Knowsley Metropolitan Borough Council
Cabinet, Wednesday 21 September 2016 at 5.00pm

2015/16 Capital Outturn and 2016/17 Capital Monitoring (*)

Noted Executive 1 paper

Cabinet noted this item on Wednesday 21 September 2016. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

RESOLVED – That (i) the final outturn position for the Council’s 2015/16 Capital Programme, as identified in paragraph 3.1 of the report, be noted; (ii) the rephasing over £1m for the Knowsley Business Park Access and Connectivity Improvements and the A5300 Knowsley Expressway/A562 schemes, as set out in paragraph 3.4 of the report, be noted; (iii) the proposed additions over £1m, as set out in paragraph 4.2.2 of the report, be approved; (iv) the Council should act as the Accountable Body status of the two schemes, as set out in paragraph 4.2.3 of the report; and (v) as a result of the adjustments identified in section 3 and section 4 of the report, the revised total Capital Programme of £35.124m, of which £21.129m was phased to be spent in 2016/17, as set out in paragraph 5.1.3 of the report, be approved. (Note: The above item was deemed a ‘General Exception’ item in accordance with the Access to information Procedure Rules in the Council’s Constitution.)
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

This report presents the outturn position for the Council’s 2015/16 Capital Programme and also provides an update on the position for 2016/17 and future years.

Recommendations

Members of the Cabinet are recommended to:-

(a) Note the final outturn position for the 2015/16 Capital Programme as set out in paragraph 3.1 of this report;

(b) Note the rephasings over £1m for the Knowsley Business Park Access and Connectivity Improvements and A5300 Knowsley Expressway/A562 schemes as set out in paragraph 3.4 of this report;

(c) Approve the proposed additions over £1m as set out in paragraph 4.2.2 of this report;

(d) Agree that the Council should act as the Accountable Body for the two schemes set out in paragraph 4.2.3 of this report; and,

(e) As a result of the adjustments identified in section 3 and section 4 of this report, approve the revised total Capital Programme of £35.124m, of which £21,129m is phased to be spent in 2016/17 as set out in paragraph 5.1.3 of this report. 3. 2015/16 CAPITAL PROGRAMME OUTTURN POSITION

3.1At Quarter 3, the Capital Programme for 2015/16 was £24.623m as shown at Appendix A. During the last quarter of 2015/16, final amendments of £0.515m were identified resulting in a revised Capital Programme of £24.108m. At 31 March 2016, a total of £20.559m was actually spent against this Programme, therefore meaning that the revised Programme was underspent by 15% at the outturn stage.

3.2The remaining expenditure of £3.549m has been rephased into 2016/17 along with the associated resources.

3.3The table below summarises the rephasings made at the outturn stage, and the overall 2015/16 Capital Programme is attached at Appendix A to this report:-

Capital Programme Rephasings £m from 2015/16 into 2016/17 Adult Social Care 0.035 Public Health and Wellbeing (0.058) Special Projects (0.001) Early Help 0.055 Children’s Social Care 0.189 Schools Programme 0.311 Sustainable Resources 0.217 Streetscene, Fleet and Logistics 0.058 Neighbourhoods (0.017) Economic Development 0.199 Regeneration and Housing 2.561 TOTAL 3.549

3.4The Regeneration and Housing rephasing includes two schemes exceeding £1m (£2.185m in total) which are summarised below for the Cabinet to note:-

(a) Knowsley Business Park Access and Connectivity Improvements (£1.093m rephased) – delays in finalising the legal agreements for the associated Merseytravel grant impacted severely on the scheme commencement date and the remainder of the construction programme which had to be extended into 2017/18;

(b) A5300 Knowsley Expressway/A562 (£1.092m rephased) – again, delays in finalising the legal agreements for the associated Merseytravel grant impacted severely on the scheme commencement date and the remainder of the construction programme which had to be extended into 2017/18. 4. MONITORING OF THE 2016/17 CAPITAL PROGRAMME

4.1Capital Programme Rephasings

4.1.1 Since the original 2016/17 Programme was approved by the Council on 9 March 2016, scheme managers have identified the need to rephase £2.064m of the 2016/17 Programme into 2017/18 and 2018/19. These rephasings are summarised below:-

Capital Programme Rephasings 2017/18 2018/19 from 2016/17 into future years £m £m Adult Social Care 0.300 0.204 Economic Development 0.047 Regeneration and Housing 1.513 TOTAL 1.860 0.204

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2015/16 Capital Outturn and 2016/17 Capital Monitoring (*)Report 219 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. 2015/16 Capital Outturn and 2016/17 Capital Monitoring (*)This decision
  2. Capital Programme: 2025/26 Final Outturn (*)Agreed
  3. Capital Programme 2021/22 Final Outturn and 2022/23 Monitoring(*)Agreed
  4. 2018/19 Capital Outturn and 2019/20 Capital Monitoring(*)Agreed
  5. 2017/18 Capital Outturn and 2018/19 Capital Monitoring(*)Agreed
  6. 2016/17 Capital Outturn and 2017/18 Capital Monitoring (*)Noted

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies