Education, Library and Sports - Education Capital Programme (LL/56)

Decided Executive 1 paper

Executive Board decided this item on Friday 19 March 2004. Below is the council's own wording, with the papers it was decided on.

Item124

Resolved

Resolved that subject to consultation with the Asset Management Group - (i) the balance of the Standards Fund Capital Grant 614 of £139,000 be set against the financing of the project at Phoenix Primary School (BEEPH36). General resources freed up as a result be set against the overspend on the Education Capital Programme; (ii) the remaining overspend of £57,000 be financed from slippage identified against the project at Stockton Wood Primary School and a contribution of £57,000 be made from the Modernisation Fund (all schools) for 2004/05 to the funding of the project.; and (iii) a budget of £115,000 be established from a CERA contribution from Education revenue budgets in 2003/04 to fund emergency refurbishment works at Lower Lee.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

CITYWIDE STATUS – PUBLIC LL/56 Portfolios: Education and Lifelong Executive Members: Learning / Resources Cllr Paul Clein / Cllr Chris Curry Date of submission: Subject: Education, Library and Sports – 27 February 2004 Education Capital Programme

Report No. DE/11/04 Contact officer: Rob Gilland Background papers: None Ext: 233 2703

Executive summary: The purpose of the report is to:

1. advise on the current overspend within the Education capital Programme and seek approval to the proposed financing of the overspend

2. seek authority for a budget of £115,000 to be established from a CERA contribution from Education revenue budgets in 2003/04 to fund emergency refurbishment works at Lower Lee.

Financial Summary 2003/04 Programme Throughout 2003/04 because of ongoing commitments to support a substantial school’s capital programme it has been necessary to restrict the number of new projects commissioned to essential schemes either of an urgent health and safety nature, or further phases of works to complete existing projects where it would not be practical or feasible for operational reasons to stop. It has also been necessary to allocate significant funds as identified in two previous capital reports DE/086/03 and DE/100/03 to overspends on projects within the current programme. The third quarter financial forecast as at the end of November 2003 identifies a net overspend on the Education Capital Programme of £250,000. This has now been revised. Net savings of £54,000 have been identified and the balance of the Standards Fund Capital Grant 614 of £139,000 has been set against Phoenix Primary School (BEEPH36). The grant is aimed at improving access to early education for 3-4 year olds and the project at Phoenix involves adaptations and extensions to the school to accommodate children from Acorn Nursery. The grant can be matched against the current financing in the project and will enable an equivalent amount in general resources to be freed up to be set against the overspend. This reduces the net overspend to £57,000 and it is recommended that: • the remaining overspend of £57,000 be financed from slippage identified against the project at Stockton Wood Primary School, with a contribution of £57,000 being made from the Modernisation Fund (all schools) for 2004/05 to fund the slippage Lower Lee School An inspection by the National Care Standards Commission towards the end of 2003 raised serious concerns about the condition of the residential accommodation at the school with the threat of action unless immediate remedial works were undertaken. 20:20 Liverpool have surveyed the property and produced an agreed scheme of refurbishment with a total cost estimate of £100,000 plus fees. Authority is therefore sought to establish a budget of £115,000 in the Capital Programme funded from a CERA contribution from within Education revenue budgets for 2003/04 to finance the project at Lower Lee.

Executive Director recommendation: Colin Hilton recommends that, subject to consultation with the Asset Management Group:

1. The balance of the Standards Fund Capital Grant 614 of £139,000 be set against the financing of the project at Phoenix Primary School (BEEPH36). General resources freed up as a result be set against the overspend on the Education Capital Programme 2. the remaining overspend of £57,000 be financed from slippage identified against the project at Stockton Wood Primary School and a contribution of £57,000 be made from the Modernisation Fund (all schools) for 2004/05 to the funding of the project. 3. A budget of £115,000 be established from a CERA contribution from Education revenue budgets in 2003/04 to fund emergency refurbishment works at Lower Lee.

Key Decision: Yes

Forward Plan: No – appropriate Notice will be served under the Constitution

Implementation effective from: 26 March 2004

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Education, Library and Sports: Education Capital Programme (LL/56)Report 4 pages DownloadRead as text

At this meeting

Whole meeting
107Minutes of the Last MeetingApproved 108Land at Southbrook Way (RES/98)Decided 109Land at Breeze Close (RES/99)Agreed 1102/12 Muirhead Avenue and 669/679 West Derby Road (RES/101)Agreed 111Access Liverpool, Disposal of Long Term Vacants, Contract 5 (RES/102)Agreed 112Land at Linbridge Road, Site 3 and Site 4 (RES/103)Agreed 113Land Parkhill Road (RES/104)Decided 114Land Cuckoo Lane (RES/105)Decided 115IT Data Centre - Lower Ground Floor, Basement and Sub-Basement, India Buildings, Water Street (RES/106)Approved 116Art Project, Menlove Avenue (RES/107)Decided 117Authority to Amend Delegated Powers Contained within the Constitution (HSG/44)Approved 118Stock Options Appraisal for Liverpool City Council Housing (HSG/45)Noted 119Speke Garston Business Unit - Project Exetension (REG/78)Approved 120Scandinavia Hotel, 2-8 Nelson Street and premises 8a Nelson Street - Compulsory Purchase Order (REG/81)Agreed 121Littlewoods Home Shopping HQ: Approval to act as accountable body for Objective 1 ERDF Grant for Hangar 2 and Plot F at the Former Speke Airport Site (REG/82)Decided 122The Matchworks Phase 2 - Approval to act as accountable body for Objective 1 ERDF Grant the former Bryant and May Match Works Factory (REG/83)Decided 123Merseytram Supplemmentary Planning Guidance - Final Version (REG/84)Noted
124Education, Library and Sports - Education Capital Programme (LL/56)This decision
125Disposal of Former Queen Mary High School Site (LL/58)Decided 126Results of Consultations on a Proposal to Discontinue Cross Farm Community Primary School (LL/62)Agreed 127Smoke Free LiverpoolApproved 128Strategic Acquisitions - English Partnerships (HSG/46)Approved 129150-152 London Road (RES/116)Decided

On this subject at Liverpool

Search all
  1. Education, Library and Sports - Education Capital Programme (LL/56)This decision
  2. Education, Library and Sports Services - Comments, Compliments, ComplaintsAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies