RESOLVED – That:- ( i ) the final outturn position for the 2017/18 Capital Programme as set out in section 3.1.3 of the report be agreed; (ii) the proposed additions to the 2018/19 Capital Programme of schemes over £1m as set out in paragraph 4.3 of the report be approved; (iii) the new Capital Programme of £72.331m in total, of which £30.643m is phased to be spent in 2018/19, as set out in paragraph 4.5.1 of the report, be approved; and (iv) the treasury management prudential indicators as presented in section 6 of the report be noted.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
1.1This report provides a summary of how the Council’s capital resources were spent during 2017/18, and sets out the planned programme of expenditure on capital schemes for 2018/19 and future years.
1.2Total capital expenditure during 2017/18 was £20.881m. The programme has spent ahead of schedule and previously approved resources have therefore been brought forward from 2018/19.
1.3The report requests approval for two new schemes over £1m to be added to the Capital Programme - £2.887m for the Sustainable Transport Enhancement Programme and £1.837 for the Local Growth Fund 3 Key Route Network. Both of these investments are possible due to successful bids to the Liverpool City Region Combined Authority.
1.4Subject to the Cabinet’s consideration of this report, the Council’s total Capital Programme for the next three years would be £72.331m, of which £30.643m is planned to be spent during 2018/19.
1.5Key schemes included in the 2018/19 Capital Programme would include:-
Shakespeare North - £8.609m; Disabled Facilities Grants - £3.243m; Bowring Park Restoration - £2.463m; County Road/Hall Lane Junction Improvements - £1.837m; General Highways Maintenance and Potholes - £1.737m; Prescot Townscape Heritage Initiative - £1.600m; and, Capital Investment in Schools - £1.488m. 1.6 The report also explains that there are currently no unallocated capital receipts expected to be available in 2018/19. While there are estimated potential receipts of £3.531m forecast for 2019/20, this estimate is subject to market demand and final selling prices.
Recommendations
Members of the Cabinet are recommended to:-
(a) Agree the final outturn position for the 2017/18 Capital Programme as set out in section 3.2 of this report;
(b) Approve the proposed additions to the 2018/19 Capital Programme of schemes over £1m as set out in paragraph 4.3 of this report;
(c) Approve the new Capital Programme of £72.331m in total, of which £30.643m is phased to be spent in 2018/19, as set out in paragraph 4.5.1 of this report; and,
(d) Note the treasury management prudential indicators as presented in section 6 of this report.
3. 2017/18 CAPITAL PROGRAMME OUTTURN
3.1Adjustments to the Programme
3.1.1 The Quarter Three Capital Programme monitoring report to the Cabinet (on 21 February 2018) noted that the estimated 2017/18 Programme was £17.299m. During the last quarter of 2017/18, a number of amendments to the Programme were made:-
a) Disabled Facilities Grants - £0.169m - further contributions were received from registered housing providers and individual applicants towards the cost of providing disabled facilities in their properties;
b) Capital Investment in Schools - £0.481m - the Schools Remodelling Programme was accelerated to undertake more remodelling works during 2017/18 than had previously been anticipated. Both the relevant multi-academy trusts and the Roman Catholic Archdiocese of Liverpool have also made funding contributions towards such works and increased the size of the programme; and, c) Building and Property Alterations - £0.274m - resources had previously been set aside for costs associated with NHS properties which could potentially have fallen on the Council as a result of the transfer of public health responsibilities from the NHS to local government. A provision for these costs was set aside until liability was fully clarified. Liability for these costs has now been settled and the resources were released back to the Council’s programme to fund general building and property allocations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.