That i. the proposed amendments to the Highways and Transport Capital Programmes as outlined in the report be approved. ii. the proposed 2017/18 New Start Cycle Safety Programme as outlined in the report be approved iii. the proposed 2017/18 National Productivity Investment Fund (NPIF) Programme as outlined in the report be approved.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
As part of the normal process of service delivery the approved Highways and Transport Capital Programmes now require certain amendments in order to meet emerging priorities and to respond to some unanticipated service demands. The proposed amendments are set out at Appendix 'A'.
The report also seeks approval of the proposed 2017/18 New Start Cycle Safety Programme at Appendix 'B' and the proposed 2017/18 National Productivity Investment Fund (NPIF) Programme as outlined at Appendix 'C'
This is deemed to be a Key Decision and the provisions of Standing Order No. 25 have been complied with.
Recommendation
The Cabinet is recommended to:
(i) Approve the proposed amendments to the Highways and Transport Capital Programmes as outlined at Appendix 'A'. (ii) Approve the proposed 2017/18 New Start Cycle Safety Programme at Appendix 'B' (iii) Approve the proposed 2017/18 National Productivity Investment Fund (NPIF) Programme as outlined at Appendix 'C'. Background and Advice
Proposed Changes to the Highways and Transport Capital Programmes
The following detailed highway and transport capital programmes of work have previously been approved by the Cabinet Member for Highways and Transport;
2014/15 New Starts Programme - 27 January 2014 2015/16 New Starts Programme - 5 March 2015 2016/17 New Starts Programme - 18 April 2016 2017/18 New Starts programme - 13 March 2017
As part of the normal process of service delivery these detailed programmes of work now require certain amendments in order to meet the emerging priorities and to respond to some unanticipated service demands. The proposed amendments are set out at Appendix 'A'.
Proposed 2017/18 New Start Cycle Safety Programme
On 12 October 2017 Cabinet approved the criteria for developing the 2017/18 Cycling Safety programme. A proposed programme developed in line with the approved criteria is detailed at Appendix 'B'. All schemes in the proposed programme demonstrate a rate of return greater than 50%, which is a measure of the likely casualty savings resulting from a scheme during its first year of operation compared to the scheme cost. A rate of return greater than 50% is considered to offer a good rate of return.
Proposed 2017/18 National Productivity Investment Fund (NPIF) Programme
The Chancellor of the Exchequer's 2016 Autumn Statement announced a new National Productivity Investment Fund (NPIF) to provide £23 billion of additional spending in areas that are key to boosting productivity: transport, digital communications, research and development (R&D) and housing.
In January 2017, the Department for Transport (DfT) confirmed that the county council would receive a direct grant award of £4.655 million in 2017/18 from a national allocation of £185 million, to fund local highway and transport improvements that aim to reduce congestion at key locations, upgrade or improve maintenance of local highway assets, improve access to employment and housing or develop economic and job creation opportunities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.