Resolved
Resolved that the recommendation be approved.
Executive Board approved this item on Friday 9 January 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved.
The report advises members of the outcome of the Best Value Review of Day Services where new ways of providing such services are required in order to provide a modern, customer-centred service.
Executive Member/Director recommendation (Cllr Jeremy Chowings/Tony Hunter):
That:
(a) the recommendations for the future delivery of Day Services and the original Service Improvement Plan, be approved; and
(b) a progress report on the Service Improvement Plan be prepared and submitted to members by May 2004.
Key Decision?
Yes
Forward Plan:
Not included in the Forward Plan. Appropriate notices will be served.
Implementation effective from:
16 January 2004. Timescale for action:
The changes in this report are largely already being progressed to comply with changes in legislation and best practice.
1) To affirm Best Value Review Conclusions.
2) To improve service delivery.
3) To enable the City Council to respond appropriately to the expectations of the Social Services Inspectorate.
None appropriate.
As part of the Best Value Review, consultation was carried out with service users, carers, staff and other relevant stakeholders. Views of the various stakeholders are reflected in the report.
The report was considered by the Social Care and Health Select Committee on 29 May 2003 and in response to questions and comments made by Select Committee Members at subsequent meetings held in July and September 2003. The Select Committee noted the report and requested that the Liverpool Association for Disabled People to be consulted on future reviews of day services and to extend, where appropriate, the membership of the various task groups which had been established to modernise day services. The Select Committee comments and request are being incorporated into the Service Improvement Plan.
None arising from this recommendation in the short term. However it is anticipated the Service Improvement Plan process will lead to a more effective commissioning strategy for day services in 2004/5 and subsequent years.
Best Value:
The recommendation of the report will ensure Best Value is increasingly demonstrated and achieved within Day Services. Equality implications:
The Service Improvement Plan includes recommendations on improving fairer access to day care services for people from all communities within the City.
Corporate strategy:
The Report is consistent with the corporate strategy to improve services for customers through developing Day Services which promote independence and enable customers to access the full range of services available to citizens of the City.
Budget and Policy Framework:
The recommendations are in line with the Budget and Policy framework.
Community safety implications:
None arising directly from this report.
Report attached:
Best Value Review Report and Service Improvement Plan
Signature: ………………………… Signature:……………………………. (Executive Member) (Executive Director)
Date: ………………………………… Date: …………………………………. Best Value final report: Day care services
1. Setting the scene
Day care services are a range of services for adults with learning and physical disabilities, older people and those with mental health needs. The service is provided at council-run day centres and centres operated by the independent sector. The aim as described in the service procedural manual is to: ‘help to maintain the increasingly large number of vulnerable people in the community by meeting their physical, psychological and social needs, and offering support and respite to relatives and friends who act as informal carers’.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Best Value Review of Day ServicesReport | 31 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.