Liverpool City Council
Executive Board, Friday 9 January 2004

St George's Hall Restoration (Phase 2)

Agreed Executive 1 paper

Executive Board agreed this item on Friday 9 January 2004. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

Resolved that – (i) the St George’s Hall Director be supported and authorised to submit applications to appropriate grant agencies including the Heritage Lottery Fund and ERDF in connection with the Phase 2 improvement works at St. George’s Hall; and (ii) the City Council agrees to make funding available in a sum not exceeding £200,000 in order to meet a proportion of the anticipated Phase 2 improvement costs of £2,000,000.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Executive summary

The current phase of restoration work at St.George’s Hall is now well advanced and it is scheduled for completion in September 2004. The overall project value of this phase of restoration works is £18,022, 464. The works are presently within budget though certain items have been placed “on hold” for implementation either at a later stage within this contract, or within a future phase of work.

Prior to commencing the present phase of works it was necessary to reduce the scope of the project in line with the then available grant monies, particularly in respect of funding from the Heritage Lottery Fund (HLF). The HLF are presently funding over 70% of the overall costs of the Project. Other funding is in place from the City Council, ERDF, SRB, World Monument Fund and others.

At the time of commencement of the Phase 1 works, the HLF indicated that they would support a further (Phase 2) bid for grant monies at the Hall on a similar match-funding basis. In particular, this would be in respect of Interpretation / Tourism, and Educational enhancements at the Hall.

The purpose of this report is to seek Members support in proceeding with the grant funding applications for the Phase 2 works. Match funding will be required from the Authority though this is not anticipated to exceed £200,000 of the likely Phase 2 project costs of £2,000.000.

Executive Member/Director recommendation (Councillors Warren Bradley and Chris Curry/Colin Hilton) That –

(i) the St George’s Hall Director be supported and authorised to submit applications to appropriate grant agencies including the Heritage Lottery Fund and ERDF in connection with the Phase 2 improvement works at St. George’s Hall; and

(ii) the City Council agrees to make funding available in a sum not exceeding £200,000 in order to meet a proportion of the anticipated Phase 2 improvement costs of £2,000,000. Key Decision?

Yes.

Forward Plan

No. – Appropriate Notices will be served under the Constitution.

Implementation effective from:

16 January 2004

Timescale for action:

Subject to Executive Board approval, applications for grant funding support to the Heritage Lottery Fund, ERDF and others will be completed and submitted by mid-January 2004.

Reason(s) for Recommendation:

When the project was approved by the HLF in March 2002, they recognised that further works particularly in connection with the provision of Education facilities and Interpretation facilities to support tourism were important for the project as a whole. At that stage though, the Consultants had not defined the precise nature of these essential facilities. This work has now been completed and a second application has been encouraged by the HLF. This is anticipated to be at the same rate of over 70% of the phase 1 project costs. In respect of the future operational arrangements, and provision of educational and visitor facilities at the Hall. The restoration of St George's Hall is a key action in the Tourism, Arts Heritage Service Plan.

Alternative options to be considered:

An alternative option would be to not undertake the proposed phase 2 works at the Hall at this time. However, this may mean that further HLF monies may not be available in a future year. Members will be aware that this is particularly important in view of the continued decreasing receipts for the National Lottery.

Consultation

The Chief Executive Officer and the St George's Hall Charitable Trust are supporting this application for a grant increase. Discussions have already been held with the HLF on both the timing and content of the application.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St George's Hall Restoration (Phase 2)Report 4 pages DownloadRead as text

At this meeting

Whole meeting
2Minutes of Last MeetingApproved 3Financial Review Report 2003/04 - Half YearNoted 4Land Ingoe Lane KirkbyDecided 5Stopgate Centre, Stopgate Lane, Aintree Industrial EstateDecided 655 Canning StreetDecided 7Merseyside Magistartes Court - Bids for Capital Funds 2003-05Approved 82 Leece Street (Hannah's Bar)Decided 9Land at Smithdown RoadDecided 10Part 2nd Floor, 111 Dale StreetApproved 11Major Repairs Allowance Planned Maintenance/Demolition Programme 2003/04Approved 12Citysafe CCTV ProjectApproved 13Strategic Acquisitions Funded by English PartnershipsAgreed 14Sefton Park Stock TransferApproved 15Family Accommodation Contract with National Asylum Support Service (NASS)Approved 16Best Value Review of Day ServicesApproved 17Liverpool Buisness Centre a Joint Venture ProposalApproved 18Sweeting Street Public Realm WorksDecided 19St Peters Church ERDF Project - Approval to Vary Capital ProgrammeDecided 20Transportation Capital Programme 2003/04Approved 21Rope Walks Action Plan - Public Realm Progress ReportApproved 22Neighbourhood Renewal Fund Year 4 ProgrammeApproved 23Consultation on the Community and Controlled Primary School and Community Secondary School Admission Policies for September 2005Decided 24Revised Policy concerning the Recognition of Long ServiceDecided 25Promoting Employment Opportunities for Liverpool Residents - Pilot SchemeDecided 26Premier Placements - Pool of Available StaffDecided 27Area Committee Chairs - Minutes of Meeting held on 5 December 2003On the agenda 28Overview and Scrutiny Select Committee - MInutes of Meeting held on 9 December 2003On the agenda 29Allocations Policy ReviewApproved
30St George's Hall Restoration (Phase 2)This decision
31Liverpool Football Club - Walton Area Committee - 8 December 2003Decided

On this subject at Liverpool

Search all
  1. St George's Hall Restoration (Phase 2)This decision
  2. St. George's Hall Annual ReviewAgreed
  3. St george's hall reportAgreed
  4. St George's Hall: Phase II Restoration Works (EH/20)Agreed
  5. Town Hall and St. Georges Hall Operational Management ReportAgreed
  6. St George's Hall - Phase II Restoration Works (EH/4)Agreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies