RESOLVED – That (i) the amendments to the final 2016/17 Capital Programme, as set out in paragraph 4.1 of the report, be noted; (ii) the final outturn position for the 2016/17 Capital Programme, as set out in paragraph 4.2 of the report, be noted; (iii) the proposed additions to the 2017/18 Capital Programme of schemes over £1m, as set out in paragraph 5.3 of the report, be approved; (iv) as a result of the adjustments identified in sections 4 and 5 of the report, the revised total Capital Programme of £36.261m, of which £20.474m is phased to be spent in 2017/18, as set out in paragraph 5.4 of the report, be approved; and (v) the treasury management prudential indicators, as presented in section 7 of the report, be noted.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
This report presents the outturn position for the Council’s 2016/17 Capital Programme and an update on the position for 2017/18 and future years. It also highlights over £32m of capital investment into Knowsley which is planned over the next three years.
Recommendations
Members of the Cabinet are recommended to:-
(a) Note the amendments to the final 2016/17 Capital Programme as set out in paragraph 4.1 of this report;
(b) Note the final outturn position for the 2016/17 Capital Programme as set out in paragraph 4.2 of this report;
(c) Approve the proposed additions to the 2017/18 Capital Programme of schemes over £1m as set out in paragraph 5.3 of this report;
(d) As a result of the adjustments identified in sections 4 and 5 of this report, approve the revised total Capital Programme of £36.261m, of which £20.474m is phased to be spent in 2017/18 as set out in paragraph 5.4 of this report; and,
(e) Note the treasury management prudential indicators as presented in section 7 of this report. 3. EXECUTIVE SUMMARY
3.1At the end of 2016/17, the Council had spent 99% of the final Capital Programme for the year. This position takes into account a number of rephasings and amendments to the Programme in the final quarter of the year.
3.2In 2017/18, spending at the end of July 2017 equates to 21% of the current Programme for the year, which is a similar rate of spending to the preceding year. Scheme managers have individually suggested that this is in line with their expectations, but, to allow for the overall impact of potential delays across the full Capital Programme, a built-in level of rephasing (20%) will be assumed for the rest of the year.
4. 2016/17 CAPITAL PROGRAMME OUTTURN POSITION
4.1At the Quarter 3 stage in 2016/17, the Capital Programme for the year was £17.912m. During the last quarter of 2016/17, amendments of £0.071m resulted in a final Capital Programme for the year of £17.983m. The overall 2016/17 Capital Programme is shown at Appendix A to this report.
4.2At the end of 2016/17, a total of £17.826m was actually spent against this Programme, meaning that the revised Programme was underspent by £0.086m (less than 1%) at the outturn stage.
4.3A number of rephasings were made in the last quarter of 2016/17. Details of all rephased schemes are available on request from the Executive Director (Resources). The main changes made in the last quarter of 2016/17 were:-
(a) Knowsley Business Park Access and Connectivity Improvements: £1.549m was rephased into 2017/18. Due to technical feasibility issues associated with the final component of this major transport scheme, the re-profiling of the scheme was agreed by the Liverpool City Region Combined Authority;
(b) Industrial and Commercial Developments: £1.150m brought forward into 2016/17. The Council is in the process of securing a 20 acre development site within Knowsley Business Park, which has necessitated buying out an historical agreement which gave Potter Group Holdings the option to purchase a piece of land from the Council. The timescale for the purchase was anticipated to be early 2017/18, but completion actually took place on 20 March 2017 and therefore the reserve set aside for this purpose was used slightly earlier than originally planned; (c) Kirkby Leisure Centre 3G Soccer Pitch Upgrade: £0.584m rephased into 2017/18. Work was delayed due to adverse weather conditions and flooding, which meant that the ground could not be levelled. The facilities are now open for public use; and,
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.