Executive Board, Friday 19 March 2004

Littlewoods Home Shopping HQ: Approval to act as accountable body for Objective 1 ERDF Grant for Hangar 2 and Plot F at the Former Speke Airport Site (REG/82)

Decided Executive 1 paper

Executive Board decided this item on Friday 19 March 2004. Below is the council's own wording, with the papers it was decided on.

Item121

Resolved

Resolved that – (i) Liverpool City Council acts as Accountable Body for Objective 1 funding in respect of the project at hangar 2 the Aerodrome, Littlewoods Home Shopping HQ; and (ii) on the receipt of offer letters from the Government Office North West - · authority be granted for the Executive Director (Regeneration) to accept capital grant of up to £3,448,325 phased over the financial years 2004/5 to 2005/6 to contribute towards the cost of delivering the scheme; · the Divisional Manager (Regeneration Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; · the City Council’s capital programme be adjusted, to reflect expenditure on these projects for a sum up to £3,448,325 phased over the financial years 2004/5 (£2,486,827), 2005/6 (£961,498); and · expenditure be committed to the project namely Littlewoods HQ, after the confirmation of funding from all the relevant organisations/ bodies upon which this project relies and the finalisation of all other relevant documents .
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

The project consists of two elements. Firstly, the be-spoke redevelopment of the Hangar 2 building (Grade 2 * listed) on the old Speke Airport site. This will produce 120,000 square feet of accommodation. The second element is a new building adjacent to the hangar which will provide 70,000 square feet.

The need for the project arises from the disposal of the Littlewoods building on Old Hall Street by Barclay Brothers who are the new owners of Littlewoods, and the consequent relocation of the staff and functions from that building. Littlewoods has been split into 3 separate companies; High Street Retail, Home Shopping and Finance

The buildings will house the home shopping company employing almost 1,200 people. The bulk of these employees have skills which it is important to retain on Merseyside. It is not known where the retail and finance operations will be based but it is likely that they will be outside Merseyside

The project has the support of Liverpool Land Development Company and the Speke Halewood SIA has endorsed the use of its ERDF allocation at its meeting Deleted: ’ on 19 January 2004. Deleted: ’

GONW will not accept the new owners of Littlewoods as applicants for Objective 1 Funding as they have no track record in delivering projects. The NWDA do not act as accountable body for ERDF projects which realistically leaves only the City Council to fulfil that role.

If the ERDF funding cannot be secured, there is a danger that the Home Shopping Company will re-locate outside the sub-region. If the City Council acts as accountable body, this should secure ERDF funding and ensure the project goes ahead retaining the jobs on Merseyside. If LCC acts as accountable body, it is important to protect the City Council’s financial position. To achieve this, we need to ensure the correct level of local project management. As a project being promoted by the Liverpool Land Development Company, one of their staff will need to act as project officer. In addition, LCC should only act as accountable body if the developers sign a Service Level Agreement with LCC and demonstrate their ability to meet any claw-back liabilities which may arise. The SLA will transfer the obligations of the ERDF offer letter onto the developer

Executive Member/Director recommendation: Councillors Peter Millea and Chris Curry/Charlie Parker

That: -

(i) Liverpool City Council acts as Accountable Body for Objective 1 funding in respect of the project at hangar 2 the Aerodrome, Littlewoods Home Shopping HQ; and

(ii) on the receipt of offer letters from the Government Office North West:

• authority be given to the Executive Director for Regeneration to accept capital grant of up to £ 3,448,325 phased over the financial years 2004/5 to 2005/6 to contribute towards the cost of delivering the scheme;

• The Divisional Manager for Regeneration Programmes is appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises;

• The City Council’s capital programme be adjusted, to reflect expenditure on these projects for a sum up to £3,448,325 phased over the financial years 2004/5 (£2,486,827), 2005/6 (£961,498);and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Littlewoods Home Shopping HQ: Approval to act as accountable body for Objective 1 ERDF Grant for Hangar 2 and Plot F at the Former Speke Airport Site (REG/82)Report 6 pages DownloadRead as text

At this meeting

Whole meeting
107Minutes of the Last MeetingApproved 108Land at Southbrook Way (RES/98)Decided 109Land at Breeze Close (RES/99)Agreed 1102/12 Muirhead Avenue and 669/679 West Derby Road (RES/101)Agreed 111Access Liverpool, Disposal of Long Term Vacants, Contract 5 (RES/102)Agreed 112Land at Linbridge Road, Site 3 and Site 4 (RES/103)Agreed 113Land Parkhill Road (RES/104)Decided 114Land Cuckoo Lane (RES/105)Decided 115IT Data Centre - Lower Ground Floor, Basement and Sub-Basement, India Buildings, Water Street (RES/106)Approved 116Art Project, Menlove Avenue (RES/107)Decided 117Authority to Amend Delegated Powers Contained within the Constitution (HSG/44)Approved 118Stock Options Appraisal for Liverpool City Council Housing (HSG/45)Noted 119Speke Garston Business Unit - Project Exetension (REG/78)Approved 120Scandinavia Hotel, 2-8 Nelson Street and premises 8a Nelson Street - Compulsory Purchase Order (REG/81)Agreed
121Littlewoods Home Shopping HQ: Approval to act as accountable body for Objective 1 ERDF Grant for Hangar 2 and Plot F at the Former Speke Airport Site (REG/82)This decision
122The Matchworks Phase 2 - Approval to act as accountable body for Objective 1 ERDF Grant the former Bryant and May Match Works Factory (REG/83)Decided 123Merseytram Supplemmentary Planning Guidance - Final Version (REG/84)Noted 124Education, Library and Sports - Education Capital Programme (LL/56)Decided 125Disposal of Former Queen Mary High School Site (LL/58)Decided 126Results of Consultations on a Proposal to Discontinue Cross Farm Community Primary School (LL/62)Agreed 127Smoke Free LiverpoolApproved 128Strategic Acquisitions - English Partnerships (HSG/46)Approved 129150-152 London Road (RES/116)Decided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies