St Luke's Church, Accepting English Heritage Grant and allocating Liverpool Buildings at Risk Budget (RTC/34)

Decided Executive 2 papers

Cabinet 2010/21 decided this item on Friday 22 January 2016. Below is the council's own wording, with the papers it was decided on.

Item76a

Resolved

Should the grant application be successful the report seeks authority to accept a Historic England grant totalling £175,305 in 2015/16 and for the City Council to contribute a further £175,000 in 2016/17 from the Capital Programme in the form of additional funding applied to the Buildings at Risk allocation.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 1 pages

Question to the Cabinet Member – Regeneration, Transport & Climate Change

By Councillor Tom Crone

Question In relation to Agenda Item 4 (a) regarding St Luke’s Church, is it the case that bidders for the management contract for the site will be required to enter into a thirty year contract?

If so, why has this long term model been decided upon?

Can the proposed terms under which bids will be invited be published?

Answer The duration of the lease contract has not yet been decided. The proposed terms under which expressions of interest will be invited are in the process of being drafted. It is anticipated that the duration of the lease will be approximately 21 years.

This length of term reflects the need to strike an appropriate balance to enable the leaseholder to have sufficient duration of tenure to enable them to bid for grant funding to support their operation and maintenance costs, and to give the City Council appropriate certainty. The lease contract will include appropriate conditions and safeguards to protect the interests of the City Council.

Draft Heads of Terms for the lease will be included in the Expressions of Interests document which is due to be published during February 2016.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St Luke's Church: Question by Councillor Tom CroneReport 1 pages DownloadRead as text
PDF
St Luke's Church, Accepting English Heritage Grant and allocating Liverpool Buildings at Risk Budget (RTC/34)Report 8 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. St Luke's Church, Accepting English Heritage Grant and allocating Liverpool Buildings at Risk Budget (RTC/34)This decision
  2. St Luke’s (Bombed Out Church) – Selection of Leaseholder to Secure Future Operation & Renovation (RTC/55)Agreed
  3. Church of St Luke - Acceptance of English Heritage Grant & Council Buildings at Risk budget allocation for urgent repairs (RTC/22)Approved
  4. St Luke's Church - Proposals for Future Use (G/7)Approved

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies