Resolved
Resolved that the recommendation be approved.
Cabinet 2010/21 approved this item on Friday 20 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved.
The former Church of St Luke is a grade II* listed building and has been included on the English Heritage Register of Buildings at Risk since the register’s initial publication in 1998. The interior suffered catastrophic incendiary bomb damage at the hands of the Luftwaffe which ‘blitzed’ Liverpool in 1941 leaving only the external masonry walls capable of salvage.
Whilst the building is of outstanding architectural value the asset remains in a generally poor state of repair and this report is primarily concerned with the need for repair and consolidation works to the historic fabric.
In recognising the historical and cultural importance of St Luke’s Church, The Mayor has agreed to undertake consultations to identify a long term, sustainable future for the Church. In conjunction with this consultation it is important to ensure that the fabric and structure of the Church does not further deteriorate.
The report seeks authority to accept a English Heritage grant totalling £74,591 in 2014/15 and for the City Council to contribute a further £75,409 in 2014/15 to be funded from the existing Buildings at Risk allocation. Background
The City Council has an interest in this property as freeholder of the land. The former church is a grade II* listed building and has been included on the English Heritage Register of Buildings at Risk since the register’s initial publication in 1998. The asset remains in a generally poor state of repair and this report is primarily concerned with the need for repair and consolidation works to the historic fabric.
The City Council has maintained freehold ownership of the property since its construction by the Liverpool Corporation in 1811 under the supervision of Corporation Surveyor and architect for the building, John Foster Senior. The Chancel with polygonal east end was added in 1822 to the design of his son John Foster Junior. The building is of outstanding architectural value.
The interior suffered catastrophic incendiary bomb damage at the hands of the Luftwaffe which ‘blitzed’ Liverpool in 1941 leaving only the external masonry walls capable of salvage. These survive to their full extent including the crenulated parapet and pinnacles as well as the splendid west tower. The disused building, although earmarked for demolition in the 1950s and 60s, came to be regarded as a war memorial to the civilian casualties sustained during the Second World War in Liverpool. Latterly the building has been used as a focus for community and public arts projects managed and superintended by local volunteers.
Ad hoc repairs and maintenance has been carried out by the City Council in recent years, however incremental deterioration and loss of historic fabric continues to occur at a steady rate.
Background to the St Luke’s Buildings at Risk project and its objectives
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Church of St Luke: Acceptance of English Heritage Grant & Council Buildings at Risk budget allocation for urgent repairs (RTC/22)Report | 7 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.