That i. the current forecast underspend of £15.758m on the revenue budget in 2017/18 be noted, and the transfer of the final underspend at year end into the transitional reserve be agreed. ii. the revised funding gap of £144.492m covering the period 2018/19 to 2021/22 as set out in the revised financial outlook forecast for the Council be noted. iii. the additional budget adjustments for 2018/19, and following years' increases, included in the revised MTFS following the financial settlement, be approved. iv. the budget proposals set out in Appendix C be approved for the purposes of consultation, the outcomes of the consultation to be reported back to Cabinet for consideration in due course. v. the budget proposals set out in Appendix D be approved, officers be authorised to proceed with their implementation, and the 2018/19 budget is based upon these revenue decisions vi. Full Council on 8th February 2018 be recommended to set a Band D Council Tax for 2018/19 reflecting a 5.99% increase including 3% to be used for social care as per the new flexibilities. vii. the contents of the County Council's Reserves position at 31 st December 2017, forecast at £190.285m at the end of 2019/20, be noted, and the transfers between reserves be approved as contained within the report. viii. the specific capital programme estimated at £226.117m for 2018/19 – 2020/21 be approved as presented within the body of the report. ix. prudential borrowing totalling £200.428m over the period 2017/18 to 2020/21 be approved as identified within the Capital Programme report. x. the advice of the Interim Chief Executive and Director of Resources in relation to the robustness of the budget and the adequacy of reserves be noted.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
This report sets out an overview of the Council's financial position from 2017/18 to 2021/22. It includes an update on the current year's financial position and a revised Medium Term Financial Strategy (MTFS) reflecting the provisional settlement for 2018/19 announced on 19th December 2017 as well as updated financial assumptions based on the latest evidence.
Like all councils, Lancashire County Council is facing significant financial pressures, and while good progress has been made in addressing the forecast financial shortfall over the strategy period, further work is required to ensure the council can achieve a financially sustainable position.
In summary:
The 2017/18 revenue forecast outturn is £709.064m, an underspend of £15.758m (c2%) on the original budget.
The MTFS indicates a financial deficit of £144.492m in 2021/22 and a cumulative deficit of £381.796m after allowing for savings of £135m, including £81m of new savings proposals included in reports to Cabinet during 2017/18.
The Council is forecast to hold a General Reserve against unforeseen issues of £23.627m representing c3% of net budget.
The Council is forecast to hold £122.801m of uncommitted transitional reserve (including the forecast underspend in the current financial year), which is sufficient to meet the deficit in 2018/19 and could also support the 2019/20 deficit, however in order to set a legal budget in future years further savings will need to be made. The in-year agreed capital programme is £171.611m with a forecast spend of £155.271m and therefore a delivery variance of £16.340m.
A capital programme for the period 2018/19 – 2020/21 of £226.117m, is proposed, reflecting additions to the programme agreed by Cabinet including revenue savings linked to capital. Prudential borrowing totalling £200.428m covering the period 2017/18 to 2020/21 is required to fund the proposed programme.
Council Tax is assumed to increase by 5.99% in 2018/19, including 3% for adult social care. This maximises the flexibilities set out in the latest provisional settlement without the need for a referendum.
Recommendations
The Cabinet is asked to:
(i) Note the current forecast underspend of £15.758m on the revenue budget in 2017/18 and agree the transfer of the final underspend at year end into the transitional reserve.
(ii) Note the revised funding gap of £144.492m covering the period 2018/19 to 2021/22 as set out in the revised financial outlook forecast for the Council.
(iii) Approve the additional budget adjustments for 2018/19, and following years' increases, included in the revised MTFS following the financial settlement.
(iv) Approve for purposes of consultation the budget proposals set out in Appendix C, the outcomes of the consultation to be reported back to Cabinet for consideration in due course.
(v) Approve the budget proposals set out in Appendix D, authorise officers to proceed with their implementation and agree that the 2018/19 budget is based upon these revenue decisions
(vi) Agree to make recommendations to Full Council on 8th February 2018 a Band D Council Tax for 2018/19 reflecting a 5.99% increase including 3% to be used for social care as per the new flexibilities.
(vii)Note the contents of the County Council's Reserves position at 31st December 2017 forecast at 190.285m at the end of 2019/20, and approve the transfers between reserves contained within the report.
(viii) Approve the specific capital programme estimated at £226.117m for 2018/19 – 2020/21 as presented within the body of the report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.