Fire Safety Remedial Works 2026-27 - Contract Award
ApprovedCommittee1 paper
AI summaryKingston's Corporate and Resources Committee approved a 12-month, £2.192m contract with Quinn London for fire safety remedial works on council housing, plus £2.932m in additional capital budget across 2025/26 and 2026/27.
Written from the decision and the officer reportPDF Pro
OutcomeApproved12-month fire safety remedial works, direct call-off
Money£2.192m contractPlus £1.522m and £1.410m budget increases
What happens nextContract runs to end March 2027Completion of 935 outstanding fire safety items
Who it affectsCouncil housing tenants and leaseholdersAcross the borough's affordable housing stock
What was decided
Award a 12-month contract to Quinn London for fire safety remedial works at a maximum value of £2.192m, via a direct call-off under the Procure Public Buildings Remediation Framework. Report P3, P11, P20
Approve a £1.522m increase to the 2025/26 capital budget to cover overspend on the current year's fire remediation works, bringing the year total to £3.544m. Report P3, P15, P16
Approve a £1.410m increase to the 2026/27 capital budget to fund the new contract, bringing the fire safety capital budget to £2.9m. Report P3, P17, P18
Why
The Council has a statutory duty as a corporate landlord to maintain fire safety in its housing stock, with failure risking prosecution, financial loss and reputational damage. Report P4, P5
Of more than 4,139 fire safety actions originally identified through Fire Risk Assessments, 935 remain outstanding and the current Quinn London contract ends in March 2026 with no extension option. Report P5, P7
The 2025/26 fire remediation budget of £2.022m has been exhausted, and a competitive tender or mini competition would take 4 to 6 months, risking service disruption and statutory non-compliance. Report P5, P10, P15
What happens next
Complete the 935 outstanding fire safety actions during the 12-month contract, with priority on high-risk homes, high rise blocks, hostels and housing for older people. Report P5, P7, P12
Publish the required Contract Award Notice and, within 30 days of contract entry, a Contract Details Notice under the Procurement Act 2023; record the award on the Contract Register. Report P20
After the contract ends in March 2027, revert to regular fire safety monitoring and inspection, with any future minor works covered from existing budgets. Report P5, P14
The money
£2.192m Maximum contract value for Quinn London over 12 months Report P3, P5
£1.522m Additional capital budget requested for 2025/26 Report P3, P15, P16
£1.410m Additional capital budget requested for 2026/27 Report P3, P17, P18
£2,192,000 (exclusive of VAT) Estimated total contract value stated in legal section Report P20
£2.022m Existing approved 2025/26 capital budget for fire remediation Report P15, P16
£3.544m Total 2025/26 budget requirement for fire remediation Report P15, P16
£1.49m Original 2026/27 budget approved for fire safety works Report P17, P18
£2.9m Revised 2026/27 budget requirement for fire safety works Report P17, P18
Options considered
Rejected: Do nothing. Risk of failing statutory landlord fire safety obligations Report P10
Rejected: Bring the work within the existing housing repairs and maintenance contractors. Insufficient skills, accreditation and long mobilisation period required Report P10
Chosen: Direct call-off under the Procure Public Buildings Remediation Framework (direct award to Quinn London). Quickest route, best value through preferential rates, continuity of proven supplier and reduced risk of service disruption Report P10, P11, P12
Rejected: Run a competitive tender or mini competition against an established framework. Would take 4 to 6 months, with TUPE, transition and service disruption risks Report P10
Implications
Legal: Call-off under the Procure Public Buildings Remediation Framework established under the Procurement Act 2023; Council must publish a Contract Award Notice and a Contract Details Notice within 30 days, and comply with Contract Regulation No. 11 and the Local Government Transparency Code 2015. Report P20
Financial: Budgets are within the Housing Revenue Account; borrowing costs to cover the additional capital are to be covered within existing HRA revenue budgets. Report P19
Risk: Risk of non-compliance with fire safety regulations (fines or imprisonment) rated medium, mitigated by continuing with the existing capable supplier; Section 20 leaseholder consultation risk rated medium, mitigated by ongoing consultation. Report P22
Equalities: An Equalities Impact Assessment was completed in advance of the original tender; no significant equality issues identified, with any specific needs of protected groups to be addressed as they arise. Report P23
Climate: Contract is expected to contribute to the Council's Climate Action Strategy 2024-2030, including high environmental performance standards, a Site Waste Management Plan, social value commitments and support for vulnerable residents in preparing for climate change impacts. Report P25, P26
Staffing: Resources are in place to manage the contract, including validating fire risk assessment orders and monthly monitoring of contract spend. Report P22
Who and where
Tenants in the Council's affordable housing stock, including those in higher rise blocks, hostels and housing for older people Report P4, P5, P7
Leaseholders, who are being consulted under Section 20 on charges they may be liable to reimburse the Council for Report P14, P22
The Council's term maintenance contractor (Cardo South Ltd) and specialist fire door contractor (Delco), whose work sits alongside the Quinn London contract Report P17
Timeline
2023: Quinn London Ltd appointed via competitive tender under the Fusion21 Framework for specialist fire safety remediation Report P5, P7
9 February 2026: Call-off process for the new contract issued via the Procure Public Buildings Remediation Framework Report P14
20 February 2026: Deadline for tender responses Report P14
End of March 2026: Existing Quinn London contract ends Report P5, P7
19 March 2026: Corporate and Resources Committee decision to award contract and approve budget increases Report P1
End of March 2027: New 12-month Quinn London contract ends Report P5, P14
Plain English for the jargon
FRA: Fire Risk Assessment, a systematic inspection of properties to identify fire safety deficiencies
FIRAS: Third-party accreditation for companies installing fire-resisting products and systems
HRA: Housing Revenue Account, the ring-fenced account for income and spending on council housing
PA23: Procurement Act 2023, which governs public procurement and award notice requirements
PCR15: Public Contracts Regulations 2015, under which the Procure Public Framework was established
EQIA: Equalities Impact Assessment, an assessment of the equality effects of a decision
CDM 2015: Construction (Design and Management) Regulations 2015, governing health and safety on construction projects
Section 20 consultation: The statutory consultation process landlords must follow when proposing qualifying works or long-term agreements affecting leaseholders
TUPE: Transfer of Undertakings (Protection of Employment) regulations, which can apply when services transfer between contractors
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item167
Resolved
RESOLVED that: 1) the award of a contract to Quinn London for Fire Safety Remedial works for a contract period of 12 months for a maximum contract value of £2.192m be approved; the £1.522m increase to the 2025/26 capital budget be approved and added to the capital programme; and 3. the £1.410m increase to the 2026/27 capital budget be approved and added to the capital programme.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Corporate and Resources Committee 19 March 2026 Fire Safety Remedial Works 2026-27 - Contract Award Report by Andrew Campion, Corporate Head of Housing Asset Management Relevant Portfolio Holder: Councillor Emily Davey, Portfolio Holder for Housing Last Committee Reference: Minute 29 of the Place Committee, 24 September 2024
Purpose of Report o award a contract for the provision of fire safety remedial works to ensure fire safety T compliance with the relevant regulations across the Council’s housing stock. The Committee is also requested to approve an increase of the capital budgets for 2025/26 and 2026/27 to ensure the completion of all identified Fire Safety Remedial Works in a timely manner.
Recommendation(s) The Committee is asked to RESOLVE that: 1. the award of a contract to Quinn London for Fire Safety Remedial worksfor a contract period of 12 months for a maximum contract value of£2.192m be approved; 2. the £1.522m increase to the 2025/26 capital budget be approved and added to the capital programme; and 3. the £1.410m increase to the 2026/27 capital budget be approved and added to the capital programme.
Benefits to the Community: he Council has a responsibility as a Corporate Landlord to ensure fire safety within T those homes owned by the Council including through undertaking appropriate Fire Risk Assessments and completing all fire safety actions which require remedial works. Council Priorities nsuring thatKingston’s communities are places whereresidents feel safenecessitates E maintaining the integrity of all passenger fire doors for Council Housing. n essential part oftaking responsibility and doingwhat’s necessary to put the council A on a sustainable financial footingis protecting lifeand our property assets. he consequences of failure to discharge our statutory duties in regard to fire safety T remediation includes serious financial loss, criminal prosecution and reputational damage. Key Points
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.