Growth, Environment & Transport Cabinet Committee noted this item on Tuesday 23 May 2023. Below is the council's own wording, with the papers it was decided on.
RESOLVED to note the report and recommend that the Cabinet Member for Highways and Transport investigate the feasibility of the following measures for reducing the number of road closures in Kent: 1. Roads should only be closed when workers are present unless the works go all the way across the carriageway. 2. Whenever possible roads should be reopened when workers are not present such as at weekends and after hours. 3. Every road closure permit issued should have a condition of late evening work and weekend work to shorten the period of disruption. 4. The works on a site should be staged so that work which does not need closure is done before moving to the one metre safety rule needing closure on the opposite carriage way. 5. There must be better coordination between the main contractors whose schedules should be rearranged so that when one works behind road closed signs as many others as possible do their work at the same time. 6. Discover ways to get around the one metre rule, for instance with ramps on pavements or verges, allowing traffic to move partly over them. 7. There should be more unannounced inspections of ... view the full minutes text for item 157.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 7 pages
From: David Brazier, Cabinet Member for Highways and Transport
Haroona Chughtai, Director of Highways and Transportation
To: Environment & Transport Cabinet Committee – 23 May 2023
Subject: Temporary Road Closures – Update Report
Key decision: No
Classification: Unrestricted
Past Pathway of Paper: N/A
Future Pathway of Paper: N/A
Electoral Division: All Divisions
Summary: This report updates Members on the position regarding Temporary Road Closure applications and actions since report to this Cabinet Committee on 8th November 2022.
Recommendation: The Cabinet Committee is asked to note the revised details and follow up actions regarding Temporary Road Closure Applications.
1. Introduction
1.1A report detailing the Temporary Road Closure Application process and the statutory and associated regulatory process was presented to ETCC on 8th November 2022.
1.2A number of recommended actions were resolved at the committee namely:
a) note the 225% increase, from approximately 4833 to nearly 16,000 per year, in road closure permits issued between 2018 and 2022;
b) recommend that the Cabinet Member tasks highways officers with seeking to reduce the number of road closure permits issued in the county to levels of the year ending 2018, namely fewer than 5,000;
c) recommend that the Cabinet Member ensures that every road closure should carry conditions of extended hours and weekend working to shorten the disruption suffered by road users;
d) recommend that the Cabinet Member ensures there is a programme of rigorous enforcement of conditions and organisation of diversions; and
e) requests that Scrutiny Committee undertake a Short-Focused Inquiry into reducing the numbers of road closures in the county. 2. Update on Actions
2.1Action a) and action b). These relate to the volume of temporary road closures and a request to reduce.
2.2During the investigation into the volume of temporary closures an error in the reporting was discovered. The system had double counted several road closure applications where a closure had either been re-applied for and / or the date had changed. The closure would have only taken place once and not multiple times.
2.3The table below details the revised numbers for 20/21 and 21/22.
Number of applications Year received: Yearly total 2017/18 4,833 2018/19 6,224 2019/20 7,284 2020/21 9,991 2021/22 9,455 2022/23 10,736
Year Previously reported as: Actual volume 2020/21 12,027 9991 2021/22 15, 751 9455
2.3The temporary road closure applications for 2022/23 have been interrogated to consider both the works promoter and the relationship between planned and emergency road closures.
Works Promoter Planned Road Closure Emergency Road Closure Kent County 1073 2858 Council South East 352 1391 Water Southern Water 450 530 Southern Gas 848 150 Networks Openreach 1112 546 Thames Water 104 151 UK Power 333 287 Networks Other 426 125 Totals 4698 6038
2.4The increase in temporary road closures from 2018/19 has almost doubled over the past few years. This reflects the increasing number of organisations now seeking to access the highway to undertake critical work (e.g., utility companies, telecommunications, and developers – all with increasing numbers of sub-contractors of differing capability and experience of highway working).
2.5The permit process is bound by legislation and regulatory procedure. This protects both the works promoter and the highway authority but does place obligations and conditions on both parties.
2.6As the Highways Authority, KCC, through its Streetworks Team, administers the process (for a fee) whilst also seeking to mitigate the impact of the proposed works and coordinate it with other prevailing/competing works.
2.7It is important to note that when a works promoter meets the conditions of the scheme, KCC has no ability to refuse or reject the application and as such the opportunity to reduce permits remains limited especially during programmes of significant infrastructure modernisation which are stipulated by national regulators.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.