to note and comment on the report.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 4 pages

From: David Brazier, Cabinet Member for Highways & Transport

Simon Jones, Corporate Director, Growth, Environment and Transport

To: Environment and Transport Cabinet Committee – 23 May 2023

Subject: Highway Term Maintenance Service Commissioning Programme

Classification: Unrestricted

Past Pathway of Paper: N/A

Future Pathway of Paper: Environment and Transport Cabinet Committee; Cabinet Member Decision

Electoral Division: All

Summary: Kent County Council is the Statutory Authority responsible for the delivery of highways services to Kent residents. Many of these services are delivered through a Highways Term Maintenance Contract (HTMC). The prevailing contract will expire on 31 August 2023. A new commissioning programme to replace this contract is expected to take 27-months.

This paper identifies market risks and outlines the commissioning programme required to deliver a replacement contract.

Recommendation: The Cabinet Committee is asked to note and comment on the report.

1. Introduction

1.1Kent County Council (KCC) is the Statutory Authority responsible for the delivery of highway services for the residents of Kent (excluding Medway). The Highway Term Maintenance Contract (HTMC) is delivered by Amey Highways Ltd and the contract is managed by Highways and Transportation (H&T).

1.2The current arrangement commenced on 1 September 2011 and has been worth between £40m and £50m per annum split across revenue and capital budgets and has relied upon both grant and KCC funding. Several key services are delivered through this contract including:

 Winter Service Provision – i.e. gritting of our major routes during freezing conditions.  Drainage Maintenance and Capital Projects – i.e. gully cleansing and drainage repairs.  Structures Maintenance – i.e. bridge repairs and construction.  Patching and Small Resurfacing Services – i.e. pothole and surface defect repairs.  Surface Treatments – i.e. road and footway surface preservation and life extension.  Emergency Response – i.e. supporting emergency services in response to incidents across the network including weather events and structural failure.  Highway Schemes Delivery – i.e. construction of highway improvement schemes, including those for crash remedial measures and s106 requirements.

1.3Whilst the current contract is due to expire on 31 August 2023 work is nearing completion to secure a final extension to this contract which will see the expiry of the contact be revised to 30 April 2026.

1.4This paper outlines the pathway to recommission this contract to ensure continuity of operational service from May 2026.

2. Current Market Capacity

2.1The industry is experiencing significant volatility due to the impact and aftermath of COVID-19 and the war in Ukraine. The consequence of these and other market challenges has seen widescale problems in the supply of materials, skilled and unskilled labour and increasing fuel and financing costs. This has led to large uplifts in inflation with many indices (e.g. RPI, CPI and BCIS) forecasting be between 10% and 30% over the past 12-18 months.

2.2It is expected that this market uncertainty will remain for the short/medium term with some forecasting that it may take many years to normalise.

2.3Local authorities that are procuring new contracts are seeing highly volatile pricing, reduced supplier availability and tenderers seeking to transfer several critical risks back to the client.

2.4Initial conversations have identified that there remains congestion in the tendering programmes of many industries (including highways and construction). In this climate there remains little confidence that letting a contract at this time would deliver a contract that would be affordable or that it would represent best value over the longer-term.

2.5Market intelligence suggests that delaying procurement for a period of somewhere between 3-5 years should allow the market to stabilise.

2.6In summary the prevailing primary procurement risks include amongst others:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Term Maintenance Service Commissioning Programme UpdateReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Highway Term Maintenance Service Commissioning Programme UpdateThis decision
  2. 24/00086 - Highways Term Maintenance Contract 2026 AwardDecided
  3. Highways Term Maintenance Contract - Update and Next StepsAgreed
  4. Decision 23/00058 - Highway Term Maintenance Service ContractDecided
  5. 20/00015 - Highways Term Services Commissioning ProgrammeAgreed
  6. Proposed extension to the Highways Term Maintenance Contract currently let to Enterprise AOL (now Amey)Agreed

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies