Resolved unanimously: (1) That the report be noted. Reasons for making the decision: Performance, project and resource monitoring provides a link between the Council Plan and operational achievement by providing regular updates on the impact of operational initiatives against strategic aims.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Delivering Our Priorities: Q2 2023/24 5 December 2023
Report of Chief Executive & s151 Officer PURPOSE OF REPORT
To provide members with an update on performance, projects, and resources during the first two quarters of 2023/24 (April – September 2023).
Key Decision Non-Key Decision Referral from Cabinet N Member Date of notice of forthcoming N/A key decision This report is public
RECOMMENDATIONS OF COUNCILLOR HAMILTON-COX
That Cabinet (1) Consider the update on performance, projects, and resources for Quarter 2 2023/24.
1.0INTRODUCTION
1.1The primary purpose of this report is to present information relating to the council’s projects, performance and resources for the period April-September 2023, which can be found within the appendices.
2.0PERFORMANCE REPORTING
2.1The highlight report at Appendix A provides a broadly consistent set of information across Q2 – Q4 2022-23 and Q1 and Q2 2023-24.
2.2Direction of travel indicators are now included against each performance measure to show if the KPI has improved, is broadly the same or has worsened. The typical definition of ‘broadly the same’ is within 3% variation on the comparative quarter. Most indicators compare to the previous quarter, those marked with an asterisk compare to the like quarter from the previous year.
2.3The direction of travel indicators show that 4 KPIs have improved, 11 are broadly the same and 3 have worsened.
2.4The definition of the three measures shown in the ‘A Sustainable District’ section that are used to show energy usage have changed their definition.
The measure used to include the 4 main council office buildings and now include all 51 of the council assets classified as corporate. The data shown for all quarters on the report has been updated to reflect the changes. Therefore, the quarters included are comparable. 3.0 PROJECT REPORTING
3.1In order to provide a more accurate view of the progress for each project, the Red – Amber – Green status is now assigned for three elements of the project, these being Plan, Cost and Scope, instead of one status being applied across the whole project.
3.2Of the 11 projects where full update reports have been received, five are reporting ‘amber’ (minor) delays with their project plans (progress) and three have reported ‘amber’ (minor) deviations in the cost of the project. No projects are reporting concerns about their ability to deliver the planned scope (benefits). No projects have reported ‘red’ (significant) variations.
3.3The highlight report shows the majority of the council’s Strategic Projects are progressing as planned at the end of Quarter 2 2023-24.
3.4The South Lancaster Growth Catalyst project has been closed.
3.5The District Heat Network Feasibility project has now completed.
4.0FINANCIAL MONITORING
4.1The 2023/24 Budget and Medium-Term Financial Strategy (MTFS) 2022-2026 approved by Council in February 2023 set a balanced budget for the year based on the assumptions made at that time.
4.2All portfolios are required to examine their revenue budgets and meet with their budget holders regularly and reports are submitted to Cabinet and Budget & Performance Panel for review. To enable Portfolio Holders to meet this requirement, Financial Services continually reviews and refreshes how it presents the Council’s corporate monitoring information, with the Quarter 2 information distributed to Cabinet in November 2023.
4.3In an attempt to aid understanding Members should note that where projected variances values are presented with brackets ( ) this reflects a negative, or adverse movement from the budgeted position. Conversely, projected variances accompanied with a + sign represents a positive, or favourable movement from the budgeted position. The following financial appendices accompany the financial monitoring section of this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.