Proposed Deysbrook Training and Resource Centre (REG/71)

Decided Executive 1 paper

Executive Board decided this item on Friday 18 March 2005. Below is the council's own wording, with the papers it was decided on.

Item157i

Resolved

Resolved that – (i) in view of the practical difficulties facing the project, the consequent inability to spend the SRB grant in full and in accordance with the NWDA grant conditions and the serious doubts about its future sustainability , the proposed construction of the Deysbrook Training and Resource Centre should not proceed and the NWDA be informed accordingly; and (ii) in view of the continuing nuisance in the area, arrangements be made for the demolition of the existing shopping parade on Deysbrook Way as soon as it is vacant and the costs involved be financed from the existing capital resources allocated for the Deysbrook Training and Resource Centre.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 10 pages

Executive summary

INTRODUCTION

1. There have been considerable efforts over a number of years, particularly through the Liverpool East SRB Programme, to revitalise the Deysbrook area. The SRB Programme was originally approved in 1996 with its central theme of “Remaking the Neighbourhoods”. The Deysbrook Project was developed as a key part of that programme and sought to complement the investment in the new and existing residential areas with new local community facilities. This included the proposed Deysbrook Training and Resource Centre, which was intended both to replace the existing Community Centre (to be demolished as part of the redevelopment of the Deysbrook housing estate) and to provide enhanced and quality local facilities in an area of considerable need.

2. Since then, progress has been made in implementing the overall Deysbrook Project. The development of 104 new houses is underway at Deysbrook Way and a further 340 houses are being built on the former Barracks site. A new local shopping centre has recently been completed on Deysbrook Lane. In addition, Berrybridge Housing has a major investment programme for the former City Council housing stock in the area.

3.The proposed Deysbrook Training and Resource Centre was the remaining key project in the SRB programme but the development and implementation of the proposal has been beset with difficulties. The delays in securing both possession of the site and planning consent for the development of the shopping centre(to house some of the shopkeepers from the existing parade) meant that the project did not start in 2003/04 as intended in the approved SRB Delivery Plan for that year. Consequently, negotiations took place with the NWDA to extend the SRB Programme for a further year in order to implement the proposal. In June 2004, the NWDA agreed the Year 8 Delivery Plan to enable SRB grant to support the delivery of the project in 2004/05. 3. It is important to emphasise that, under the terms of the NWDA approval, the SRB grant of £245k must be fully spent by 31 March 2005. However the project has not yet started on site; the last remaining shop is still occupied and the demolition of the existing shopping parade cannot take place until that is vacated; and there are still a number of outstanding financial and practical issues (including the future viability of the proposed Centre) to be resolved. There would appear therefore to be little prospect of the SRB grant being spent in full by 31 March.

4. It should also be noted that the project now planned is substantially different from the original concept of a local neighbourhood centre predominantly used for local activities run by the local community.

5. This report outlines the background to the project and sets out the actions taken to progress the proposal and to resolve the outstanding issues. However the project is at a very critical stage and if it does not proceed, there are a number of financial and other implications for the City Council; these are set out.

Background

6. The central theme of the Liverpool East SRB Programme was “Remaking the Neighbourhoods”; this focused on reviving and strengthening the older shopping parades/neighbourhood centres to complement the investment in the surrounding residential areas.

7. A key element of that programme was the proposed Deysbrook Training and Resource Centre, which has been developed in conjunction with Liverpool Deysbrook Action Group (LDAG) with considerable local community consultation. LDAG comprises local community representatives and is now established as a new charitable company made up of local interested people, with the aim of developing and managing the proposed Centre.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Deysbrook Training and Resource Centre (REG/71)Report 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Proposed Deysbrook Training and Resource Centre (REG/71)This decision
  2. Proposed Deysbrook Training and Resource Centre (RT/9)Approved
  3. Called in Item - Proposed Deysbrook Training and Resource CentreAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies