Resolved
Resolved that this matter be referred for consideration to a meeting of the Executive Board to be held at 8.00am on Monday 29 March.
Executive Board decided this item on Friday 19 March 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that this matter be referred for consideration to a meeting of the Executive Board to be held at 8.00am on Monday 29 March.
The purpose of this report is to seek members views as to the most appropriate disposal arrangements for 150-152 London Road.
In January 2000 Members agreed to enter into a 12 month exclusivity agreement with the Big Issue in the North, a registered charity, to allow them to bring forward proposals for the re-development of 142-152 London Road in which to locate their new and expanded Liverpool Head Office.
The buildings are owned freehold by the City Council. Nos 142-148 were subject to the residue of a long leasehold interest. They were in a dilapidated condition and the City were pursuing their repossession. As the City were unable to extinguish the existing long leasehold interest on Nos 142-148 London Road. The Big Issue decided to concentrate on the refurbishment of Nos 150-152 alone.
A report (EDR/61/01) was submitted to the Resources Portfolio Executive Member meeting on Wednesday 14 February 2001 and it was resolved:
That
(1) Subject to the Big Issue in the North obtaining, within six months from the date of agreement:
(a) Planning permission; (b) Satisfactory funding; (c) City Council's consent for the scheme as landlord;
The City Council grant a 125 year lease of 150-152 London Road subject to the payment of a premium £45,000 (including fees). The lease will require the property to be refurbished in line with the approved plans within two years of grant of lease; and
(2) The City Council grant the Big Issue in the North a six month period of exclusivity from the date vacant possession is achieved on Nos 142- 148 London Road, enabling them to purchase a leasehold interest in the properties subject to the Big Issue obtaining planning consent, funding and approval for the scheme on terms to be agreed. A further report will be submitted to members for approval detailing the terms when agreed.
The proposal and the premium in respect of 150-152 London Road was at that time certified as best price.
A further report EDR/333/02 reviewing the position on the disposal was considered by the Executive Board on 4 October 2002.
It advised that whilst the Big Issue had obtained planning permission to refurbish 150-152 London Road for a head office to support their magazine sellers and the homeless by the provision of a training and medical resource, the funding position had not been fully resolved.
GONW had at that time been unable to complete the appraisal process as Big issue had not forwarded sufficient other funding information to support their bid for ERDF funding. However, other applications for funding were being progressed satisfactorily with other funding regimes.
At that time, the repossession of 142-148 London Road was secured and members requested officers to market the site.
It was resolved that:-
(i) The City Council confirms the grant of a 125 year lease of 150-152 London Road, Liverpool 3 to the Big Issue in the North, subject to:-
• obtaining ERDF funding and scheme approval from the Council as landlord within six months from the date of approval of this decision; and
• the payment of £45,000 (including fees) upon legal completion of the lease; and
(ii) the offer of a grant exclusivity to the Big Issue in the North in respect of 142-148 London Road, Liverpool 3, be rescinded, and these premises be offered for redevelopment on the open market.
Current Position
142-148 London Road were offered for sale by tender in June 2003 and the highest offer received of £251,000 plus fees and costs from J D Property Services Limited was recommended and accepted by the Executive Board at the meeting on 8 August 2003.
The proposed use is for refurbishment for four retail shops with apartments on the upper floor, this sale has now been completed and work has started on site.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
150-152 London Road (RES/116)Report | 7 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.