Resolved unanimously : (1) That the update on performance, projects and resources for Quarter 1 2023/24 be noted. Reasons for making the decision: Performance, project and resource monitoring provides a link between the Council Plan and operational achievement by providing regular updates on the impact of operational initiatives against strategic aims.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Delivering Our Priorities: Q1 2023/24 12 September 2023
Report of Chief Executive & s151 Officer PURPOSE OF REPORT
To provide members with an update on performance, projects, and resources during the first quarter of 2023/24 (April – June 2023).
Key Decision Non-Key Decision Referral from Cabinet N Member Date of notice of forthcoming N/A key decision This report is public
RECOMMENDATIONS OF COUNCILLOR HAMILTON-COX
That Cabinet (1) Consider the update on performance, projects, and resources for Quarter 1 2023/24.
1.0INTRODUCTION
1.1The primary purpose of this report is to present information relating to the council’s projects, performance and resources for the period April-June 2023, which can be found within the appendices.
2.0PERFORMANCE REPORTING
2.1The highlight report at Appendix A provides a broadly consistent set of information across 2022-23 and Q1 2023-24.
2.2Gas KWH usage in council buildings has reduced significantly. This has been attributed to Improvements in data collection combined with energy saving measures.
2.3The measure which was “Average number of days’ sickness per full-time employee” has been replaced with “Average number of days’ sickness per full-time equivalent” to give a truer picture of absence rates as all employees are now included.
3.0PROJECT REPORTING
3.1The highlight report shows the majority of the council’s Strategic Projects are progressing as planned at the end of Quarter 1 2023-24.
3.2Three projects are reporting as Amber: Heritage Action Project and Outcomes Based Resourcing due to delays encountered Fair Work Charter due to lack of buy in from businesses and resource issues 3.3 The District Heat Network Feasibility study has now concluded.
4.0FINANCIAL MONITORING
4.1The 2023/24 Budget and Medium-Term Financial Strategy (MTFS) 2022-2026 approved by Council in February 2023 set a balanced budget for the year based on the assumptions made at that time.
4.2All portfolios are required to examine their revenue budgets and meet with their budget holders regularly and reports are submitted to Cabinet and Budget & Performance Panel for review. To enable Portfolio Holders to meet this requirement, Financial Services continually reviews and refreshes how it presents the Council’s corporate monitoring information, with the Quarter 1 information distributed to Cabinet in August 2023.
4.3In an attempt to aid understanding Members should note that where projected variances values are presented with brackets ( ) this reflects a negative, or adverse movement from the budgeted position. Conversely, projected variances accompanied with a + sign represents a positive, or favourable movement from the budgeted position. The following financial appendices accompany the financial monitoring section of this report
Appendix B: General Fund Service Analysis Appendix C: General Fund Subjective Analysis Appendix D: HRA Service Analysis Appendix E: General Fund Capital Projects Appendix F: HRA Capital Projects Appendix G: Reserves Projected Outturn Appendix H: Approved Savings Monitoring Appendix I: Service Analysis
4.4It should also be noted that projected outturn figures are monitored against the working budget and not the original budget within this report. The working budget includes approved virements and in-year budget adjustments. This alleviates a number of variances surrounding items such as ‘grossing-up’ of grant income/expenditure and movement of employees to different costs centres which is especially needed in these times of service restructuring. It provides a more accurate up-to date forecast and eliminates the need for duplicate reporting at service and subjective levels.
5.0COST OF LIVING / ENERGY PRICE CRISIS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.