Resolved unanimously: That the updates be approved and the report commended to the Budget & Performance Panel. Officer responsible for effecting the decision: Director of Corporate Services Reasons for making the decision: Performance, project and resource monitoring provides a link between the Council Plan and operational achievement by providing regular updates on the impact of operational initiatives against strategic aims.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Delivering Our Ambitions: Performance, Projects and Resources Q1 2019-20 3 September 2019
Report of Director of Corporate Services PURPOSE OF REPORT
To provide members with an update on performance, projects and resources during the first quarter of 2019-20 (April-June 2019).
Key Decision Non-Key Decision Referral from Cabinet X Member This report is public.
RECOMMENDATIONS OF COUNCILLOR ANNE WHITEHEAD
(1) That Cabinet consider the update on performance, projects and resources for quarter 1, 2019-20.
1.0Introduction 1.1 This report and appendices represents the initial step in aligning performance, project and resource information into an integrated format, to provide members with a comprehensive view of progress against the council’s agreed priorities.
2.0Performance Scorecard 2.1 Appendix A contains an update on performance against key success measures.
2.2As Cabinet and the council’s priorities continue to develop, success measures will be updated accordingly to align with the priorities.
3.0Project Update 3.1 Appendix B contains corporate project reporting information. Updates in this document primarily cover the Q1 time period. However, where projects are giving monthly updates, the most recent report (in this case from July) is included, to ensure that the information presented is as up-to-date as possible. Columns showing the reporting frequency for each project and the date on which the update was written are included, so the age of each update can easily be seen. 3.2 Each project can report one of the following statuses:
a. Red – Used when the project encounters significant issues and requires corrective action to meet its business objectives.
b. Amber – Used when the project encounters problems which have a negative effect on project performance. Typically these can be resolved at project lead level.
c. Green – Used when the project is on track against the plan and progressing well.
d. Not Started – Where the project is identified and planned for as a corporate project, but is yet to complete the ‘Start-up’ stage
e. On Hold – Used when for reasons outside of the control of the project lead, the project is stalled pending action elsewhere. For example, when the project is dependent on an external decision or the outcome of another project
f. Complete – When the project is complete and is going through the project closure process. Once project closure is signed off it will be removed from the list of corporate projects reported on.
g. No data available – Used when the project lead has not been able to supply an update
3.3When a project reports a status other than ‘Green’, brief notes will be added to the Comments and Issues section of the report to explain further.
4.0Financial Monitoring
4.1Appendices C and D provide information on the overall revenue financial position of the Council, highlighting any significant issues and variations in the first quarter of the financial year. In an attempt to aid understanding Members should note that where projected variances values are presented with brackets ( ) this reflects a negative, or adverse movement from the budgeted position. Conversely, projected variances accompanied with a + sign represents a positive, or favourable movement from the budgeted position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.