Resolved
That a submission be made to the Planning Authority of revised proposals for , as set out in this report
Cabinet decided this item on Thursday 18 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That a submission be made to the Planning Authority of revised proposals for , as set out in this report
The renewal of planning consent granted for Broughton bypass included a condition that proposals be developed for cycling, walking and environmental enhancements along the existing A6 Garstang Road, Broughton.
An original set of proposals were approved for implementation by the Planning Authority in April 2017. Following a value engineering exercise, a modified set of proposals are now proposed. This report sets out the revised proposals and the results of stakeholder consultation.
This is deemed to be a Key Decision and the provisions of Standing Order No. 25 have been complied with.
The Cabinet is recommended to approve a submission to the Planning Authority of revised proposals for A6 Corridor Works, Broughton, as set out in this report.
Background and Advice
Planning consent for the construction of Broughton bypass was renewed in December 2013. Condition no. 8 included a requirement that within six months of the bypass works commencing, a scheme of environmental enhancement and traffic calming measures for the A6 Garstang Road through Broughton village be submitted to the Planning Authority for approval. This was to include improved walking and cycling facilities on Garstang Road, including a length of the Preston Guild Wheel. Following two rounds of stakeholder consultation, the former Cabinet Member for Highways and Transport approved a package of proposed measures in March 2016. These were subsequently submitted to the Planning Authority, which approved the proposals in April 2017.
During the summer of 2017, the original proposals were subject to a value engineering exercise. This was carried out to ensure that the proposals provide maximum value for money and are affordable within the allocated budget, whilst still meeting the requirements of the Planning Authority in terms of;
Landscaping, environmental and public realm improvements. Measures to discourage through traffic from continuing to use A6 Garstang Road. Measures to enhance pedestrian and cycling facilities along A6 Garstang Road, including part of the Preston Guild Wheel.
The principle of the revised proposals are very similar to the original. The main changes are as follows;
A minor reduction in scope of the village centre public realm works. Replacement of a road narrowing/priority traffic calming feature with 2 no. road humps north of Broughton crossroads. Replacement of a junction table with a road hump south of Broughton crossroads. Reduction in the use of high quality paving materials at locations not within the main area of village centre public realm improvements.
The proposed measures are shown on the plans attached at Appendices 'A', 'B' and 'C'. The main elements are summarised as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A6 Corridor Works, BroughtonReport | 113 KB | DownloadRead as text |
PDF |
(Updated Scheme, Southern Section)Appendix A | 3.2 MB | Download |
PDF |
(Updated Scheme, Central Section)Appendix B | 7.5 MB | Download |
PDF |
(Updated Scheme, Northern Section)Appendix C | 5.2 MB | Download |
PDF |
View item 6. as DOC 162 KBReport | 5 pages | Download |
Follow Cabinet at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. | Decided | Open |
| 3 Sep 2026 | Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... | Noted | Open |
| 3 Sep 2026 | 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... | Noted | Open |
| 3 Sep 2026 | Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... | Approved | Open |
| 3 Sep 2026 | SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.