Resolved
Resolved that – (i) the contract sum be increased from £131,668 to £142,795 and that this expenditure be financed from the existing funding allocation; and (ii) authority be given to commit the expenditure
Executive Board decided this item on Friday 9 January 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that – (i) the contract sum be increased from £131,668 to £142,795 and that this expenditure be financed from the existing funding allocation; and (ii) authority be given to commit the expenditure
Increased financial authorisation of the contract sum is required on the Sweeting Street Public Realm Works Scheme, which forms part of the City Centre Movement Strategy.
Restoration work to the ironworks at the entrances to the site, which was not in the original contract, was requested to be included in the works, thus exceeding the authorised contract sum. However, this additional work was approved for additional SRB6 funding.
Therefore, although the funding is in place to meet all increased expenditure, financial authorisation needs to be given to increase the approved contract sum and commit the additional expenditure and meet the City Council’s contractual commitments.
There is no previous report relating to Sweeting Street as financial approval to the scheme was covered through the City Focus Year 2 Delivery Plan Report.
Executive Member/Director recommendation (Councillors Peter Millea, Chris Curry / Charlie Parker)
That: -
(i) the Sweeting Street Public Realm Works Contract Sum is increased from £131,668 to £142,795 and that this expenditure be financed from the existing funding allocation; and
(ii) authority be given to commit the expenditure
Key Decision
No Forward Plan N/A
Implementation effective from:
16 January 2004
Timescale for action Certificate payment to the contractor requires immediate payment to avoid delayed payment costs being incurred.
Reasons for Recommendation The City Council has a contractual obligation to meet payments to the contractor.
Alternative options to be considered Not applicable
Consultation Lynne Parry, Finance Officer, Regeneration Finance Graham Carswell, Principal Quantity Surveyor, 2o2o
The Final Contract Sum for the Main Contract is £142,795 with an original Contract Sum of £131,668. Approval is therefore required to increase the contract sum by £11,127.
This increase of £11,127 is to cover the additional ironworks that was included mid way through the contract period and can be contained within the existing budgets allocated to the project.
Best Value:
This work was based on current rates and is considered to be Best Value.
The scheme includes full provision for all users, with improved access. Corporate strategy:
The Sweeting Street Public Realm scheme furthers the corporate strategy to make Liverpool a premier European city, and is part of the City Centre Movement Strategy, part of the Local Transport Plan for Merseyside.
The restoration supports the City’s vision of a rich and protected architectural heritage and pride in Liverpool’s culture and heritage.
Budget and Policy Framework
The Sweeting Street Public Realm Scheme is a key element within the City Centre Movement Strategy Programme which is included within the Budget and Policy Framework of the City Council.
Community safety implications:
The restoration of the street, including the lighting, has led to safer public environment.
Report attached
No
Contract papers and files held in the Design Consultancy
Signature: ……………………………. Signature: ……………………………. (Executive Member) (Executive Director)
Date: …………………………………. Date: ………………………………….
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sweeting Street Public Realm WorksReport | 3 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.