That Planning Permission be granted, subject to the following conditions, as set out in the case officer’s report, with an amendment to condition no. 13: 1. Development within three years. 2. Development in accordance with the approved plans. 3. Time limited to 25 years following commercial generation. 4. Notification of date of commencement. 5. Decommissioning Plan. 6. 6 month period if the scheme fails to generate to be removed. 7. Construction Traffic Management Plan. 8. Construction Environmental Management Plan. 9 Ecological Management Plan submission. 10. Geophysical Survey, WSI and implementation of archaeological work. 11. Scheme for access point construction. 12. Protection of visibility splays. 13. Building Materials/Finishes (Substation, CCTV Columns, Fencing and Gate). 14. Cabling to be underground and inverters to be string inverters. 15. Drainage Scheme. 16. Surface water/pollution prevention. 17. AMS/AIA submission. And, subject to the following additional conditions (suitably worded): 18. Development must accord with the Glint and Glare technical Assessment and anti-glare finish to be provided and maintained. 19. Landscaping scheme and maintenance.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Land South Of Installation of arrays of 2.5m high PV panels, Cinderbarrow Lane underground cabling, substation /control room, 1.9m Lancaster high security fencing, 4m high CCTV masts and Lancashire construction of an access point and internal roads to form a solar farm.
Name of Applicant Name of Agent
[name removed]
Decision Target Date Reason For Delay
25 December 2015 Awaiting Further Information / Re-consultation (Time extension agreed until 18th January 2016)
Case Officer [name removed] No
Approval Summary of Recommendation
(i) Procedural Note
A site visit was arranged for Elected Members and undertaken on 9th November 2015. There was a subsequent delay in the report being drafted due to the need for amended documents, and to overcome concerns in relation to Nature Conservation, Landscape and Visual Matters and also Highways. The above issues have now been resolved as this report acknowledges, and therefore the application comes before Committee for determination.
1.0The Site and its Surroundings
1.1The application site is located circa 1.7 km to the south of Burton-in-Kendal, with Yealand Conyers located 1.5 km to the west of the site, and Priest Hutton circa 1.2 km to the south-east. The application site essentially consists of two fields. The northern most field is used for crop growing, whereas the southern field is used for grazing livestock, with the application boundary of the site being circa 10 hectares. The site is bound by existing mature hedgerows to the north (along Cinderbarrow Lane) and down approximately 70% of the eastern boundary. The southern boundary of the site is then bound by hedgerow. The western boundary is largely open, however there are interspersed areas of tree and hedgerow planting. Both of the fields slope gently upwards in an easterly direction from the lowest point of the site on the western edge at approximately 46m above Ordnance Datum (AOD) to approximately 56m AOD on the eastern most edge of the site.
1.2Cinderbarrow Lane is located directly to the north, which also serves as the sites means of access beyond this are agricultural fields as there are to the southern and eastern boundaries. The Lancaster Canal directly abuts the application site with the towpath beyond the canal. The M6 motorway is located 50 metres away to the west. The nearest residential property to the proposed development is located approximately 260 metres to the south east of the site.
1.3The site is allocated in the adopted Local Plan as Countryside Land and Cinderbarrow Lane is on the Northern Loop cycle route (Regional Cycle Route 90) which is immediately to the north of the site. The site is within a mineral safeguarded zone and at potential risk from radon. The site is not within a protected landscape although it is circa 800 metres (at its closest point to the boundary) to the Arnside and Silverdale Area of Outstanding Natural Beauty. The site is not within any statutory designation for ecology however lies immediately adjacent to the Lancaster Canal which is a County Biological Heritage site.
2.0The Proposal
2.1The proposed development is for the installation of a solar farm with an installed capacity of 4.99 MW. Amended plans were received in December 2015 with an amended layout, with the panels being orientated to the south east together with changes to the on-site layout, amendments to the landscaping arrangements and confirmation regarding the panel heights.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.