Resolved that subject to consultation with the Asset Management Group - (i) the balance of the Standards Fund Capital Grant 614 of £139,000 be set against the financing of the project at Phoenix Primary School (BEEPH36). General resources freed up as a result be set against the overspend on the Education Capital Programme; (ii) the remaining overspend of £57,000 be financed from slippage identified against the project at Stockton Wood Primary School and a contribution of £57,000 be made from the Modernisation Fund (all schools) for 2004/05 to the funding of the project.; and (iii) a budget of £115,000 be established from a CERA contribution from Education revenue budgets in 2003/04 to fund emergency refurbishment works at Lower Lee.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
CITYWIDE STATUS – PUBLIC LL/56 Portfolios: Education and Lifelong Executive Members: Learning / Resources Cllr Paul Clein / Cllr Chris Curry Date of submission: Subject: Education, Library and Sports – 27 February 2004 Education Capital Programme
Executive summary: The purpose of the report is to:
1. advise on the current overspend within the Education capital Programme and seek approval to the proposed financing of the overspend
2. seek authority for a budget of £115,000 to be established from a CERA contribution from Education revenue budgets in 2003/04 to fund emergency refurbishment works at Lower Lee.
Financial Summary 2003/04 Programme Throughout 2003/04 because of ongoing commitments to support a substantial school’s capital programme it has been necessary to restrict the number of new projects commissioned to essential schemes either of an urgent health and safety nature, or further phases of works to complete existing projects where it would not be practical or feasible for operational reasons to stop. It has also been necessary to allocate significant funds as identified in two previous capital reports DE/086/03 and DE/100/03 to overspends on projects within the current programme. The third quarter financial forecast as at the end of November 2003 identifies a net overspend on the Education Capital Programme of £250,000. This has now been revised. Net savings of £54,000 have been identified and the balance of the Standards Fund Capital Grant 614 of £139,000 has been set against Phoenix Primary School (BEEPH36). The grant is aimed at improving access to early education for 3-4 year olds and the project at Phoenix involves adaptations and extensions to the school to accommodate children from Acorn Nursery. The grant can be matched against the current financing in the project and will enable an equivalent amount in general resources to be freed up to be set against the overspend. This reduces the net overspend to £57,000 and it is recommended that: • the remaining overspend of £57,000 be financed from slippage identified against the project at Stockton Wood Primary School, with a contribution of £57,000 being made from the Modernisation Fund (all schools) for 2004/05 to fund the slippage Lower Lee School An inspection by the National Care Standards Commission towards the end of 2003 raised serious concerns about the condition of the residential accommodation at the school with the threat of action unless immediate remedial works were undertaken. 20:20 Liverpool have surveyed the property and produced an agreed scheme of refurbishment with a total cost estimate of £100,000 plus fees. Authority is therefore sought to establish a budget of £115,000 in the Capital Programme funded from a CERA contribution from within Education revenue budgets for 2003/04 to finance the project at Lower Lee.
Executive Director recommendation: Colin Hilton recommends that, subject to consultation with the Asset Management Group:
1. The balance of the Standards Fund Capital Grant 614 of £139,000 be set against the financing of the project at Phoenix Primary School (BEEPH36). General resources freed up as a result be set against the overspend on the Education Capital Programme 2. the remaining overspend of £57,000 be financed from slippage identified against the project at Stockton Wood Primary School and a contribution of £57,000 be made from the Modernisation Fund (all schools) for 2004/05 to the funding of the project. 3. A budget of £115,000 be established from a CERA contribution from Education revenue budgets in 2003/04 to fund emergency refurbishment works at Lower Lee.
Key Decision: Yes
Forward Plan: No – appropriate Notice will be served under the Constitution
Implementation effective from: 26 March 2004
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.