Merseytram Supplemmentary Planning Guidance - Final Version (REG/84)

Noted Executive 4 papers

Executive Board noted this item on Friday 19 March 2004. Below is the council's own wording, with the papers it was decided on.

Item123

Resolved

Resolved that it be recommended to an Extraordinary Meeting of the City Council to be held at 6.00pm on Wednesday 7 April t hat – (i) the consultation responses received to the draft SPG and the proposed changes that have been recommended by the Divisional Manager (Planning and Public Protection), be noted; and (ii) the Council formally adopt the Supplementary Planning Guidance for Merseytram in the form contained within Appendix 2 submitted and that notice of adoption be published in a local newspaper and sent to all consultees .
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 19 pages

Executive summary

1. Following a public consultation period, amendments have been made to the Draft Supplementary Planning Guidance for Merseytram, approved by the City Council for consultation purposes on 15th October 2003.

2. Line 1 runs from Kings Waterfront via the Strand to a twin-track loop running via Canning Place, Paradise Street, Whitechapel, Dale Street, Water Street, the Pier Head and Mann Island. A smaller loop links Old Haymarket, William Brown Street, Lime Street and St. John’s Lane. From Lime Street, the route runs along London Road and Prescot Street, Brunswick Road, West Derby Road, Rocky Lane and Muirhead Avenue. It then goes along Queens Drive to Townsend Avenue and Utting Avenue East, on along Storrington Avenue and Stonebridge Lane to the East Lancashire Road and the city boundary.

3. An application for an Order has been made pursuant to Section 2 of the Transport and Works Act 1992 for power to facilitate the construction and subsequent operation of Merseytram and this was submitted to the Secretary of State for Transport on 16 October 2003. Objections to the application for the Order are due to be considered at a public inquiry which is scheduled to commence on 20 April 2004. The inquiry will be concurrent with an inquiry into objections to the associated applications for Listed Building Consent and Conservation Area Consent.

4. Assuming that there are no unforeseen intervening events, the Inspectors are expected to report by the end of this year and decisions as to whether or not to make the Order and grant the Listed Building and Conservation Area Consents are likely to be issued early next year. 5. Copies of the Draft Supplementary Planning Guidance (SPG) were sent to 152 national, regional and local organisations, and presented to all 7 Area Committees affected by the route of Line 1. All City Councillors received a copy. An advertisement was placed in the Liverpool Echo on 20th November 2003 inviting public views on the SPG, and a relevant entry was placed on the Liverpool City Council Web Site.

6. In total 36 responses were received, some triggered by the TWAO notices, by 14th January 2004. There were no objections made by the public or the Area Committees to the general route of Line 1, but understandable concern expressed about potential loss of trees, road capacity and accessibility to premises. English Heritage, CABE and LUDCAP expressed cautious support, subject to a review of detailed design.

7. A table summarising the objections is enclosed at Appendix 1. The majority of comments related to detailed matters which will be considered at the forthcoming inquiry. The SPG is intended to provide the general overriding policy framework for promotion of Merseytram. It has always been envisaged that the details would be addressed as part of the overall consideration of the application for the Order and the associated applications for Section 90(2A) Planning Direction, Listed Building Consents and Conservation Area Consents. Consequently only minor amendments to the original draft SPG are proposed, together with amendments to reflect changes in national planning procedures

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Merseytram Supplemmentary Planning Guidance: Final Version (REG/84)Report 19 pages DownloadRead as text
PDF
REG 84 Merseytram SPG Map 1Plan 1 pages Download
PDF
REG 84 Merseytram SPG Map 2Plan 1 pages Download
PDF
REG 84 Merseytram SPG Map 3Plan 1 pages Download

At this meeting

Whole meeting
107Minutes of the Last MeetingApproved 108Land at Southbrook Way (RES/98)Decided 109Land at Breeze Close (RES/99)Agreed 1102/12 Muirhead Avenue and 669/679 West Derby Road (RES/101)Agreed 111Access Liverpool, Disposal of Long Term Vacants, Contract 5 (RES/102)Agreed 112Land at Linbridge Road, Site 3 and Site 4 (RES/103)Agreed 113Land Parkhill Road (RES/104)Decided 114Land Cuckoo Lane (RES/105)Decided 115IT Data Centre - Lower Ground Floor, Basement and Sub-Basement, India Buildings, Water Street (RES/106)Approved 116Art Project, Menlove Avenue (RES/107)Decided 117Authority to Amend Delegated Powers Contained within the Constitution (HSG/44)Approved 118Stock Options Appraisal for Liverpool City Council Housing (HSG/45)Noted 119Speke Garston Business Unit - Project Exetension (REG/78)Approved 120Scandinavia Hotel, 2-8 Nelson Street and premises 8a Nelson Street - Compulsory Purchase Order (REG/81)Agreed 121Littlewoods Home Shopping HQ: Approval to act as accountable body for Objective 1 ERDF Grant for Hangar 2 and Plot F at the Former Speke Airport Site (REG/82)Decided 122The Matchworks Phase 2 - Approval to act as accountable body for Objective 1 ERDF Grant the former Bryant and May Match Works Factory (REG/83)Decided
123Merseytram Supplemmentary Planning Guidance - Final Version (REG/84)This decision
124Education, Library and Sports - Education Capital Programme (LL/56)Decided 125Disposal of Former Queen Mary High School Site (LL/58)Decided 126Results of Consultations on a Proposal to Discontinue Cross Farm Community Primary School (LL/62)Agreed 127Smoke Free LiverpoolApproved 128Strategic Acquisitions - English Partnerships (HSG/46)Approved 129150-152 London Road (RES/116)Decided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies