Growth, Environment & Transport Cabinet Committee agreed this item on Tuesday 23 May 2023. Below is the council's own wording, with the papers it was decided on.
RESOLVED to endorse the Cabinet Member for Highways and Transport on the proposed decision to: a) agree the Capital Drainage Framework for a maximum of four years; and b) provide the Corporate Director of Growth, Environment and Transport delegated authority to procure and enter into appropriate contractual arrangements for the provision of capital drainage works or other legal agreements, as necessary to implement the decision.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 6 pages
From: David Brazier, Cabinet Member, Highways and Transport
Simon Jones, Corporate Director, Growth, Environment and Transport
To: Environment and Transport Cabinet Committee – 23 May 2023
Subject: Capital Drainage Framework
Key decision: 23/00054
Past pathway of paper: N/A
Future pathway of paper: For Cabinet Member Decision
Electoral Division: All Divisions
Summary: The Capital Drainage Framework expired at the end of December 2022. Commissioned contracts through this framework are nearing their end. Due to the capital budget allocation for drainage works, there is still a requirement to procure a replacement framework to deliver this programme.
This framework will commence in the summer of 2023 and will continue for a maximum of four years. There is no workload guarantee in the framework agreement. A Key Decision is required to award the contract/s for this service as the value exceeds £1m.
Recommendation(s): The Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Highways and Transport on the proposed decision to:
a) agree the Capital Drainage Framework for a maximum of four years; and
b) provide the Corporate Director of Growth, Environment and Transport delegated authority to procure and enter into appropriate contractual arrangements for the provision of capital drainage works or other legal agreements, as necessary to implement the decision.
1. Introduction
1.1Commencing in the financial year of 2020/21, KCC Highways drainage team were allocated additional capital funding to start to address the prevailing backlog of drainage schemes. To ensure the programme was delivered, KCC procured a multi-contractor framework to supplement its Highway Term Maintenance Contract during this period.
1.2This framework expired in December 2022 with the outstanding call off contracts, which were commissioned before this date, soon due to expire. The future works programme requires a replacement framework.
1.3The works undertaken under this framework are deemed to be low risk and include but are not limited to the following activities:
Scheme works which may include new surface water drainage systems, including drains, pipe work, culverts, pumping stations, and/or new SUDS retro fit features, manholes/Catchpits, soakaways, gullies, improvement works to ponds and lagoons, etc. Routine maintenance, such as ironworks, ditching and siding, etc. Replace or repair damaged assets which may include broken pipes, deep bore of existing soakaways, broken covers, manholes, gullies, brickwork including headwalls, damaged culverts, etc. General Reinstatement works including carriageway repairs.
1.4The new framework is required to be operational by the summer of 2023 to meet the planned schedule of forthcoming drainage work.
2. Delivery Models
2.1Four options have been considered:
Option 1 – Do Nothing Allow for the outstanding contracts to lapse. The Authority would not be able to deliver the planned programme of work. This presents unacceptable operational, financial, and reputational risk. Discounted.
Option 2 – Extension of current framework There are no available contract extensions permissible in accordance with the Public Contracts Regulations 2015. Discounted.
Option 3 – Procure a replacement framework appointing three suppliers. Set up a new framework following a PCR 2015-compliant tender exercise and recognising the anticipated volume and scale of drainage improvements. Preferred Option.
Option 4 – Deliver in house. The Authority does not have the internal resources (people, plant, and facilities) to deliver this type of work in-house. The implementation cost and schedule would not be economically advantageous to meet the planned programme of work. Discounted.
3. Procurement Strategy (Preferred Option)
3.1Initial market engagement was undertaken in early 2023.
3.2This exercise identified areas of commercial and operational risk as far as:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.