AI summaryKingston Corporate and Resources Committee approves strategy to re-procure its soft facilities management contract via the Crown Commercial Services Dynamic Purchasing System, with the new contract expected to start 1 October 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTender via Crown Commercial Services DPS approved unanimously
Moneyin excess of £6mForecast total contract value over its lifetime
What happens nextTender to run April to May 2026Award decision expected at June 2026 committee
Who it affectsCleaning, porterage, pest control, fire alarm testing. Across 36 corporate sites
What was decided
The committee approved the procurement strategy for a new soft FM contract via the Crown Commercial Services Facilities and Workplace Services Dynamic Purchasing System, reference RM6264. Report P11, P18
The committee agreed that a further report will come back to it to award the contract once the procurement process is complete. Report P12
Bids will be evaluated on a 60 percent quality and 40 percent price split, with method statement sub-weightings set across service delivery, quality control, training, contract management, improvement and social value. Report P33, P34, P35, P36
Why
The current soft FM contract ends on 30 September 2026 and cannot be extended, so a new contract is needed to keep council buildings clean, safe and compliant from 1 October 2026. Report P16, P26
Market testing returned 23 supplier responses with 18 expressing interest, and officers judged the DPS route would vet suppliers financially while still allowing local firms to join at any time. Report P18, P28, P32
An in-house option was ruled out because the small FM team of five could not manage 32 transferring staff and cleaning requires specialist compliance and risk transfer. Report P31
What happens next
An Invitation to Tender will run for six weeks from April to mid May 2026, with evaluation in May 2026. Report P19, P45
A recommendation to award will go to the Commissioning and Governance Board on 4 June 2026 and to the Corporate and Resources Committee on 25 June 2026. Report P45
Contract award is planned for July 2026, with mobilisation from August to September 2026 and a new contract start date of 1 October 2026. Report P19, P45
The money
in excess of £6m Forecast total value of the new contract over its lifetime Report P20
£6m Reference figure for revenue bid likely to be needed Report P20
Options considered
Rejected: Option 1: Do nothing. Cleaning, porterage and pest control are essential for safe and compliant premises Report P31
Rejected: Option 2: Bring the service in-house. FM team of five lacks capacity to manage 32 transferring staff and cleaning is a specialist service Report P31
Chosen: Option 3: Call off under the CCS Dynamic Purchasing System. Vets suppliers financially, allows new suppliers to join, brings structure without restricting bidders, and provides pre-agreed terms Report P18, P31, P32
Rejected: Option 4: Run an open tender. Likely to attract a large number of low-standard cleaning bids and would be the most time consuming and expensive option Report P31
Rejected: Option 5: Competitive Flexible Procedure. Multi-stage process is time consuming and resource heavy and risks missing the procurement timeline Report P31
Implications
Financial: The new contract is forecast to be higher in value than the current budget allows, so a revenue bid is likely to be needed once bids are received. Report P20
Legal: The procurement will be run under the Public Contract Regulations 2015 via the CCS DPS reference RM6264, which runs to 23 February 2029, and contract details must be added to the Council's Contract Register. Report P47, P48, P49, P50
Equalities: An Equalities Relevance Test found no impact, so no full Equalities Impact Assessment was carried out. Report P57, P58
Staffing: No primary TUPE is expected, but secondary TUPE will apply, so 32 staff employed by the current supplier are likely to transfer to the successful bidder with their terms protected. Report P31, P51
Risk: Medium risk that a 10 percent price increase tied to the London Living Wage and CPI pushes up costs; low risk of TUPE cost increases and low risk of poor supplier interest. Report P53, P54
Climate: The tender will include quality questions on social value and environmental impact to support the council's net zero by 2030 target. Report P61
Who and where
Staff and visitors using the council's 36 corporate sites Report P14, P22
The 32 cleaners and porters currently employed by the incumbent supplier Report P31
Suppliers responding to the soft market testing, including local cleaning companies Report P18, P28, P32
The Place Directorate FM team, which will retain contract management responsibility Report P22, P31
Timeline
11 November 2025: Preliminary market engagement questionnaire issued Report P28
17 November 2025: Deadline for market engagement responses Report P28
19 March 2026: Corporate and Resources Committee approved the procurement strategy Report P2, P45
April to mid May 2026: Invitation to Tender open for six weeks Report P45
May 2026: Evaluation and moderation of bids Report P45
4 June 2026: Commissioning and Governance Board to endorse contract award Report P45
25 June 2026: Corporate and Resources Committee to approve contract award Report P45
July 2026: Contract award Report P45
August to September 2026: Contract mobilisation Report P45
30 September 2026: Current soft FM contract ends Report P16, P26
1 October 2026: New contract commences Report P19, P26, P45
Plain English for the jargon
Soft FM: Non-technical facilities management services such as cleaning, porterage, pest control and fire alarm testing, as distinct from hard FM like building maintenance.
CCS Dynamic Purchasing System (DPS): A Crown Commercial Services public sector buying route, reference RM6264 for Facilities Management and Workplace Services, where suppliers can join at any time and are vetted for financial stability.
TUPE: Transfer of Undertakings (Protection of Employment) regulations that move staff from an outgoing contractor to a new one on their existing terms.
LLW: London Living Wage, the minimum hourly rate paid to staff working in London.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item168
Resolved
RESOLVED that: 1) the new Soft Facilities Management (FM) contract procurement strategy via the Crown Commercial Services (CCS) Dynamic Purchasing System (DPS) be approved; and 2) a further report be brought back to the Committee for the award of the contract on the conclusion of the procurement process. Voting: Unanimous Recorded Vote Title Type Recorded Vote text Result Resolution Carried View Recorded Vote for this item
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Report by Chris Jones, Director of Property and Projects
elevant Portfolio Holder: Councillor Richard Thorpe, Portfolio Holder for Finance, Assets R and Governance
ast Committee Reference: Minute 79 of the Corporate and Resources Committee, 5 July L 2022
Purpose of Report
o approve the procurement strategy to issue a tender for the re-procurement of the T replacement soft Facilities Management (FM) services contract to include cleaning, porterage, pest control and fire alarm testing via theCrown Commercial Services (CCS) FrameworkFacilities and Workplace ServicesDynamicPurchasing System(DPS).
Recommendation(s)
The Committee is asked to RESOLVE that:
1. the new Soft Facilities Management (FM) contract procurement strategy via the Crown Commercial Services (CCS) Dynamic Purchasing System (DPS) be approved; and
2. further report be brought back to the Committee for the award of the contract on a the conclusion of the procurement process.
Benefits to the Community:
he soft FM service provides clean, hygienic and safe environments for all staff and T visitors to the Council’s premises.
Key Points
A. he current soft FM contract for the cleaning of the Council’s corporate buildings T will end on 30 September 2026 and cannot be extended therefore for continuity of the services it is vital to go out to tender for a new contract.
B. he Invitation to Tender (ITT) will be issued for a contract term of 3 years + 1 + 1 T and will be for services to include cleaning, porterage, pest control and fire alarm testing.
C. he recommended route to market is to use the Crown Commercial Services (CCS) T Dynamic Purchasing System (DPS) RM6264 Facilities Management and Workplace Services DPS, which is a dedicated DPS for Building Cleaning Services. Considering the nature of the services required, mainly cleaning of offices, there is risk of a high number of tender returns. The use of a DPS will help mitigate this by a bringing some structure to the process within initial suitability assessments (including financial checks) being completed as part of the DPS submission process.
D. he procurement process will be undertaken in April and May 2026, subject to the T Committee’s approval, and a report will be presented to the next available Committee, currently programmed for June 2026, with a recommendation to award a contract. This will enable continuity of service with the new contract commencing on 1 October 2026.
E. It is forecast that the new contract will be at a higher value than is allowed for within the current budget and that the total value over the lifetime of the contract will be in excess of £6m. Once bids have been received and evaluated it is most likely that a revenue bid will have to be submitted to accommodate all works in scope, which will include all miscellaneous services such as porterage.
Context
1. he FM Team within the Place Directorate is responsible for delivering a wide range T of Soft FM services across the organisation's corporate estate. This includes overseeing cleaning services across 36 sites, and ensuring that all buildings are maintained to appropriate hygiene and presentation standards that support staff, business partners, residents, and visitors.
2. ithin the main Guildhall, FM also manages a comprehensive porterage service. W This includes the setup and breakdown of meeting rooms, the movement of furniture and equipment, and the coordination of hospitality support, such as the provision of tea and coffee facilities for internal and external events.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.