CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Knowsley Metropolitan Borough Council
Cabinet, Wednesday 14 August 2013 at 2.00pm

2012/13 Capital Outturn and 2013/14 Capital Monitoring (*)

Noted Executive 1 paper

Cabinet noted this item on Wednesday 14 August 2013. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

RESOLVED – (i) That the revised Capital Programme as at 31 March 2013 totalling £20.624m, as identified in section 3.1 of the report, be noted; (ii) that the total expenditure in 2012/13 of £15.304m and consequent rephasing of capital expenditure of £5.798m into 2013/14, as identified in sections 3.2 to 3.7 of the report be noted; (iii) that the 2013/14 capital expenditure to date of £2.985m and the expected impact on the delivery of the approved Capital Programme, as set out in paragraph 4.2.1 of the report, be noted; (iv) that the proposals from Portfolio Holders which would result in the rephasing of schemes under £1m of £0.497m from 2013/14 into future years, as set out in paragraph 4.2.2 of the report, be endorsed; (v) that the proposals from Portfolio Holders for new start schemes under £1m (phased £0.751m in 2013/14 and £0.491m in future years), and adjustments resulting in a net reduction of £0.203m in 2013/14, as set out in section 4.3 of the report, be endorsed; (vi) that proposals for new start schemes over £1m (phased £1.258m in 2013/14 and £3.174m in future years), as set out in paragraphs 4.3.2 and 4.3.3 of the report, be endorsed; (vii) that £0.393m of the in-year estimated capital receipts of £1.228m in 2013/14 be allocated as discussed at section 5.6 of the report; (viii) that the balance of capital receipts be not allocated at this time; and (ix) that the revised three-year Capital Programme of £41.322m and the revised phasing, as noted in paragraph 6.1.2 and detailed at Appendix B to the report, be noted. ... view the full minutes text for item 22.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

This report presents the 2012/13 outturn in relation to the Council’s Capital Programme and provides an update on the position in 2013/14 and future years.

Recommendations

Members of the Cabinet are recommended to:-

(a) Note the revised Capital Programme at 31 March 2013 totalling £20.624m as identified in paragraph 3.1 of this report;

(b) Note the total expenditure in 2012/13 of £15.304m and consequent rephasing of capital expenditure of £5.798m into 2013/14 as identified in sections 3.2 to 3.7 of this report;

(c) Note the 2013/14 capital expenditure to date of £2.985m and the expected impact on the delivery of the approved capital programme as set out in paragraph 4.2.1 of this report;

(d) Endorse the proposals from Portfolio Holders which would result in the rephasing of schemes under £1m of £0.497m from 2013/14 into future years as set out in paragraph 4.2.2 of this report; (e) Endorse the proposals from Portfolio Holders for new start schemes under £1m (phased £0.751m in 2013/14 and £0.491m in future years), and adjustments resulting in a net reduction of £0.203m in 2013/14 as set out in section 4.3 of this report;

(f) Approve the proposals for new start schemes over £1m (phased £1.258m in 2013/14 and £3.174m in future years) as set out in paragraphs 4.3.2 and 4.3.3 of this report;

(g) Agree to allocate £0.393m of the in-year estimated capital receipts of £1.228m in 2013/14 as discussed at paragraph 5.6 of this report;

(h) Agree not to allocate the balance of capital receipts at this time; and,

(i) Note the revised three-year Capital Programme of £41.322m and the revised phasing as noted in paragraph 6.1.2 and detailed at Appendix B to this report.

3. 2012/13 CAPITAL PROGRAMME OUTTURN POSITION

3.1Adjustments to the 2012/13 Capital Programme

The final Capital Programme at 31 March 2013 was £20.624m (before the impact of any year-end rephasings). A summary of the outturn position is shown at Appendix A to this report. Full details have been reported to Portfolio Holders and are available on request.

3.2Proposed Rephasing of Schemes

3.2.1 Of the final Capital Programme of £20.624m, a total of £15.304m (74%) was actually spent during 2012/13. This resulted in expenditure of £5.798m, which had originally been programmed for 2012/13, being rephased into 2013/14 at outturn along with the associated resources. 3.2.2 The following table summarises the overall rephasing position, and the main reasons for the rephasing of expenditure are then set out in the following sections of the report:-

Rephasing Portfolio (£m) Children and Family Services 1.139 Health and Social Care 0.457 Leisure, Community and Culture 1.086 Neighbourhood Delivery 0.046 Regeneration, Economy and Skills 2.273 Stockbridge Village Redevelopment 0.167 Kirkby Town Centre Regeneration 0.630 Total 5.798

3.3Children and Family Services

3.3.1 The main reasons for the required rephasing are:-

• Schools and Children’s Centre Improvements (£0.336m) - a programme of work is overseen by the Schools Asset Management Working Group. As works need to be programmed during the school holidays wherever possible, some individual schemes could not be delivered in 2012/13 and therefore £0.052m will be spent during 2013/14. The remaining £0.284m of the unallocated sum has been rephased into 2014/15 as this is a more realistic scheduling of the spending programme than was originally set out. For the same reasons, the 2013/14 allocation of £1.066m has also been phased directly into 2014/15 and 2015/16. The Portfolio will need to ensure that plans are properly developed to avoid the accumulation of future unspent resources;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2012/13 Capital Outturn and 2013/14 Capital Monitoring (*)Report 159 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. 2012/13 Capital Outturn and 2013/14 Capital Monitoring (*)This decision
  2. Capital Programme: 2025/26 Final Outturn (*)Agreed
  3. Capital Programme 2021/22 Final Outturn and 2022/23 Monitoring(*)Agreed
  4. 2018/19 Capital Outturn and 2019/20 Capital Monitoring(*)Agreed
  5. 2017/18 Capital Outturn and 2018/19 Capital Monitoring(*)Agreed
  6. 2016/17 Capital Outturn and 2017/18 Capital Monitoring (*)Noted

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies