Royal Borough of Kingston upon Thames
Response and Recovery Committee, Thursday 28 January 2021 at 7.30pm

Highways Maintenance and Management Services Contract Award

Decided Committee 1 paper

Response and Recovery Committee decided this item on Thursday 28 January 2021. Below is the council's own wording, with the papers it was decided on.

Item83

Resolved

RESOLVED that: 1) Following the procurement process set out below that the existing contracts pertaining to LB Sutton with R J Dance in relation to undertaking reactive highway maintenance works and F M Conway for planned highway works be extended to operate within the Royal Borough of Kingston upon Thames as permitted under the contract. 2) The contract will be for an initial period of 6 years with 3 possible annual extensions making a total period of 9 years (aligning with extant LB Sutton contract).
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Response and Recovery Committee

Highway Maintenance and Management Services Contract Award

Relevant Director: Sarah Ireland, Executive Director Corporate and Communities

Relevant Portfolio Holder: Councillor Hillary Gander, Portfolio Holder for Environment & Sustainable Transport

Purpose

To approve the extension of the existing contract geographical working areas from the London Borough of Sutton only to include the Royal Borough of Kingston upon Thames pertaining to R J Dance Ltd in relation to undertaking reactive highway maintenance works and F M Conway Ltd for planned highway works.

To ​RESOLVE​ that -

1. Following the procurement process set out below that the existing contracts pertaining to LB Sutton with R J Dance in relation to undertaking reactive highway maintenance works and F M Conway for planned highway works be extended to operate within the Royal Borough of Kingston upon Thames as permitted under the contract.

2. The contract will be for an initial period of 6 years with 3 possible annual extensions making a total period of 9 years (aligning with extant LB Sutton contract).

Benefits to the Community:

Kingston as Highway Authority has a statutory responsibility to ensure the highway network is managed and maintained to a safe standard and this has to continue beyond 31 March 2021. . There are therefore ongoing discussions taking place with incumbent operator Kier with regards to decommissioning their service and with F M Conway and R J Dance about the possibility of taking up contracts to deliver Highways Management and Maintenance Services for Kingston. This would provide a seamless service delivery across both authorities with efficiencies and economies of scale accruing to Kingston council, and with the local community being assured of a service that has been shown to provide value for money. .

Key Points

A. The council is responsible for management and maintenance of all its Highway assets, the current contract for this is with Kier, procured through the London Highway Authority Contract (LoHAC1) and is due to expire on 31 March 2021 with no possibility of extension.

B. The management of contracts is delivered by the Shared Environment Service (SES) for both the London Borough of Sutton (LB Sutton) and the Royal Borough of Kingston upon Thames (RB Kingston). The service is responsible for the maintenance and improvement of all publicly adopted highway surfaces and structures in both boroughs.

C. Various options were explored at the start of the procurement exercise. LB Sutton, through the SES, let two term service contracts in 2020 which had a provision for the RB Kingston to become part of those contractual arrangements if it could be shown to offer value for money. The two successful bidders were R J Dance for reactive and F M Conway for planned works.

D. Transport for London (TfL) have also re-tendered the LoHAC1 (new contract called LoHAC2) with London divided into three areas; southern, central and northern. Sutton and Kingston are in the southern area where the successful tenderer is F M Conway. Analysis has been undertaken to determine which contract will deliver the best value for money for Kingston; the Sutton arrangement or LoHAC2; it has been concluded that the Sutton contracts will offer better value for money by reviewing a number of pricing scenarios based on actual schemes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Maintenance and Management Services Contract AwardReport 77 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
CK
Councillor Caroline KerrChair, present
TC
Councillor Tim CobbettVice-Chair, present
RB
Councillor Rowena BassMember, present
MB
Councillor Mark BeynonMember, present
KD
Councillor Kevin DavisMember, apologies, sent representative
LD
Councillor Lorraine DunstoneMember, present
MD
Councillor Mark DurrantMember, present
DG
Councillor Dennis GoodshipMember, present
AK
Councillor Andreas KirschMember, present
JS
Councillor John SweeneyMember, present
DW
Councillor Diane WhiteMember, apologies, sent representative

On this subject at Kingston upon Thames

Search all
  1. Highways Maintenance and Management Services Contract AwardThis decision
  2. Planned Highways Maintenance 2010/11Agreed
  3. Planned Highways Maintenance 2010/11Decided
  4. Planned Highways Maintenance 2010/11Decided
  5. Planned Highways Maintenance 2010/11Decided
  6. Highways maintenanceAgreed

More from Kingston upon Thames Response and Recovery Committee

All decisions
MeetingDecisionOutcome
13 May 2021 Kingston Communities and Economic Recovery Task Force UpdateRESOLVED that the Committee: 1. Endorse the Covid 19 Skills & Employment Response Plan set out in Annex 1 to the agen... Noted Open
13 May 2021 Heritage Led Regeneration in Kingston Town CentreRESOLVED that the Committee: 1. Delegate authority to the Executive Director of Corporate and Communities, in consult... Approved Open
13 May 2021 Hampden Road - Delivery of New Homes in PartnershipRESOLVED that the Committee: 1. Approves the final Business Case (Exempt Annex 1 to the agenda report) and authority ... Approved Open
13 May 2021 Transformation of Amy Woodgate HouseRESOLVED that the Committee: 1. Delegate authority to the Assistant Director of Property, Development and Investment ... Approved Open
25 Mar 2021 Cambridge Road Estate - Programme DeliveryRECOMMENDED to Council that: 1) Subject to the Executive Director of Place being satisfied in relation to the progres... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies