RESOLVED that: 1) Following the evaluation of a competitive tender process, run through the Crown Commercial Services (CCS) RM3830 Facilities Management Services framework, the contract for the provision of Building Maintenance - Hard FM Services be awarded to the party named in the Confidential Annex 1, commencing 1 October 2022 for an initial term of 5 years with an option to extend for a further 2 years and upon the terms detailed within this report and the associated confidential annex. 2) the decision to enter the extension period of the agreement with Kent County Council (KCC) for the provision of gas and electricity under the LASER Flexible Framework for the period up to September 2024 for the additional contract values set out in the Confidential Annex 2 - Utilities be noted.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Corporate & Resources Committee 5 July 2022 Contract for the provision of Building Maintenance – Hard Facilities Management (HFM) Services Report by: Matthew Essex, Executive Director of Place
The purpose of this report is to advise as to the outcome of the tender exercise for Hard Facilities Management and to recommend to the Committee that the winning Bidder be awarded the contract. In addition, the committee is asked to note the Council’s current contract position in regards to utilities (gas & electricity) supply.
Recommendation (s)
The Committee is asked to RESOLVE that:
1. Following the evaluation of a competitive tender process, run through the Crown Commercial Services (CCS) RM3830 Facilities Management Services framework, the contract for the provision of Building Maintenance - Hard FM Services be awarded to the party named in the Confidential Annex 1, commencing 1 October 2022 for an initial term of 5 years with an option to extend for a further 2 years and upon the terms detailed within this report and the associated confidential annex.
2. the decision to enter the extension period of the agreement with Kent County Council (KCC) for the provision of gas and electricity under the LASER Flexible Framework for the period up to September 2024 for the additional contract values set out in the Confidential Annex 2 - Utilities be noted.
Benefits to the Community:
The new contract will ensure a safe, pleasant and compliant environment for building users and continuity of service delivery, whilst complying with the Council’s wider social value objectives. The new contract will deliver targeted recruitment and pay a minimum of the London Living Wage across both the winning Bidder’s own employees and the firm’s wider supply chain. Furthermore, the new contract will assist the Council with moving towards a more sustainable estate, reducing emissions and helping to achieve carbon neutrality by 2030. Finally, the new contract will reinstate a preventative maintenance regime, improving the quality and condition of the Council’s assets. Overall, the winning Bidder will be delivering the improved service at a cost saving to the Council, allowing us to invest in other priorities to benefit the community we serve.
The extension of the agreement with Kent County Council (KCC) for the provision of gas and electricity ensures that the most cost effective supplies of gas and electricity are secured for the Council’s service including operational buildings, communal areas of housing estates, street lighting and local schools.
Key Points (Hard FM)
3. The Council owns and leases a wide range of assets which support service delivery for the local community. Of this estate, 75 buildings have been identified as core operational facilities for which the Council needs to provide Facilities Management (FM) services to ensure a safe, pleasant and compliant environment for building users and continuity of service delivery.
4. FM and Property Management is currently delivered by a single provider through a Total Facilities and Property Management (TFPM) contract. The initial 7-year period of the current TFPM contract will end in September 2022. Following a review of service provision initiated as part of the Better Contracting Review, it was agreed that the option to extend the TFPM contract was not considered viable and so a replacement delivery model was executed and a tender process for a new provider was implemented.
Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.